ML022410170

From kanterella
Jump to navigation Jump to search
Slides from 08/20/02 Meeting Re Independent Spent Fuel Storage Facility
ML022410170
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 08/20/2002
From:
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation
References
Download: ML022410170 (28)


Text

Sequoyah Nuclear Plant Independent Spent Fuel Storage Facility TVAINRC Meeting Atlanta, GA August 20, 2002

Agenda

"* Spent Fuel Storage

"* Project Workscope

  • Work Scope Status
  • Project Risks
  • Oversight Activities
  • Licensing Activities
  • NRC Review Considerations
  • Project Overview
  • Summary Smith

Spent Fuel Storage - Background

"* SQN Spent Fuel Pool

- Common to both units

- Transfer canal and cask loading area adjacent

- Uses boral as neutron poison

- Boron concentration maintained between 2,000 and 2,700 ppm

- Pool temperature typically between 70 OF and 112 OF

"* Spent Fuel Pool Capacity

- 2,091 storage locations installed with 2,089 useable storage locations

- 8 non-fuel items stored (debris container, boral specimen array, etc.)

- 1,700 spent fuel assemblies stored in pool

- 381 open cells, but full utilization limited by TS requirements Smith 2

Spent Fuel Storage - Background

  • SQN Spent Fuel Storage Considerations Originally estimated loss of full core off-load capacity 2002 by Spring

- Credit for SFP boron concentration extends SFP full core capacity loss to Fall 2004 - (U1C13)

- Comprehensive study of spent fuel storage options m Onsite dry cask storage determined to be best option

  • Proposals, Evaluations, and Decisions SQN issues request for proposals from selected vendors TVA Board awards contract to Holtec International - April 2000 SQN enters contract with Holtec International - June 2000 3

Smith

Spent Fuel Storage - site Location 4'4 Smith

Project Work Scope

"* Preliminary Design Activities

"* Engineering and Design

"* Site Construction

"* Hardware Fabrication and Delivery

"* Administrative Programs and Processes

"* Dry-Runs and NRC Demonstrations

"* Loading Campaign 5

Davis

Level 1 SQN ISFSI Schedule Pre-Design Activities 8/2000 4 mo Assemble Team Identify dwgs/procedures Negotiate final contract Environmental Assessment Detailed schedule development Engineering and Design 9/2002 18 mo Construction 312003 Soil structure interaction 0

Design Change Notices (DCN) 15 mo Workpla devlopent Start-up/Testing/NRC Demonstrations Work plan development 320 Actual construction activities 3/2004 Closure activities 12 mo Ops and Maint procedure dev.

Procedure revisions Training Pre-ops On site overpack fabrication Load 6 Casks 9/2004 6 mo Load, seal (close) and transport Davis 6

Level 1 SQN ISFSI Schedule (continued) 10 CFR 72 Subpart K Requirements 3/2004 44 mo 72.212 Evaluation Report Dose Rate Assessment FSAR Reviews 72.48 Evaluations Hardware Fabrication and Delivery 4/2003 1,

18 mO MPC - 32 HI-STORM 100s HI Trac 125 Stands / Platform Ancillary Equipment 7

Davis 8/2000 V

Work Scope Status - Design and Construction DCN

  • Railroad Bay

"* Railroad Bay Egress

"* Work Platform

"* Cask Pit Stands

  • Transport Roadway
  • Auxiliary Bldg Crane Upgrade
  • Electrical Conduit & Grounding
  • Security Lighting Complete Complete Complete Complete Complete Complete 09/06/02 (IP)

Complete Complete Construction 03/12/02 (C) 07/03/02 (C) 01/15/03 (IP) 09/23/02 (IP) 03/14/03 (IP) 10/15/02 (IP) 11/01/02 (IP) 03/14/03 (IP) 03/14/03 (IP) 8 Davis

Work Scope Status - Design and Construction

=

9 Davis

Work Scope Status - Design and Construction 10 Davis

Work Scope Status - Design and Construction 11 Davis

Work Scope Status - Design and Construction Auxiliary Building Crane Upgrade 12 Davis

Work Scope Status - Fabrication and Delivery of Storage and Transportation Equipment Start

  • Work Platform
  • Cask Support Stands
  • (1st) Multi Purpose Canisters
  • Hi -Trac Transfer Cask 1st) Storage Overpacks

"* Cask Transporter

"* Low Profile Transporter

"* Ancillary Equipment 09/15/02 06/24/02 01/27/03 12/02/02 03/03/03 08/30/02 03/01/03 01/01/03 Delivery 01/20/03 09/30/02 06/10/03 06/13/03 06/25/03 07/24/03 07/29/03 07/29/03 Hi-Trac Lift Yoke, Welding Machine, Vacuum Drying Equipment, Helium Backfill System, and Hydrostatic Test System Davis 13

