Schedule for RAI Responses
- Noel, The St. Lucie license renewal RAI letters require that FPL provide within 30 days of receipt a schedule for responses to the RAIs. The attached serves as formal notification of our response schedule to the following RAI letters:
July 1, 2002 - LRA Sections 2.0, 3.0, 4.0, and Appendix B July 1, 2002 - LRA Section 3.3 July 18, 2002 July 29, 2002 If you have any questions, please call.
Steve (See attached file: St Lucie License Renewal RAI Response Schedule.doc)
CC:
<Jack_Hoffman@fpl.com>, <Tony_Menocal@fpl.com>, <Fidel_Prieto@fpl.com>,
<Bruce_Beisler@fpl.com>, <David_T_Joy@fpl.com>, <Howard_Onorato@fpl.com>,
<George_Madden@fpl.com>
From:
<Steve_Hale@fpl.com>
Steve Hale, Florida Power and Light To:
<NFD@nrc.gov>
Noel Dudley, NRC/NRR/DRIP/RLEP Date:
7/31/02 11:30AM
Subject:
Schedule for RAI Responses
- Noel, The St. Lucie license renewal RAI letters require that FPL provide within 30 days of receipt a schedule for responses to the RAIs. The attached serves as formal notification of our response schedule to the following RAI letters:
July 1, 2002 - LRA Sections 2.0, 3.0, 4.0, and Appendix B July 1, 2002 - LRA Section 3.3 July 18, 2002 July 29, 2002 If you have any questions, please call.
Steve (See attached file: St Lucie License Renewal RAI Response Schedule.doc)
CC:
<Jack_Hoffman@fpl.com>, <Tony_Menocal@fpl.com>, <Fidel_Prieto@fpl.com>,
<Bruce_Beisler@fpl.com>, <David_T_Joy@fpl.com>, <Howard_Onorato@fpl.com>,
<George_Madden@fpl.com>
Docket Nos. 50-335 and 50-389
Enclosure:
As stated cc w/encl: See next page DISTRIBUTION: See next page Document Name:C:\\ORPCheckout\\FileNET\\ML022130514.wpd OFFICE PM:RLEP LA:RLEP NAME NDudley HBerilla DATE 08/1/02 08/1/02 OFFICIAL RECORD COPY
ST. LUCIE LICENSE RENEWAL RAI RESPONSE SCHEDULE 7/31/02 LRA SEC LRA SECTION TITLE OF RAIs NRC LTR FPL LTR L-2002 DRAFT RAI RESPONS E DATE NRC MEETING DATE FINAL RAI
RESPONSE
DATE 2.1 Scoping and Screening Methodology 3
7/1/02 (LRA Sec. 2, 3, 4, App B) 139 7/19/02 (Actual) 8/15-16/02 10/11/02 (9/6/02 TARGET) 2.2 2.3 2.4 2.5 Plant Level Scoping Results Scoping and Screening Results-Mechanical Systems Scoping and Screening Results-Structures Scoping and Screening Results-Elec/I&C Systems 52 7/1/02 (LRA Sec. 2, 3, 4, App B) 7/18/02 7/29/02 144 8/2/02 8/15-16/02 10/11/02 (9/6/02 TARGET) 3.1 3.2 3.4 3.5 3.6 AMR Results-Reactor Coolant Systems AMR Results-Engineered Safety Features Systems AMR Results-Steam and Power Conversion Systems AMR Results-Structures and Structural Components AMR Results-Electrical and I&C 24 7/1/02 (LRA Sec. 2, 3, 4, App B) 7/18/02 TBD LTR #3 8/2/02 TBD 10/11/02 (9/20/02 TARGET) 3.3 AMR Results-Auxiliary Systems 31 7/1/02 LRA Sec.3.3 TBD LTR #4 8/9/02 TBD 10/11/02 (9/20/02 TARGET)
APP B
Aging Management Programs 30 7/1/02 (LRA Sec. 2, 3, 4, App B) 7/18/02 7/29/02 TBD LTR #5 8/23/02 TBD 10/11/02 (9/27/02 TARGET) 4 Time-Limited Aging Analyses 15 7/1/02 (LRA Sec. 2, 3, 4, App B) 7/18/02 TBD LTR #6 8/23/02 TBD 10/11/02 (9/27/02 TARGET)