ML022410170
| ML022410170 | |
| Person / Time | |
|---|---|
| Site: | Sequoyah |
| Issue date: | 08/20/2002 |
| From: | Tennessee Valley Authority |
| To: | Office of Nuclear Reactor Regulation |
| References | |
| Download: ML022410170 (28) | |
Text
Sequoyah Nuclear Plant Independent Spent Fuel Storage Facility TVAINRC Meeting Atlanta, GA August 20, 2002
Agenda
"* Spent Fuel Storage
"* Project Workscope
- Work Scope Status
- Project Risks
- Oversight Activities
- Licensing Activities
- NRC Review Considerations
- Project Overview
- Summary Smith
Spent Fuel Storage - Background
"* SQN Spent Fuel Pool
- Common to both units
- Transfer canal and cask loading area adjacent
- Uses boral as neutron poison
- Boron concentration maintained between 2,000 and 2,700 ppm
- Pool temperature typically between 70 OF and 112 OF
"* Spent Fuel Pool Capacity
- 2,091 storage locations installed with 2,089 useable storage locations
- 8 non-fuel items stored (debris container, boral specimen array, etc.)
- 1,700 spent fuel assemblies stored in pool
- 381 open cells, but full utilization limited by TS requirements Smith 2
Spent Fuel Storage - Background
- SQN Spent Fuel Storage Considerations Originally estimated loss of full core off-load capacity 2002 by Spring
- Credit for SFP boron concentration extends SFP full core capacity loss to Fall 2004 - (U1C13)
- Comprehensive study of spent fuel storage options m Onsite dry cask storage determined to be best option
- Proposals, Evaluations, and Decisions SQN issues request for proposals from selected vendors TVA Board awards contract to Holtec International - April 2000 SQN enters contract with Holtec International - June 2000 3
Smith
Spent Fuel Storage - site Location 4'4 Smith
Project Work Scope
"* Preliminary Design Activities
"* Engineering and Design
"* Site Construction
"* Hardware Fabrication and Delivery
"* Administrative Programs and Processes
"* Dry-Runs and NRC Demonstrations
"* Loading Campaign 5
Davis
Level 1 SQN ISFSI Schedule Pre-Design Activities 8/2000 4 mo Assemble Team Identify dwgs/procedures Negotiate final contract Environmental Assessment Detailed schedule development Engineering and Design 9/2002 18 mo Construction 312003 Soil structure interaction 0
Design Change Notices (DCN) 15 mo Workpla devlopent Start-up/Testing/NRC Demonstrations Work plan development 320 Actual construction activities 3/2004 Closure activities 12 mo Ops and Maint procedure dev.
Procedure revisions Training Pre-ops On site overpack fabrication Load 6 Casks 9/2004 6 mo Load, seal (close) and transport Davis 6
Level 1 SQN ISFSI Schedule (continued) 10 CFR 72 Subpart K Requirements 3/2004 44 mo 72.212 Evaluation Report Dose Rate Assessment FSAR Reviews 72.48 Evaluations Hardware Fabrication and Delivery 4/2003 1,
18 mO MPC - 32 HI-STORM 100s HI Trac 125 Stands / Platform Ancillary Equipment 7
Davis 8/2000 V
Work Scope Status - Design and Construction DCN
- Railroad Bay
"* Railroad Bay Egress
"* Work Platform
"* Cask Pit Stands
- ISFSI Storage Pad
- Transport Roadway
- Auxiliary Bldg Crane Upgrade
- Electrical Conduit & Grounding
- Security Lighting Complete Complete Complete Complete Complete Complete 09/06/02 (IP)
Complete Complete Construction 03/12/02 (C) 07/03/02 (C) 01/15/03 (IP) 09/23/02 (IP) 03/14/03 (IP) 10/15/02 (IP) 11/01/02 (IP) 03/14/03 (IP) 03/14/03 (IP) 8 Davis
Work Scope Status - Design and Construction
=
9 Davis
Work Scope Status - Design and Construction 10 Davis
Work Scope Status - Design and Construction 11 Davis
Work Scope Status - Design and Construction Auxiliary Building Crane Upgrade 12 Davis
Work Scope Status - Fabrication and Delivery of Storage and Transportation Equipment Start
- Work Platform
- Cask Support Stands
- (1st) Multi Purpose Canisters
- Hi -Trac Transfer Cask 1st) Storage Overpacks
"* Cask Transporter
"* Low Profile Transporter
"* Ancillary Equipment 09/15/02 06/24/02 01/27/03 12/02/02 03/03/03 08/30/02 03/01/03 01/01/03 Delivery 01/20/03 09/30/02 06/10/03 06/13/03 06/25/03 07/24/03 07/29/03 07/29/03 Hi-Trac Lift Yoke, Welding Machine, Vacuum Drying Equipment, Helium Backfill System, and Hydrostatic Test System Davis 13
Work Scope Status -Storage Equipment Hi-Trac Transfer Cask Multi-Purp Canisti HI-ST4 10(
Stor Overc Work platform ose er ORM 3s age pack Cask Pit support stands 14 Davis v
I
Work Scope Status - Transport Equipment Typical Cask and Low Profile Transporter 15 Davis
Work Scope Status Administrative Processes and Procedures Start
