FENOC FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant 10 Center Road PO. Box 97 Perry, Ohio 44081 August 13, 2002 PY-CEINRR-2655L United States Nuclear Regulatory Commission Document Control Desk Washington, D.C.
20555 Perry Nuclear Power Plant Docket No. 50-440 License No. NPF-58 Monthly Operating Report Ladies and Gentlemen:
Attached is the July 2002 Monthly Operating Report for Perry Unit 1. Page 1 is the Operating Data Report and page 2 is the Unit Shutdowns Report. This report is submitted in accordance with Technical Specification 5.6.4 and Generic Letter 97-02, "Revised Contents of the Monthly Operating Report."
If you have questions or require additional information, please contact Ms. Toni Phelps at (440) 280-7660.
V trly ours, for Gregory A. Dunn Manager - Regulatory Affairs Attachment cc: NRC Region III Administrator NRC Project Manager NRC Resident Inspector
OPERATING DATA REPORT UNIT:
Perry_
DATE:
8/5/02 Docket: 50-440 Unit Name:
Perry Nuclear Power Plant Reporting Period: July 2002 Utility
Contact:
T. Phelps Telephone: 440-280-7660 Design Electrical Rating (Net MWe):
Maximum Dependable Capacity (Net MWe):
1260 1235 Hours Reactor was Critical Hours Generator On-Line Unit Reserve Shutdown Hours Net Electrical Energy (MWeH)
This Month 744.0 744.0 0.0
.QO. R17 0 Yr-to-Date 4,930.0 4,846.5 0.0 5 879.723.0 Cumulative 101,515.2 98,919.5 0.0 112.480.125.0
- 1.
- 2.
- 3.
- 4.
- 5.
- 6.
7.
- 8.
- 9.
- 10.
11.
Page 1 909I i-
- 1.
0
UNIT SHUTDOWNS REPORT MONTH - JULY 2002 DOCKET NO: 50-440 NAME: Perry Nuclear Power Plant DATE: 08/05/02 CONTACT: T. Phelps TELEPHONE: (440) 280-7660 No.
Date Type Duration Reason Method Cause and Corrective Action to Prevent Recurrence 1
Hours 2
3
SUMMARY
- The Perry Plant was on line the entire month of July, 2002.
- 1. TYPE:
F: Forced S: Scheduled
- 2. REASON:
A - Equipment Failure (explain)
B - Maintenance or Test C - Refueling D - Regulatory E - Operating Training &
License Examination F - Administrative G - Operational Error (explain)
H - Other (explain)
- 3. METHOD:
1-Manual 2 - Manual Scram 3 -Automatic Scram 4 - Continuation 5 - Other Page 2