ML022390638

From kanterella
Jump to navigation Jump to search
Tva/Nrc Meeting Browns Ferry Nuclear Plant License Renewal Application
ML022390638
Person / Time
Site: Browns Ferry  
(DPR-033, DPR-052, DPR-068)
Issue date: 07/24/2002
From: Abney T, Adkins G, Ryan Alexander, Burzynski M, Valente J
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation
References
Download: ML022390638 (12)


Text

Tennessee Valley Authority Browns Ferry Nuclear Plant Units 1, 2, and 3 I

I License Renewal Application

-x I"

,-

Ii



I

'v-

  • s.



4Uv

- a s

,*.j*--

b4

~'--

AVA~I NRCMeeting Nuiclear R

.11-,eactor Regulation --,RocVile -MDj

~

July 24,2002,.

Enclosur

-b'



¶ a

I I

.4

  • 1 II p



J,ýlk-Luoul U

/,

Agenda Uiaý Introduction & Background Project Organization Unit 1 Licensing Basis Unit 1 Restart & Power Uprate Programs

--Synergies With License Renewal Application Format Application Methodology Project Status & Schedule Environmental Review Closing Remarks 1

Tim Abney Ray Alexander Tim Abney Joe Valente Gary Adkins Gary Adkins Gary Adkins Mark Burzynski Tim Abney

Introduction & Background

    • TVA voluntarily shutdown all three units in 1985 Unit 2 restarted in 1991 SUnit 3 restarted in 1995 Unit 1 defueled with a layup and preservation program in place
  • - Record of Decision issued June 18, 2002
    • Unit 1 restart by May 2007 Tim Abney 2

Introduction & Background, continued TVA will submit an application to renew the operating licenses for Browns Ferry, Units 1, 2, and 3 by December 2003 SConsistent with NRC regulatory burden reduction policy and NRC strategic plan Most economical, efficient path for both TVA ratepayers and NRC Three-unit application has no safety impacts TVA NRC Reduced NRC fees Simultaneous review of three identical units is Optimizes staff resources the most efficient process Consistent with staff approach for other multi unit sites

  • o TVA will submit a complete application that will enable the staff to make a reasonable assurance finding Tim Abney 3

I Ray Alexander BFN License Renewal Project Organization Unit I Recovery Chief Engineer's Engineering Mgr. *......

Design Engineering Manager Staff Joe Valente Ray Alexander BFN Project Design Browns Ferry Site ManagrojeLicensing Manager Manager*

Tim Abney License Renewal OGC Manager Licensing Project Ed Vgluici Gry AkinsManagement Ed-guci ayA kn Mike Morrison Environmental Project Control Review Proj. Mgmt Mark Burzynski Computer Scoping &

Mechanical Civil I&C/Electrical Engineers Screening

Unitl1 Licensing Basis

.:. The Unit 1 licensing basis is well-known, documented Unit 1 elements of the FSAR have been maintained Unit differences identified 4:e Key Unit 1 scoping documentation is available SFSAR Technical Specifications Safe shutdown analysis

o.

UFSAR update planned just prior to LRA submittal

,Annual application updates will reflect the modification program
  • o TVA has a clear vision of the ultimate Unit 1 licensing basis based on the Units 2/3 precedent as reflected in the FSAR Technical Specifications Nuclear Performance Plan Programs Generic letter & Bulletin responses Tim Abney

Unit I Restart & Power Uprate Programs Synergies With License Renewal

    • Unit fidelity Same design and licensing basis, materials, and environments Common control bay for Units 1 and 2 Unit 1 reactor building design same as Units 2 and 3 Extended power uprate conditions factored into license renewal EQ calculations RPV pressure - temperature curves Unit I modification program predominantly involves commodity upgrades that do not change the licensing basis 750,000 feet of cable S10,000 feet of large bore pipe S15,000 feet of small bore pipe
  • Rigorous configuration management program in place Ensures the licensing basis continues to be maintained
    • Extensive pre-service Section Xl inspections in addition to other baseline condition monitoring and post-modification inspections Provides enhanced opportunities for license renewal inspections Joe Valente

Application Format

    • SRP/ GALL format with lessons-learned from Demonstration Project and subsequent applications
  • o TVA's plan for Unit 1 will result in identical units at restart Any Unit 1 licensing basis differences will be annotated in combined application (multi-site) format o:o Implementation of Unit 1 modifications (and incorporation into the licensing basis) are expected to have minimal impact on the application No new intended functions, materials or environments anticipated for Unit 1 No new aging management programs anticipated for Unit 1 Gary Adkins 7

Application Methodology

  • Use the Unit 1 current licensing basis for scoping, screening, and TLAA identification

),Implement process for reviewing Unit 1 modifications for impact on the LRA

,e:- Operating experience Three identical units - Units 2/3 operating experience applicable to Unit 1 Unit 1 included in industry operating experience review

>. Supplemented by Unit 1 layup program experience AMRs -same aging management programs will be credited for all three units

ý, Aging management programs will be evaluated against the GALL AMP commitments will be implementation commitments No Unit 1 specific program commitments Gary Adkins 8

Project Status and Schedule Level 1 (CY) 2001 2002 2003 2004 2005 2006 2007 2008 I

i I

I I

I i

I System Boundary Delfinition/Drawings (U2/3)

SSystem Boundary Definition/Drawings (U1)

System Scoping & Screening (U2/S

!System Scoping & Screening (U1)

Component Material Evaluation (U2/3)

A SEIS Preparation Component Material Evaluation (Ul)

Aging Management Reviews (Ul/2/3)

TLAA Evaluations (Ul/2/3)

TVA Board Decision External Peer Review+

Application Preparation External Peer Review*

Ul FP Program Analysis Complete Ul EQ Analysis Complete*

Ul SBO Calc. Updated Ul ATWS Updated C PUR Impl.

PUR Impl.

PUR Impl.

(U3)

(U2)

(Ul)

U2/3 PUR Submittal 0, 0 C

PUR Submittal (Ul)

C)

LRA Submittal C Renewed Licenses Issued C Ul Breaker Closure*

Gary Adkins 9

Environmental Review

    • SEIS addresses NRC environmental review items Specifically incorporates the GElS Includes Part 51 plant-specific issues
    • SEIS has been extensively reviewed Intergovernmental reviews EPA comments incorporated Cooperating federal agency efficiencies noted by EPA
    • Public participation accomplished Two public meetings Three public comment periods
    • Process provides for NRC independent review prior to adoption
    • NRC adoption would allow for additional public input
    • NRC (AEC) was a cooperating federal agency on the original Browns Ferry Construction/Operation EIS Mark Burzynski 10

Closing Remarks Tim Abney 11