ML022190241

From kanterella
Jump to navigation Jump to search
Units 1 & 2 Regulatory Issue Summary 2002-09 Preparation & Scheduling of Operator Licensing Examinations Additional Information
ML022190241
Person / Time
Site: Surry, North Anna  Dominion icon.png
Issue date: 07/26/2002
From: Sarver S
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
02-357A, RIS-02-009
Download: ML022190241 (4)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 July 26, 2002 U.S. Nuclear Regulatory Commission Serial No.: 02-357A Attention: Document Control Desk NL&OS/MM Washington, D.C. 20555-0001 Docket Nos.: 50-280/281 50-338/339 License Nos.: DPR-32/37 NPF-4/7 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)

SURRY POWER STATION UNITS 1 AND 2 NORTH ANNA POWER STATION UNITS 1 AND 2 REGULATORY ISSUE

SUMMARY

2002-09 PREPARATION AND SCHEDULING OF OPERATOR LICENSING EXAMINATIONS ADDITIONAL INFORMATION On June 6, 2002, the Nuclear Regulatory Commission issued Regulatory Issue Summary 2002-09, "Preparation and Scheduling of Operator Licensing Examinations." Virginia Electric and Power Company (Dominion) submitted its response July 10, 2002 (Serial No. 357) without providing a proposed primary and alternate date for the initial operator license examinations. Attached is the information requested, including the proposed examination dates.

No new commitments are intended by this letter. If you have any questions or require additional information, please contact us.

Very truly yours, S. P. Sarver, Director Nuclear Licensing and Operations Support Attachments

cc: U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth St. SW, Suite 23T85 Atlanta, Georgia 30303-8931 Mr. R. A. Musser NRC Senior Resident Inspector Surry Power Station Mr. M. J. Morgan NRC Senior Resident Inspector North Anna Power Station

NRC FORM 536 U.S NUCLEAR REGULATORY COMMISSION APPROVED BY 0MB NO 3150-0131 EXPIRES 07/31/2002 (8-2000) Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources for operator examinations. Send comments regarding burden OPERATOR LICENSING estimate to the Records Management Branch (T-6 E6) U S Nuclear Regulatory Commission, Washington, DC 20555-0001 or by intemet email to EXAMINATION DATA bjs@nrm.gov and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget Washington, DC 20503. If a means used to impose an information collection does not display a currently valid 0MB control number the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY NRC REGION Surry Power Station Region II A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 2003 CY 2004 CY 2005 CY 2006 ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS ESTIMATED NUMBER OF 1 1 NRC-PREPARED EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 2003 CY 2004 CY 2005 CY 2006 NUMBER OF REACTOR 8 10 OPERATORS NUMBER OF SENIOR REACTOR 2 6 OPERATORS-INSTANT NUMBER OF SENIOR REACTOR 4 4 OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR OPERATORS-LIMITED PROPOSED DATES PRIMARY DATE February 23, 2004 October 24, 2005 ALTERNATE DATE March 1, 2004 October 31, 2005 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE cY 2003 CY 2004 PROPOSED NUMBER FIRST SECOND THIRD FIRST SECOND THIRD ESTIMATED NUMBER OF CANDIDATES 10 16 RNE NRCCE AE il OMWSDSGE SN NOM 131-00 NR FOR NRC FORM 536 (8-2000) PRINTED ON RECYCLED PAPER THIS FORM WAS DESIGNED USING INFORMS

NRC FORM 536 U.S NUCLEAR REGULATORY COMMISSION APPROVED BY 0MB NO 3150-0131 EXPIRES 07/31/2002 (8-2000) Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. Tis information collection is used to plan budgets and resources for operator examinations. Send comments regarding burden OPERATOR LICENSING estimate to the Records Management Branch (T-6 E6) U S Nuclear EDRegulatory Commission, Washington, DC 20555-0001 or by internet email to EXAMINATION DATA bjSlnrc.govs and to the Desk fficer, Office of Information and Regulatory Affairs, NEOb-10202, (3150-0131), Office of Management and Budget Washington, DC 20503. If a means used to impose an information collection does not display a currently valid 0MB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY NRC REGION North Anna Power Station Region II A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 2003 CY 2004 CY 2005 CY 2006 ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 1 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 2003 CY 2004 CY 2005 CY 2006 NUMBER OF REACTOR 8 8 OPERATORS NUMBER OF SENIOR REACTOR 2 2 OPERATORS-INSTANT NUMBER OF SENIOR REACTOR 6 6 OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR OPERATORS-LIMITED PROPOSED DATES PRIMARY DATE June 21, 2004 June 19, 2006 ALTERNATE DATE June 28, 2004 June 26, 2006 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2003 CY 2004 PROPOSED NUMBER FIRST SECOND THIRD FIRST SECOND THIRD ESTIMATED NUMBER OF CANDIDATES 10 10 NRC FORM 536 (8-2000) PRINTED ON RECYCLED PAPER THIS FORM WAS DESIGNED USING INFORMS