Mid-Cycle Performance Review & Inspection Plan - Sequoyah Nuclear Plant, Inspection/Activity Plan 09/01/2002 - 09/30/2003
ML022400291
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 08/26/2002
From: Fredrickson P
Reactor Projects Region 2 Branch 6
To: Scalice J
Tennessee Valley Authority
Shared Package
ML022400276 List:
References
IMC 0305
Download: ML022400291 (2)


Text

Sequoyah Inspection / Activity Plan 09/01/2002 - 09/30/2003 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/26/2002 13:04:10 Report 22 2

OL-EP

- EMERGENCY EXERCISE Baseline Inspections 09/30/2002 10/04/2002 Exercise Evaluation IP 7111401 1, 2 Baseline Inspections 09/30/2002 10/04/2002 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 09/30/2002 10/04/2002 Performance Indicator Verification IP 71151 1, 2 1

ISFSI

- ISFSI CONSTRUCTION Other Routine 10/28/2002 10/30/2002 On-Site Fabrication Of Components And Construction On An ISFSI IP 60853 1, 2 2

PS-SEC

- SECURITY Baseline Inspections 10/28/2002 11/01/2002 Response to Contingency Events (Protective Strategy and Implementation of Protective Strategy)

IP 7113003 1, 2 2

EB2-MR

- MAINTENANCE RULE Baseline Inspections 11/11/2002 11/15/2002 Maintenance Effectiveness IP 7111112B 1, 2 3

OL-PREP

- INITIAL EXAM PREP Not Applicable 11/12/2002 11/15/2002 SEQUOYAH/EXAMS AT POWER FACILITIES V23203 1

1 PS-RP

- RADIATION PROTECTION Baseline Inspections 11/12/2002 11/15/2002 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 11/12/2002 11/15/2002 Performance Indicator Verification IP 71151 1, 2 3

OL-EXAM

- INITIAL EXAM Not Applicable 12/02/2002 12/06/2002 SEQUOYAH/EXAMS AT POWER FACILITIES V23203 1

1 PS-RP

- RADIATION PROTECTION Baseline Inspections 12/09/2002 12/10/2002 Access Control to Radiologically Significant Areas IP 7112101 1, 2 1

EB1SSDPC - SSDPC PRE-INSPECTION VISIT Baseline Inspections 01/13/2003 01/17/2003 Safety System Design and Performance Capability IP 7111121 1, 2 1

PB6-FP

- FLOOD PROTECTION Baseline Inspections 01/13/2003 01/17/2003 Flood Protection Measures IP 7111106 1, 2 6

EB1SSDPC - SAFETY SYS DESIGN & PERFORMANCE CAPABILI Baseline Inspections 02/10/2003 02/14/2003 Safety System Design and Performance Capability IP 7111121 1, 2 Baseline Inspections 02/24/2003 02/28/2003 Safety System Design and Performance Capability IP 7111121 1, 2 1

EB2-SGRP

- SGRP-U1 Other Routine 03/16/2003 05/30/2003 Steam Generator Replacement Inspection IP 50001 1

1 EB2-ISI

- INSERVICE INSPECTION-U1 Baseline Inspections 03/24/2003 03/28/2003 Inservice Inspection Activities IP 7111108 1

3 PS-RP

- RADIATION PROTECTION Baseline Inspections 04/14/2003 04/18/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 04/14/2003 04/18/2003 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 04/14/2003 04/18/2003 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 04/14/2003 04/18/2003 Performance Indicator Verification IP 71151 1, 2 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Sequoyah Inspection / Activity Plan 09/01/2002 - 09/30/2003 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/26/2002 13:04:10 Report 22 2

PS-RP

- RADIATION PROTECTION Baseline Inspections 05/12/2003 05/16/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 05/12/2003 05/16/2003 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 05/12/2003 05/16/2003 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 05/12/2003 05/16/2003 Performance Indicator Verification IP 71151 1, 2 1

OL EP

- EP INSPECTION Baseline Inspections 06/23/2003 06/27/2003 Alert and Notification System Testing IP 7111402 1, 2 Baseline Inspections 06/23/2003 06/27/2003 Emergency Response Organization Augmentation Testing IP 7111403 1, 2 Baseline Inspections 06/23/2003 06/27/2003 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 06/23/2003 06/27/2003 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1, 2 Baseline Inspections 06/23/2003 06/27/2003 Performance Indicator Verification IP 71151 1, 2 1

EB2-HS

- HEAT SINK Baseline Inspections 07/07/2003 07/11/2003 Heat Sink Performance IP 7111107B 1, 2 3

PI&R

- IDENTIFICATION AND RESOLUTION OF PROBLEM Baseline Inspections 07/14/2003 07/18/2003 Identification and Resolution of Problems IP 71152 1, 2 3

PI&R

- IDENTIFICATION AND RESOLUTION OF PROBLEM Baseline Inspections 07/28/2003 08/01/2003 Identification and Resolution of Problems IP 71152 1, 2 3

EB2-MODS - MODIFICATIONS/10CFR50.59 Baseline Inspections 08/25/2003 08/29/2003 Evaluation of Changes, Tests, or Experiments IP 7111102 1, 2 Baseline Inspections 08/25/2003 08/29/2003 Permanent Plant Modifications IP 7111117B 1, 2 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.