ML022110540

From kanterella
Jump to navigation Jump to search

Notice of Consideration of Issuance of Amendments Proposed to Change Implementation Date of the Improved Technical Specifications
ML022110540
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 07/19/2002
From: Stephen Monarque
NRC/NRR/DLPM/LPD2
To: Christian D
Virginia Electric & Power Co (VEPCO)
Monarque S, NRR/DLPM, 415-1544
References
07/25/2002 #67 FR 48679, TAC MB5637, TAC MB5638
Download: ML022110540 (9)


Text

Mr. David A. Christian July 19, 2002 Sr. Vice President and Chief Nuclear Officer Virginia Electric and Power Company 5000 Dominion Blvd.

Glen Allen, Virginia 23060

SUBJECT:

NORTH ANNA POWER STATION, UNITS 1 AND 2 - NOTICE OF CONSIDERATION OF ISSUANCE OF AMENDMENTS TO FACILITY OPERATING LICENSES, PROPOSED NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION, AND OPPORTUNITY FOR A HEARING (TAC NOS. MB5637 AND MB5638)

Dear Mr. Christian:

Enclosed is a copy of a Notice of Consideration of Issuance of Amendments to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing for your information. This notice relates to your application dated July 18, 2002, in which you proposed to change the implementation date of the Improved Technical Specifications for North Anna Power Station, Units 1 and 2.

This notice has been forwarded to the Office of the Federal Register for publication.

Sincerely,

/RA/

Stephen Monarque, Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-338 and 50-339

Enclosure:

Notice cc w/encl: See next page

Mr. David A. Christian July 19, 2002 Sr. Vice President and Chief Nuclear Officer Virginia Electric and Power Company 5000 Dominion Blvd.

Glen Allen, Virginia 23060

SUBJECT:

NORTH ANNA POWER STATION, UNITS 1 AND 2 - NOTICE OF CONSIDERATION OF ISSUANCE OF AMENDMENTS TO FACILITY OPERATING LICENSES, PROPOSED NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION, AND OPPORTUNITY FOR A HEARING (TAC NOS. MB5637 AND MB5638)

Dear Mr. Christian:

Enclosed is a copy of a Notice of Consideration of Issuance of Amendments to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing for your information. This notice relates to your application dated July 18, 2002, in which you proposed to change the implementation date of the Improved Technical Specifications for North Anna Power Station, Units 1 and 2.

This notice has been forwarded to the Office of the Federal Register for publication.

Sincerely,

/RA/

Stephen Monarque, Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-338 and 50-339

Enclosure:

Notice cc w/encl: See next page DISTRIBUTION:

PUBLIC JNakoski OGC PDII-1 Rdg SMonarque (Hard Copy)

ACRS/ACNW HBerkow EDunnington (Hard Copy)

KLandis, RII ADAMS ACCESS.NO.ML022110540 OFFICE PM:PDII/S1 LA:PDII/S2 SC:PDII/S1 NAME SMonarque Dunnington JNakoski DATE 7/19/02 7/19/02 7/19/02 COPY Yes/No Yes/No Yes/No OFFICIAL RECORD COPY

7590-01-P UNITED STATES NUCLEAR REGULATORY COMMISSION VIRGINIA ELECTRIC AND POWER COMPANY DOCKET NOS. 50-338 AND 50-339 NOTICE OF CONSIDERATION OF ISSUANCE OF AMENDMENTS TO FACILITY OPERATING LICENSES, PROPOSED NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION, AND OPPORTUNITY FOR A HEARING The U.S. Nuclear Regulatory Commission (the Commission) is considering issuance of amendments to Facility Operating License Nos. NPF-4 and NPF-7 issued to Virginia Electric and Power Company (the licensee) for operation of the North Anna Power Station, Units 1 and 2, located in Louisa County, Virginia.

The proposed amendments would permit the licensee to delay the effective implementation date of the Improved Technical Specifications from no later than September 2, 2002, to no later than December 20, 2002.

Before issuance of the proposed license amendments, the Commission will have made findings required by the Atomic Energy Act of 1954, as amended (the Act), and the Commissions regulations.

The Commission has made a proposed determination that the amendments request involves no significant hazards consideration. Under the Commissions regulations in Title 10 of the CODE OF FEDERAL REGULATIONS (10 CFR), Section 50.92, this means that operation of the facility in accordance with the proposed amendments would not (1) involve a significant increase in the probability or consequences of an accident previously evaluated; or (2) create the possibility of a new or different kind of accident from any accident previously evaluated; or (3) involve a significant reduction in a margin of safety. As required by 10 CFR 50.91(a), the

licensee has provided its analysis of the issue of no significant hazards consideration, which is presented below:

1. Do the proposed changes involve a significant increase in the probability or consequences of an accident previously evaluated?

