ML022400494
| ML022400494 | |
| Person / Time | |
|---|---|
| Issue date: | 10/19/2001 |
| From: | Lawrence Burkhart Office of Nuclear Reactor Regulation |
| To: | Nuclear Energy Institute |
| References | |
| BL-01-001, FOIA/PA-2002-0229 | |
| Download: ML022400494 (6) | |
Text
From:
To:
Date:
Subject:
- a.vwrenceBurkhart - BULLETIN 2001-01 PUBLIC MEETINGS ON 10/24/01 SLawrence Burkhart-P intemet: am @nei.org; internet: koc@ nei.org 10119/01 3:07PM BULLETIN 2001-01 PUBLIC MEETINGS ON 10124/01 I have been informed that the Nuclear Regulatory Commission (NRC) public website has been experiencing problems. In attempt to keep external stakeholders informed of issues surrounding Bulletin 2001-01, "Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles," I am forwarding 2 notices (attached) for public meetings that are scheduled to be held on Wednesday, 10/24/01. These notices are also available via the NRC's Agencywide Documents Access and Management System (ADAMS).
Jacob Zimmerman, the lead project manager for this issue, will be out of the office until Monday, October 29, 2001. You may contact me if you have and questions or comments regarding this issue.
Thank You.
Lawrence J. Burkhart Project Manager Division of Licensing Project Management Office of Nuclear Reactor Regulation A-I2 Pagell
awre.nce, Burkhart - BULLETIN 2001-01 MEETINGS SCHEDULED ON 10/24/01 Page1 From:
internet: jenny-weil@platts.com Date:
10/19/01 3:14PM
Subject:
BULLETIN 2001-01 MEETINGS SCHEDULED ON 10/24/01 I have been informed that the Nuclear Regulatory Commission (NRC) public website has been experiencing problems. In attempt to keep external stakeholders informed of issues surrounding Bulletin 2001-01, "Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles," I am forwarding 2 notices (attached) for public meetings that are scheduled to be held on Wednesday, 10/24/01. These notices are also available via the NRC's Agencywide Documents Access and Management System (ADAMS).
Jacob Zimmerman, the lead project manager for this issue, will be out of the office until Monday, October 29, 2001. You may contact me if you have and questions or comments regarding this issue.
Thank You.
Lawrence J. Burkhart Project Manager Division of Licensing Project Management Office of Nuclear Reactor Regulation
-..awrence Burkhart - BULLETIN 2001-01 PUBLIC MEETINGS SCHEDULED FOR 10/24/01 Pg From:
internet: jbeattie@kingpublishing.com Date:
10/19/01 3:15PM
Subject:
BULLETIN 2001-01 PUBLIC MEETINGS SCHEDULED FOR 10/24/01 I have been informed that the Nuclear Regulatory Commission (NRC) public website has been experiencing problems. In attempt to keep external stakeholders informed of issues surrounding Bulletin 2001-01, "Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles," I am forwarding 2 notices (attached) for public meetings that are scheduled to be held on Wednesday, 10/24/01. These notices are also available via the NRC's Agencywide Documents Access'and Management System (ADAMS).
Jacob Zimmerman, the lead project manager for this issue, will be out of the office until Monday, October 29, 2001. You may contact me if you have and questions or comments regarding this issue.
Thank You.
Lawrence J. Burkhart Project Manager Division of Licensing Project Management Office of Nuclear Reactor Regulation
- ,,..awrence Burkhart - BULLETIN 2001-01 PUBLIC MEETINGS SCHEDULED FOR 10/24/01 From:
internet: draleigh@scientech.com; internet: tsutter@scientech.com Date:
10/19/01 3:17PM
Subject:
BULLETIN 2001-01 PUBLIC MEETINGS SCHEDULED FOR 10/24/01 I have been informed that the Nuclear Regulatory Commission (NRC) public website has been experiencing problems. In attempt to keep external stakeholders informed of issues surrounding Bulletin 2001-01, "Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles,' I am forwarding 2 notices (attached) for public meetings that are scheduled to be held on Wednesday, 10/24/01. These notices are also available via the NRC's Agencywide Documents Access and Management System (ADAMS).
Jacob Zimmerman, the lead project manager for this issue, will be out of the office until Monday, October 29, 2001. You may contact me if you have and questions-or comments regarding this issue.
Thank You.
Lawrence J. Burkhart Project Manager Division of Licensing Project Management Office of Nuclear Reactor Regulation
,,;,wrence Burkhart - BULLETIN 2001 -01 PUBLIC MEETINGS PEage 1 From:
internet: dlochbaum@ucsus.org Date:
10/19/01 3:12PM
Subject:
BULLETIN 2001-01 PUBLIC MEETINGS I have been informed that the Nuclear Regulatory Commission (NRC) public website has been experiencing problems. In attempt to keep external stakeholders informed of issues surrounding Bulletin 2001-01, "Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles," I am forwarding 2 notices (attached) for public meetings that are scheduled to be held on Wednesday, 10/24/01. These notices are also available via the NRC's Agencywide Documents Access and Management System (ADAMS).
Jacob Zimmerman, the lead project manager for this issue, will be out of the office until Monday, October 29, 2001. You may contact me if you have and questions -or comments regarding this issue.
Thank You.
Lawrence J. Burkhart Project Manager Division of Licensing Project Management Office of Nuclear Reactor Regulation
From:
internet: dlochbaum @ ucsusa.org Date:
10/19/01 3:33PM
Subject:
PUBLIC MEETINGS SCHEDULED FOR 10/24/01 RE: BULLETIN 2001-01 I have been informed that the Nuclear Regulatory Commission (NRC) public website has been experiencing problems. In attempt to keep external stakeholders informed of issues surrounding Bulletin 2001-01, "Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles,' I am forwarding 2 notices (attached) for public meetings that are scheduled to be held on Wednesday, 10/24/01. These notices are also available via the NRC's Agencywide Documents Access and Management System (ADAMS).
Jacob Zimmerman, the lead project manager for this issue, will be out of the office until Monday, October 29, 2001. You may contact me if you have any questions -or comments regardir~g this issue.
Thank You.
Lawrence J. Burkhart Project Manager Division of Licensing Project Management Office of Nuclear Reactor Regulation P a g e 1 a=,,wren'ce Burkhart - PUB~IC-M-EETINGS SCHEDULED FOR 10/24/1 !_RE: BULLETIN 2001-01