ML022470082

From kanterella
Jump to navigation Jump to search

Withholding from Public Disclosure, Document Titled Pressure- Temperature Curves for Firstenergy Corporation, Using Klc Methodology, Perry Unit 1, Dated 04/02/2002
ML022470082
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 09/30/2002
From: Pickett D
NRC/NRR/DLPM/LPD3
To: Kanda W
FirstEnergy Nuclear Operating Co
Pickett D, NRR/DLPM, 415-1364
References
PY-CEI/NRR-2627L, TAC MB6061
Download: ML022470082 (4)


Text

September 30, 2002 Mr. William R. Kanda Vice President - Nuclear, Perry FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P.O. Box 97, A200 10 Center Road Perry, OH 44081

SUBJECT:

PERRY NUCLEAR POWER PLANT, UNIT NO. 1 - REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE (TAC NO. MB6061)

Dear Mr. Kanda:

By letter dated June 4, 2002, (PY-CEI/NRR-2627L), FirstEnergy submitted an affidavit dated April 2, 2002, executed by George B. Stramback and requested that the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 2.790:

Pressure-Temperature Curves for FirstEnergy Corporation, Using the Klc Methodology, Perry Unit 1," dated April 2, 2002.

A nonproprietary copy of this document has been placed in the Nuclear Regulatory Commission's (NRC's) Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room.

The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:

(4)a Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by General Electrics competitors without license from General Electric constitutes a competitive economic advantage over other companies; (4)b Information which, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product; We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.790 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

W. Kanda Therefore, the version(s) of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.790(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the document. If the need arises, we may send copies of this information to our consultants working in this area. We will, or course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You should also understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, I may be reached at 301-415-3154.

Sincerely,

/RA by Douglass V. Pickett for/

Stephen P. Sands, Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-440 cc: See next page

ML022470082 OFFICE PM:LPD3-2 LA:LPD3-2 BC:SRXB OGC SC:LPD3-2 NAME SSands THarris JWermiel MPSiemien AMendiola DATE 09/05/02 09/05/02 09/05/02 09/20/02 09/26/02 Perry Nuclear Power Plant, Unit 1 cc:

Mary E. OReilly Carol OClaire, Chief, Radiological Branch FirstEnergy Corporation Ohio Emergency Management Agency 76 South Main St. 2855 West Dublin Granville Road Akron, OH 44308 Columbus, OH 43235-7150 Resident Inspectors Office Mayor, Village of Perry U.S. Nuclear Regulatory Commission P.O. Box 100 P.O. Box 331 Perry, OH 44081-0100 Perry, OH 44081-0331 Dennis Clum Regional Administrator, Region III Radiological Assistance Section Supervisor U.S. Nuclear Regulatory Commission Bureau of Radiation Protection 801 Warrenville Road Ohio Department of Health Lisle, IL 60532-4531 P.O. Box 118 Columbus, OH 43266-0118 Sue Hiatt OCRE Interim Representative Zack. A. Clayton 8275 Munson DERR Mentor, OH 44060 Ohio Environmental Protection Agency ATTN: Mr. Zack A. Clayton Gregory A. Dunn P.O. Box 1049 Manager - Regulatory Affairs Columbus, OH 43266-0149 FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant Chairman P.O. Box 97, A210 Perry Township Board of Trustees Perry, OH 44081 3750 Center Road, Box 65 Perry, OH 44081 Timothy Rausch, Plant Manager FirstEnergy Nuclear Operating Company Daniel Z. Fisher Perry Nuclear Power Plant Transportation Department P.O. Box 97, SB306 Public Utilities Commission Perry, OH 44081 180 East Broad Street Columbus, OH 43215-3793 Mayor, Village of North Perry North Perry Village Hall 4778 Lockwood Road North Perry Village, OH 44081 Donna Owens, Director Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P. O. Box 4009 Reynoldsburg, OH 43068-9009