The proposed changes delay implementation of the Improved Technical Specifications (ITS) to permit completion of system modifications and final functional testing of the Control Room Bottled Air System. The proposed changes are administrative in nature in that they simply delay implementation of ITS for four months. Until the ITS are implemented the current Technical Specifications will remain in effect. Since the changes are administrative, they will not alter the operation or otherwise increase the failure probability of any plant equipment that initiates an analyzed accident. As a result, the probability of any accident previously evaluated is not significantly increased. The changes will not affect the design, function or operation of any system, structure or component nor will it affect any maintenance, modification or testing activities. Thus, there will be no impact on the capability of any structure, system or component to perform its intended safety function. Therefore, it is concluded that operation in accordance with the proposed changes will not involve a significant increase in the probability or consequences of accidents previously analyzed.

2. Do the proposed changes create the possibility of a new or different kind of accident from any accident previously evaluated?

Deferral of the ITS implementation date is an administrative change. As such the changes do not involve a physical alteration of the plant (no new or different type of equipment will be installed) or a change in the methods governing normal plant operation. Thus, these changes do not create the possibility of a new or different kind of accident from any accident previously evaluated.

3. Do the proposed changes involve a significant reduction in a margin of safety?

Deferral of the ITS implementation date is an administrative change. The proposed changes do not affect the plant design or operations. The changes do not eliminate any requirements or impose any new requirements or alter any physical parameters, which could reduce the margin to an identified acceptance limit. Hence, these changes do not involve a significant reduction in the margin of safety.

The NRC staff has reviewed the licensees analysis and, based on this review, it appears that the three standards of 10 CFR 50.92(c) are satisfied. Therefore, the NRC staff proposes to determine that the amendments request involves no significant hazards consideration.

The Commission is seeking public comments on this proposed determination. Any comments received within 30 days after the date of publication of this notice will be considered in making any final determination.

Normally, the Commission will not issue the amendments until the expiration of the 30-day notice period. However, should circumstances change during the notice period such that failure to act in a timely way would result, for example, in derating or shutdown of the facility, the Commission may issue the license amendments before the expiration of the 30-day notice period, provided that its final determination is that the amendments involve no significant hazards consideration. The final determination will consider all public and State comments received. Should the Commission take this action, it will publish in the FEDERAL REGISTER a notice of issuance and provide for opportunity for a hearing after issuance. The Commission expects that the need to take this action will occur very infrequently.

Written comments may be submitted by mail to the Chief, Rules and Directives Branch, Division of Administrative Services, Office of Administration, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, and should cite the publication date and page number of this FEDERAL REGISTER notice. Written comments may also be delivered to Room 6D59, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland, from 7:30 a.m.

to 4:15 p.m. Federal workdays. Documents may be examined, and/or copied for a fee, at the NRCs Public Document Room, located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland.

The filing of requests for hearing and petitions for leave to intervene is discussed below.

By August, 2002, the licensee may file a request for a hearing with respect to issuance of the amendments to the subject facility operating licenses and any person whose interest may be affected by this proceeding and who wishes to participate as a party in the proceeding must file a written request for a hearing and a petition for leave to intervene.

1 The most recent version of Title 10 of the Code of Federal Regulations, published January 1, 2002, inadvertently omitted the last sentence of 10 CFR 2.714(d) and subparagraphs (d)(1) and (2), regarding petitions to intervene and contentions. Those provisions are extant and still applicable to petitions to intervene. Those provisions are as follows: "In all other circumstances, such ruling body or officer shall, in ruling on--

(1) A petition for leave to intervene or a request for hearing, consider the following factors, among other things:

(i) The nature of the petitioners right under the Act to be made a party to the proceeding.

(ii) The nature and extent of the petitioners property, financial, or other interest in the proceeding.

(iii) The possible effect of any order that may be entered in the proceeding on the petitioners interest.

(2) The admissibility of a contention, refuse to admit a contention if:

(i) The contention and supporting material fail to satisfy the requirements of paragraph (b)(2) of this section; or (ii) The contention, if proven, would be of no consequence in the proceeding because it would not entitle petitioner to relief."

Requests for a hearing and a petition for leave to intervene shall be filed in accordance with the Commissions "Rules of Practice for Domestic Licensing Proceedings" in 10 CFR Part 2.

Interested persons should consult a current copy of 10 CFR 2.714, 1 which is available at the Commissions Public Document Room, located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland, or electronically on the Internet at the NRC Web site http://www.nrc.gov/reading-rm/doc-collections/cfr/. If there are problems in accessing the document, contact the Public Document Room Reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr@nrc.gov. If a request for a hearing or petition for leave to intervene is filed by the above date, the Commission or an Atomic Safety and Licensing Board, designated by the Commission or by the Chairman of the Atomic Safety and Licensing Board Panel, will rule on the request and/or petition; and the Secretary or the designated Atomic Safety and Licensing Board will issue a notice of hearing or an appropriate order.

As required by 10 CFR 2.714, a petition for leave to intervene shall set forth with particularity the interest of the petitioner in the proceeding, and how that interest may be affected by the results of the proceeding. The petition should specifically explain the reasons why intervention should be permitted with particular reference to the following factors: (1) the nature of the petitioners right under the Act to be made party to the proceeding; (2) the nature and extent of the petitioners property, financial, or other interest in the proceeding; and (3) the

possible effect of any order which may be entered in the proceeding on the petitioners interest.