Work Scope Status -Storage Equipment Hi-Trac Transfer Cask Multi-Purp Canisti HI-ST4 10(

Stor Overc Work platform ose er ORM 3s age pack Cask Pit support stands 14 Davis v

I

Work Scope Status - Transport Equipment Typical Cask and Low Profile Transporter 15 Davis

Work Scope Status Administrative Processes and Procedures Start

  • Internal Process
  • 0 & M Procedures Revisions Development
  • Training Program Development

"* Personnel Training

"* Readiness Reviews

  • 10 CFR 72.212 Evaluations 05/2002 09/2002 02/2003 07/2003 09/2003 08/2001 Complete 06/2003 02/2003 05/2003 09/2003 12/2003 03/2004
  • NRC Inspections and Demonstrations TBD Davis 16

Work Scope Status Administrative Processes and Procedures

"* Quality Assurance Requirements

- Revise Nuclear Quality Assurance Plan

"* Revise Radiological Emergency Plan

"* Site Security Plan

- Revise implementing procedure

  • Records Requirements

- Define QA Records and retention requirements

  • Procedure Control Process

- Revise procedures controlling administration of procedures site technical 17 Davis

Work Scope Status Administrative Processes and Procedures

"* Licensing Processes

- Revise reporting requirements

- Develop new procedure to control cask certificate of compliance and cask SAR updates

"* Engineering Processes

- Revise plant modifications and engineering change control program

- Revise qualification-list and UNID control

- Develop new procedure to address 10 CFR 72.48 change control requirements

"* Maintenance and Operations Procedures

- Review and revise existing procedures as appropriate 18 Davis

Work Scope Status Administrative Processes and Procedures

  • Develop
Loading, O&M Procedu res and Training Program for Sealing and Transporting

- RFP for procedures and training program developed and proposals received

- Evaluations in progress

- Award contract in late August

- Benefit of "Lessons Learned" from other utilities Davis 19

Work Scope Status - Readiness Review

  • On-Going Self-Assessments
  • Perform Dry-Runs of Loading, Sealing, Transporting and Storing to Verify:

- Equipment operation

- Site procedures

- Personnel qualifications

- Personnel and equipment safety

  • Independent Review of Dry-Runs (Peer Reviews)

Davis 20

Project Risks Risks Countermeasures

"* Storage Equipment Fabrication and Delivery Schedule

"* Soil Structure Interaction Methodology and Changing NRC Requirements

  • Potential Changes to Site Security
  • Working closely with Holtec to establish and maintain the schedule and quality
  • Increased TVA Engineering and Licensing oversight

-Working closely with Site Security and Licensing to monitor rulemaking activities for potential security changes 21 Davis

Oversight Activities

"* Dedicated Quality Manager Working on both SQN and BFN ISFSI Projects

"* Quality Oversight Plan Developed, reviewed and concurred-with by the ISFSI Project Team and TVA's Nuclear Assurance Organization Oversight Plan objectives

"* Ensure Holtec, US Tool & Die, and TVA Nuclear organizations understand and effectively implement the QA attributes related to 10 CFR 72

"* Ensure industry lessons-learned are incorporated into the TVA programs

"* Identify vendor and TVA quality issues early

"* Assessments of Holtec, US Tool & Die and SQN Site Activities

"* TVAN will provide an onsite QC Inspector at US Tool & Die Smith 22

Oversight Activities

  • Participated in 2 audits of Holtec with Entergy and NUPIC

"* Assisted in the formation of Holtec Users QA Group (HUQAG)

"* Led the first joint utility surveillance of Holtec by the new HUQAG

"* On-site NA organization provide additional oversight of site activities

  • On going surveillances of US Tool & Die based on work in progress
  • On-site self-assessments/readiness assessments to ensure program adequacy 23 Smith

Licensing Activities

- Inspection of pad design adequacy prior to concrete pours

- Preoperational and Operational ISFSI Dry-Runs 10 CFR 72.212 Evaluation Report 10 CFR 72.48 Evaluations

  • Submit 90-Day General Spring 2004 Operation License Notification to Support 24 Smith

NRC Review Considerations

  • TVA will be revising the Radiological Emergency Plan Submit to NRC reviewing the Security Plan and submitting to NRC, as appropriate
  • TVA appreciates NRC efforts towards a timely and approval of Amendment 1 to HI-STORM 1 Certificate of Compliance 1014 NRC approval of LAR 2 to HI-STORM 100 COc review 00 C 1014 Critical element for SQN is update to the MPCs thermal rating

- Holtec submitted for NRC review on March 4, 2002 TVA requests NRC approval by Spring 2003 25 Smith

Project Overview 0 Project Schedule Previously Presented to NRC on 1999, August 23, 2000, and October 11, 2001

/

v" V

/

26 June 29, t is or ions,

Davis

Summary

  • ISFSI Project is on Schedule
  • NRC Inspections and Dry-Runs to be Scheduled 27