- Internal Process
- 0 & M Procedures Revisions Development
- Training Program Development
"* Personnel Training
"* Readiness Reviews
- 10 CFR 72.212 Evaluations 05/2002 09/2002 02/2003 07/2003 09/2003 08/2001 Complete 06/2003 02/2003 05/2003 09/2003 12/2003 03/2004
- NRC Inspections and Demonstrations TBD Davis 16
Work Scope Status Administrative Processes and Procedures
"* Quality Assurance Requirements
- Revise Nuclear Quality Assurance Plan
"* Revise Radiological Emergency Plan
"* Site Security Plan
- Revise implementing procedure
- Records Requirements
- Define QA Records and retention requirements
- Procedure Control Process
- Revise procedures controlling administration of procedures site technical 17 Davis
Work Scope Status Administrative Processes and Procedures
"* Licensing Processes
- Revise reporting requirements
- Develop new procedure to control cask certificate of compliance and cask SAR updates
"* Engineering Processes
- Revise plant modifications and engineering change control program
- Revise qualification-list and UNID control
- Develop new procedure to address 10 CFR 72.48 change control requirements
"* Maintenance and Operations Procedures
- Review and revise existing procedures as appropriate 18 Davis
Work Scope Status Administrative Processes and Procedures
- Develop
- Loading, O&M Procedu res and Training Program for Sealing and Transporting
- RFP for procedures and training program developed and proposals received
- Evaluations in progress
- Award contract in late August
- Benefit of "Lessons Learned" from other utilities Davis 19
Work Scope Status - Readiness Review
- On-Going Self-Assessments
- Perform Dry-Runs of Loading, Sealing, Transporting and Storing to Verify:
- Equipment operation
- Site procedures
- Personnel qualifications
- Personnel and equipment safety
- Independent Review of Dry-Runs (Peer Reviews)
Davis 20
Project Risks Risks Countermeasures
"* Storage Equipment Fabrication and Delivery Schedule
"* Soil Structure Interaction Methodology and Changing NRC Requirements
- Potential Changes to Site Security
- Working closely with Holtec to establish and maintain the schedule and quality
- Increased TVA Engineering and Licensing oversight
-Working closely with Site Security and Licensing to monitor rulemaking activities for potential security changes 21 Davis
Oversight Activities
"* Dedicated Quality Manager Working on both SQN and BFN ISFSI Projects
"* Quality Oversight Plan Developed, reviewed and concurred-with by the ISFSI Project Team and TVA's Nuclear Assurance Organization Oversight Plan objectives
"* Ensure Holtec, US Tool & Die, and TVA Nuclear organizations understand and effectively implement the QA attributes related to 10 CFR 72
"* Ensure industry lessons-learned are incorporated into the TVA programs
"* Identify vendor and TVA quality issues early
"* Assessments of Holtec, US Tool & Die and SQN Site Activities
"* TVAN will provide an onsite QC Inspector at US Tool & Die Smith 22
Oversight Activities
- Participated in 2 audits of Holtec with Entergy and NUPIC
"* Assisted in the formation of Holtec Users QA Group (HUQAG)
"* Led the first joint utility surveillance of Holtec by the new HUQAG
"* On-site NA organization provide additional oversight of site activities
- On going surveillances of US Tool & Die based on work in progress
- On-site self-assessments/readiness assessments to ensure program adequacy 23 Smith
Licensing Activities
- NRC ISFSI Inspections
- Inspection of pad design adequacy prior to concrete pours
- Preoperational and Operational ISFSI Dry-Runs 10 CFR 72.212 Evaluation Report 10 CFR 72.48 Evaluations
- Submit 90-Day General Spring 2004 Operation License Notification to Support 24 Smith
NRC Review Considerations
- TVA will be revising the Radiological Emergency Plan Submit to NRC reviewing the Security Plan and submitting to NRC, as appropriate
- TVA appreciates NRC efforts towards a timely and approval of Amendment 1 to HI-STORM 1 Certificate of Compliance 1014 NRC approval of LAR 2 to HI-STORM 100 COc review 00 C 1014 Critical element for SQN is update to the MPCs thermal rating
- Holtec submitted for NRC review on March 4, 2002 TVA requests NRC approval by Spring 2003 25 Smith
- TVA is
Project Overview 0 Project Schedule Previously Presented to NRC on 1999, August 23, 2000, and October 11, 2001
/
v" V
/
26 June 29, t is or ions,
Davis
Summary
- ISFSI Project is on Schedule
- NRC Inspections and Dry-Runs to be Scheduled 27