Hatch Inspection / Activity Plan 09/01/2002 - 09/30/2003 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/26/2002 13:33:25 Report 22 7
EB1SSDPC - SAFETY SYS DESIGN & PERFORMANCE CAPABILI Baseline Inspections 09/09/2002 09/13/2002 Safety System Design and Performance Capability IP 7111121 1, 2 1
- ISFSI Other Routine 09/16/2002 09/20/2002 Operation Of An ISFSI IP 60855 1, 2 4
OL PREP
- INITIAL EXAM PREP Not Applicable 09/30/2002 10/04/2002 HATCH/EXAMS AT POWER FACILITIES V23191 1
4 OL EXAM
- INITIAL EXAM Not Applicable 10/21/2002 10/25/2002 HATCH/EXAMS AT POWER FACILITIES V23191 1
1 BR2-FP
- FLOOD PROTECTION Baseline Inspections 11/18/2002 11/21/2002 Flood Protection Measures IP 7111106 1, 2 4
EB2-MODS - MODIFICATIONS/10CFR50.59 Baseline Inspections 12/02/2002 12/06/2002 Evaluation of Changes, Tests, or Experiments IP 7111102 1, 2 Baseline Inspections 12/02/2002 12/06/2002 Permanent Plant Modifications IP 7111117B 1, 2 1
EB2-MR
- MAINTENANCE RULE Baseline Inspections 12/09/2002 12/13/2002 Maintenance Effectiveness IP 7111112B 1, 2 1
PS-RP
- RAD PROTECTION -ONSITE PREP/ISFSI Baseline Inspections 02/10/2003 02/12/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 3
PS-RP
- RADIATION PROTECTION - ISFSI Baseline Inspections 03/03/2003 03/07/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 03/03/2003 03/07/2003 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 03/03/2003 03/07/2003 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 03/03/2003 03/07/2003 Performance Indicator Verification IP 71151 1, 2 1
EB2-ISI
- INSERVICE INSPECTION-U2 Baseline Inspections 03/10/2003 03/14/2003 Inservice Inspection Activities IP 7111108 2
3 PS-RP
- RADIATION PROTECTION - ISFSI Baseline Inspections 03/17/2003 03/21/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 03/17/2003 03/21/2003 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 03/17/2003 03/21/2003 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 03/17/2003 03/21/2003 Performance Indicator Verification IP 71151 1, 2 6
EB1-TFP
- TFP - PRE-INSPECTION VISIT Baseline Inspections 06/16/2003 06/20/2003 Fire Protection IP 7111105T 1, 2 6
EB1-FP
- TRIENNIAL FIRE PROTECTION INSP Baseline Inspections 07/07/2003 07/11/2003 Fire Protection IP 7111105T 1, 2 Baseline Inspections 07/21/2003 07/25/2003 Fire Protection IP 7111105T 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Hatch Inspection / Activity Plan 09/01/2002 - 09/30/2003 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/26/2002 13:33:25 Report 22 1
EB2-HS
- HEAT SINK Baseline Inspections 08/11/2003 08/15/2003 Heat Sink Performance IP 7111107B 1, 2 3
BR2-PIR
- PROBLEM IDENTIFICATION AND RESOLUTION Baseline Inspections 08/11/2003 08/15/2003 Identification and Resolution of Problems IP 71152 1, 2 Baseline Inspections 08/25/2003 08/29/2003 Identification and Resolution of Problems IP 71152 1, 2 2
- EMERGENCY EXERCISE Baseline Inspections 08/18/2003 08/22/2003 Exercise Evaluation IP 7111401 1, 2 Baseline Inspections 08/18/2003 08/22/2003 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 08/18/2003 08/22/2003 Performance Indicator Verification IP 71151 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.