The petition should also identify the specific aspect(s) of the subject matter of the proceeding as to which petitioner wishes to intervene. Any person who has filed a petition for leave to intervene or who has been admitted as a party may amend the petition without requesting leave of the Board up to 15 days prior to the first prehearing conference scheduled in the proceeding, but such an amended petition must satisfy the specificity requirements described above.

Not later than 15 days prior to the first prehearing conference scheduled in the proceeding, a petitioner shall file a supplement to the petition to intervene which must include a list of the contentions which are sought to be litigated in the matter. Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted. In addition, the petitioner shall provide a brief explanation of the bases of the contention and a concise statement of the alleged facts or expert opinion which support the contention and on which the petitioner intends to rely in proving the contention at the hearing. The petitioner must also provide references to those specific sources and documents of which the petitioner is aware and on which the petitioner intends to rely to establish those facts or expert opinion.

Petitioner must provide sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact. Contentions shall be limited to matters within the scope of the amendments under consideration. The contention must be one which, if proven, would entitle the petitioner to relief. A petitioner who fails to file such a supplement which satisfies these requirements with respect to at least one contention will not be permitted to participate as a party.

Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to participate fully in the conduct of the hearing, including the opportunity to present evidence and cross-examine witnesses.

If a hearing is requested, the Commission will make a final determination on the issue of no significant hazards consideration. The final determination will serve to decide when the hearing is held.

If the final determination is that the amendments request involves no significant hazards consideration, the Commission may issue the amendments and make them immediately effective, notwithstanding the request for a hearing. Any hearing held would take place after issuance of the amendments.

If the final determination is that the amendments request involves a significant hazards consideration, any hearing held would take place before the issuance of any amendments.

A request for a hearing or a petition for leave to intervene must be filed with the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention: Rulemakings and Adjudications Staff, or may be delivered to the Commissions Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland, by the above date. Because of the continuing disruptions in delivery of mail to United States Government offices, it is requested that petitions for leave to intervene and requests for hearing be transmitted to the Secretary of the Commission either by means of facsimile transmission to 301-415-1101 or by e-mail to hearingdocket@nrc.gov. A copy of the petition for leave to intervene and request for hearing should also be sent to the Office of the General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, and because of continuing disruptions in delivery of mail to United States Government offices, it is requested that copies be transmitted either by means of facsimile transmission to 301-415-3725 or by e-mail to OGCMailCenter@nrc.gov. A copy of the request for hearing and petition for leave to intervene should also be sent to Ms. Lillian M.

Cuoco, Esq., Senior Nuclear Counsel, Dominion Nuclear Connecticut, Inc., Millstone Power

Station, Building 475, 5th Floor, Rope Ferry Road, Rt. 156, Waterford, Connecticut 06385, attorney for the licensee.

Nontimely filings of petitions for leave to intervene, amended petitions, supplemental petitions and/or requests for hearing will not be entertained absent a determination by the Commission, the presiding officer or the presiding Atomic Safety and Licensing Board that the petition and/or request should be granted based upon a balancing of the factors specified in 10 CFR 2.714(a)(1)(i)-(v) and 2.714(d).

For further details with respect to this action, see the application for amendments dated July 18, 2002, which is available for public inspection at the Commissions PDR, located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible from the Agencywide Documents Access and Management Systems (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS, should contact the NRC PDR Reference staff by telephone at 1-800-397-4209, 301-415-4737, or by e-mail to pdr@nrc.gov.

Dated at Rockville, Maryland, this 19th day of July 2002.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Stephen R. Monarque, Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation

Mr. David A. Christian North Anna Power Station Virginia Electric and Power Company Units 1 and 2 cc:

Mr. C. Lee Lintecum Mr. David A. Heacock County Administrator Site Vice President Louisa County North Anna Power Station P.O. Box 160 P.O. Box 402 Louisa, Virginia 23093 Mineral, Virginia 23117-0402 Ms. Lillian M. Cuoco, Esq.

Senior Nuclear Counsel Mr. Richard H. Blount, II Dominion Nuclear Connecticut, Inc.

Site Vice President Millstone Power Station Surry Power Station Building 475, 5th Floor Virginia Electric and Power Company Rope Ferry Road 5570 Hog Island Road Rt. 156 Surry, Virginia 23883-0315 Waterford, Connecticut 06385 Dr. W. T. Lough Robert B. Strobe, M.D., M.P.H.

Virginia State Corporation State Health Commissioner Commission Office of the Commissioner Division of Energy Regulation Virginia Department of Health P.O. Box 1197 P. O. Box 2448 Richmond, Virginia 23209 Richmond, Virginia 23218 Old Dominion Electric Cooperative Mr. William R. Matthews 4201 Dominion Blvd.

Vice President - Nuclear Operations Glen Allen, Virginia 23060 Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Mr. Stephen P. Sarver, Director Glen Allen, Virginia 23060-6711 Nuclear Licensing & Operations Support Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Blvd.

Glen Allen, Virginia 23060-6711 Office of the Attorney General Commonwealth of Virginia 900 East Main Street Richmond, Virginia 23219 Senior Resident Inspector North Anna Power Station U.S. Nuclear Regulatory Commission 1024 Haley Drive Mineral, Virginia 23117