Meeting Summary with Tennesee Valley Authority Re Plans for Independent Spent Fuel Storage Installation at Sequoyah Nuclear Plant
ML022410162
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 08/28/2002
From: Ayres D
Division of Nuclear Materials Safety II
To: Scalice J
Tennessee Valley Authority
References
Download: ML022410162 (4)


Text

August 28, 2002 Tennessee Valley Authority ATTN: Mr. J. A. Scalice Chief Nuclear Officer and Executive Vice President 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801

SUBJECT:

MEETING

SUMMARY

- PLANS FOR AN INDEPENDENT SPENT FUEL STORAGE INSTALLATION AT THE SEQUOYAH NUCLEAR PLANT 327, AND 50-328

Dear Mr. Scalice:

This letter refers to the open meeting at the NRC Region II Office in Atlanta, Georgia on August 20, 2002, during which your staff discussed plans for the dry storage of spent fuel at the Sequoyah Nuclear facility. The meeting was beneficial and provided the NRC with an understanding of the project schedule so that adequate resources could be more effectively scheduled to conduct pre-operational inspection activities.

The names of attendees at the meeting are enclosed.

In accordance with 10 CFR 2.790 of NRCs "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in NRCs Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS).

ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-rm/ADAMS.html (the Public Electronic Reading Room).

Should you have any questions concerning this meeting, please contact me at 404-562-4711.

Sincerely,

/RA/

David A. Ayres, Chief Fuel Facilities Branch Division of Nuclear Materials Safety Docket Nos. 50-327, 50-328 License Nos. DPR-77, DPR-79

Enclosures:

(See Page 2)

TVA 2

Enclosures:

1. List of Participating Attendees
2. Meeting Handouts cc w/encl 1:

Karl W. Singer Pedro Salas, Manager Senior Vice President Licensing and Industry Affairs Nuclear Operations Sequoyah Nuclear Plant Tennessee Valley Authority Tennessee Valley Authority Electronic Mail Distribution Electronic Mail Distribution Jon R. Rupert, Vice President (Acting) D. L. Koehl, Plant Manager Engineering and Technical Services Sequoyah Nuclear Plant Tennessee Valley Authority Tennessee Valley Authority Electronic Mail Distribution Electronic Mail Distribution Richard T. Purcell Lawrence E. Nanney, Director Site Vice President TN Dept. of Environment & Conservation Sequoyah Nuclear Plant Division of Radiological Health Electronic Mail Distribution Electronic Mail Distribution General Counsel County Executive Tennessee Valley Authority Hamilton County Courthouse Electronic Mail Distribution Chattanooga, TN 37402-2801 Robert J. Adney, General Manager Ann Harris Nuclear Assurance 341 Swing Loop Tennessee Valley Authority Rockwood, TN 37854 Electronic Mail Distribution John D. White, Jr., Director Mark J. Burzynski, Manager Tennessee Emergency Management Nuclear Licensing Agency Tennessee Valley Authority Electronic Mail Distribution Electronic Mail Distribution Distribution w/encls:

R. W. Hernan, NRR RIDSNRRDIPMLIPB PUBLIC

  • see previous concurrence PUBLIC DOCUMENT (circle one): YES NO OFFICE RII:DNMS RII:DNMS RII:DRP RII:DRP SIGNATURE WBG 8/22/02 DAA 8/23/02 PF 8/26/02 NAME *WGloersen *DAyres *PTaylor *PFredrickson DATE 8/ /2002 8/ /2002 8/ /2002 8/ /2002 8/ /2002 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: C:\ORPCheckout\FileNET\ML022410162.wpd

TVA Tennessee Valley Authority PLANS FOR AN INDEPENDENT SPENT FUEL STORAGE INSTALLATION (ISFSI)

AT THE SEQUOYAH NUCLEAR PLANT LIST OF PARTICIPATING ATTENDEES August 20, 2002 U. S. Nuclear Regulatory Commission D. Ayres, Branch Chief, Fuel Facilities Branch (FFB), Division of Nuclear Materials Safety (DNMS), RII H. Berkow, Director, Project Directorate II, Nuclear Reactor Regulation (NRR)

P. Frederickson, Branch Chief, Division of Reactor Projects, RII W. Gloersen, Senior Fuel Facility Project Inspector, FFB, DNMS RII M. Lesser, Branch Chief, Engineering Branch, Division of Reactor Safety, RII G. Kuzo, Senior Radiation Specialist, DRS, RII S. OConnor, Project Manager, Spent Fuel Project Office (SFPO) (via teleconference)

S. Vias, Senior Reactor Branch, DRS, RII Tennessee Valley Authority C. Davis, Project Manager R. Enis, Senior Civil Engineer Z. Kitts, Licensing Engineer D. Lundy, Engineering Manager D. Osborne, Civil Design Manager J. Smith. Licensing Supervisor Enclosure 1