August 23, 2002 LICENSEE:

Exelon Generation Company, LLC (Exelon)

FACILITY:

Peach Bottom Atomic Power Station, Units 2 and 3

SUBJECT:

TELECOMMUNICATION WITH EXELON GENERATING COMPANY TO CLARIFY THE RESPONSE TO A REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO SECTION 2.3.2 ENGINEERING SAFETY FEATURES SYSTEMS OF THE PEACH BOTTOM LICENSE RENEWAL APPLICATION On August 5, 2002, a conference call was conducted between the Nuclear Regulatory Commission (NRC) staff (hereafter referred to as the staff) and representatives of Exelon Generating Company (hereafter referred to as the applicant) to clarify how environmental qualification (EQ) analysis of the high pressure coolant injection (HPCI) and reactor core isolation cooling (RCIC) pump rooms were conducted for the HPCI/RCIC room cooling coils that are required to maintain the operability of the HPCI/RCIC system during postulated design basis accidents. The staff noticed that the heat transfer function is not identified as the aging effect in Tables 2.3.2-1 and 2.3.2-4 of Section 2.3.2 of the license renewal application for the HPCI pump room cooling coils and the RCIC pump room cooling coils, respectively. The information discussed and the applicants response are provided below. A list of participants of the August 5, 2002, conference call is enclosed.

The applicant referred the above question to a teleconference conducted on December 26, 2001, regarding the staffs request for additional information, 3.2.4.2.1-3, where the staff asked a similar question for RCIC (analogous to HPCI) pump room cooling coils. The applicants response was that the cooling function of the RCIC room cooler is not required for RCIC system operability. The cooling coils are only required to maintain pressure boundary integrity of the emergency service water system. Thus, the applicant clarified that the heat transfer function for the cooling coils was not identified as an intended function. In response to the staffs EQ question, the applicant further clarified that the electrical, instrumentation, and control equipment in the RCIC and HPCI rooms, that needed to be protected against extreme environmental conditions, were relocated outside of the room. Therefore, the applicants EQ analysis of the HPCI/RCIC pump room determined that the HPCI/RCIC pump room cooling coils are not required to maintain the operability of the HPCI/RCIC system for the environmental conditions that were postulated to occur during design basis accidents for the plants.

The staff indicated that the applicants response is adequate and no further action is required.

/RA/

Peter J. Kang, Reactor Systems Engineer License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos. 50-277 and 50-278

Enclosure:

As stated cc w/encl: See next page The staff indicated that the applicants response is adequate and no further action is required.

/RA/

Peter J. Kang, Reactor Systems Engineer License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos. 50-277 and 50-278

Enclosure:

As stated cc w/encl: See next page Distribution:

See next page DOCUMENT NAME: C:\\ORPCheckout\\FileNET\\ML022380370.wpd OFFICE LA:DRIP NSE:RLEP PD:RLEP NAME HBerilla PKang SLee DATE 08/22/02 08/22/02 08/23/02 OFFICIAL RECORD COPY

DISTRIBUTION: Summary of Telecommunication with Exelon, Dated: August 23, 2002 HARD COPY RLEP RF P. Kang E-MAIL:

PUBLIC J. Johnson W. Borchardt D. Matthews F. Gillespie RidsNrrDe R. Barrett E. Imbro G. Bagchi K. Manoly W. Bateman J. Calvo C. Holden P. Shemanski H. Nieh G. Holahan H. Walker S. Black B. Boger D. Thatcher G. Galletti C. Li J. Moore R. Weisman M. Mayfield A. Murphy W. McDowell S. Droggitis T. Kobetz C. Munson RLEP Staff

TELECOMMUNICATION PARTICIPANTS NRC STAFF Ralph Caruso Muhammad Razzaque Paul Shemanski Peter J. Kang EXELON Jerry Phillabaum Kevin Muggleston Enclosure

Peach Bottom Atomic Power Station, Units 2 and 3 cc:

Vice President, General Counsel and Secretary Exelon Generation Company, LLC 300 Exelon Way Kennett Square, PA 19348 Site Vice President Peach Bottom Atomic Power Station Exelon Generation Company, LLC 1848 Lay Road Delta, PA 17314 Plant Manager Peach Bottom Atomic Power Station Exelon Generation Company, LLC 1848 Lay Road Delta, PA 17314 Regulatory Assurance Manager Peach Bottom Atomic Power Station Exelon Generation Company, LLC 1848 Lay Road Delta, PA 17314 Resident Inspector U.S. Nuclear Regulatory Commission Peach Bottom Atomic Power Station P.O. Box 399 Delta, PA 17314 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. Roland Fletcher Department of Environment Radiological Health Program 2400 Broening Highway Baltimore, MD 21224 Correspondence Control Desk Exelon Generation Company, LLC 200 Exelon Way, KSA 1-N-1 Kennett Square, PA 19348 Rich Janati, Chief Division of Nuclear Safety Bureau of Radiation Protection Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Board of Supervisors Peach Bottom Township 545 Broad Street Ext.

Delta, PA 17314-9203 Mr. Richard McLean Power Plant and Environmental Review Division Department of Natural Resources B-3, Tawes State Office Building Annapolis, MD 21401 Dr. Judith Johnsrud National Energy Committee Sierra Club 433 Orlando Avenue State College, PA 16803 Manager-Financial Control & Co-Owner Affairs Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, NJ 08038-0236 Manager Licensing-Limerick and Peach Bottom Exelon Generation Company, LLC Nuclear Group Headquarters Correspondence Control P.O. Box 160 Kennett Square, PA 19348 Mr. Alan P. Nelson Nuclear Energy Institute 1776 I Street, N.W., Suite 400 Washington, DC 20006-3708 APN@NEI.ORG Peach Bottom Atomic Power Station, Units 2 and 3 cc:

Director - Licensing Mid-Atlantic Regional Operating Group Exelon Generation Company, LLC Nuclear Group Headquarters Correspondence Control P.O. Box 160 Kennett Square, PA 19348 Vice President-Licensing and Regulatory Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Senior Vice President Mid-Atlantic Regional Operating Group Exelon Generation Company, LLC 200 Exelon Way, KSA 3-N Kennett Square, PA 19348 Senior Vice President, Nuclear Services Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Vice President, Mid-Atlantic Operations Support Exelon Generation Company, LLC 200 Exelon Way, KSA 3-N Kennett Square, PA 19348 Manager License Renewal Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348 Mr. Oliver D. Kingsley, President Exelon Nuclear Exelon Generation Company, LLC 200 Exelon Way, KSA 3-E Kennett Square, PA 19348 Public Service Commission of Maryland Engineering Division Chief Engineer 6 St. Paul Center Baltimore, MD 21202-6806 Chief Operating Officer Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555