MONTHYEARML24289A0312024-11-0808 November 2024 – Issuance of Amendments Related to the Removal of License Condition 2.F as Part of the Consolidated Line-Item Improvement Process (CLIIP) IR 05000416/20240032024-11-0606 November 2024 Integrated Inspection Report 05000416/2024003 IR 05000416/20240112024-10-16016 October 2024 – Fire Protection Team Inspection Report 05000416/2024011 ML24263A2712024-09-19019 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements IR 05000416/20240122024-09-17017 September 2024 License Renewal Post Approval Phase 2 Inspection Report 05000416/2024012 ML24257A0172024-09-17017 September 2024 Request for Withholding Information from Public Disclosure Unit 1 ML24254A3602024-09-10010 September 2024 Pre-Submittal Slides for License Amendment Request, Criticality Safety Analysis, Technical Specification 4.3.1, Criticality and Technical Specification 5.5.14, Spent Fuel Storage Rack Neutron Absorber Monitoring Program IR 05000416/20244022024-09-0909 September 2024 Security Baseline Inspection Report 05000416/2024402 05000416/LER-2024-003, Feedwater Inlet Check Valve Incorrectly Determined Operable2024-08-26026 August 2024 Feedwater Inlet Check Valve Incorrectly Determined Operable ML24235A0832024-08-22022 August 2024 Evaluations Performed in Accordance with 10 CFR 50.54(q) for Changes to Emergency Planning Documents IR 05000416/20240052024-08-21021 August 2024 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 IR 05000416/20240022024-07-29029 July 2024 Integrated Inspection Report 05000416/2024002 ML24176A1202024-07-29029 July 2024 Issuance of Amendment 234 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b ML24172A2502024-07-29029 July 2024 – Issuance of Amendment No. 233 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML24204A2432024-07-23023 July 2024 Notification of Cyber Security Baseline Inspection and Request for Information (05000416/2024403) ML24191A2432024-07-0909 July 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operations IR 05000416/20240102024-06-27027 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000416/2024010 ML24156A1762024-06-24024 June 2024 Regulatory Audit Summary in Support of License Amendment Requests to Adopt TSTF-505, Revision 2 and 10 CFR 50.69 (Epids L-2023-LLA-0081 and L-2023-LLA-0080) ML24165A1512024-06-13013 June 2024 Second Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk-Informe ML24163A2652024-06-11011 June 2024 Inservice Inspection Summary Report ML24060A2192024-05-30030 May 2024 Authorization of Alternative to Use EN-RR-01 Concerning Proposed Alternative to Adopt Code Case N-752 05000416/LER-2024-002, Automatic Actuation of Reactor Protection System2024-05-28028 May 2024 Automatic Actuation of Reactor Protection System ML24130A0912024-05-0909 May 2024 Request for Information Letter License Renewal Phase 2 Inspection ML24128A1512024-05-0909 May 2024 Project Manager Assignment ML24128A0422024-05-0707 May 2024 License Amendment Request to Remove Obsolete License Conditions IR 05000416/20240012024-05-0202 May 2024 Integrated Inspection Report 05000416 2024001 ML24122C6112024-05-0101 May 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf. ML24116A0372024-04-25025 April 2024 Report of Technical Specification Bases Changes ML24113A0972024-04-22022 April 2024 Annual Report of Individual Monitoring - NRC Form 5 for 2023 Per 1 0 CFR 20.2206 ML24113A0952024-04-22022 April 2024 Annual Radioactive Effluent Release Report for 2023 ML24107B0402024-04-16016 April 2024 Notification by Entergy Operations, Inc., of Proposed Economic Performance Incentive and Reliance on Post-Event Improvements in Plant Procedures And/Or Methods of Operation in FERC ML24107A8872024-04-16016 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) ML24101A3882024-04-10010 April 2024 Response to Request for Confirmation of Information by the Office of Nuclear Reactor Regulation Proposed Alternative Request EN-RR-22-001 Risk-Informed Categorization and Treatment for Repair ML24100A0692024-04-0909 April 2024 Report of Changes or Errors to 10 CFR 50.46 Analysis ML24094A0992024-04-0303 April 2024 (GGNS) Core Operating Limits Report (COLR) Cycle 25, Revision O ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams 05000416/LER-2024-001, High Pressure Core Spray Inoperable Due to Minimum Flow Valve Failure to Close2024-03-27027 March 2024 High Pressure Core Spray Inoperable Due to Minimum Flow Valve Failure to Close IR 05000416/20220042024-03-19019 March 2024 – Amended Integrated Inspection Report 05000416/2022004 and Exercise of Enforcement Discretion ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) IR 05000416/20230062024-02-28028 February 2024 Annual Assessment Letter for Grand Gulf Nuclear Station - Report 05000416/2023006 ML24058A3512024-02-28028 February 2024 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information IR 05000416/20233012024-02-26026 February 2024 NRC Examination Report 05000416-2023301 05000416/LER-2023-002, Reactor Scram Due to Generator Stator Fault to Ground2024-02-13013 February 2024 Reactor Scram Due to Generator Stator Fault to Ground ML24043A1892024-02-12012 February 2024 Spent Fuel Storage Radioactive Effluent Release Report for 2023 ML24012A1422024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0051 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24043A0732024-01-29029 January 2024 2024-01 Post Examination Comments IR 05000416/20230042024-01-25025 January 2024 Integrated Inspection Report 5000416/2023004 2024-09-09
[Table view] |
Text
Entergy Operations, Inc.
Waterloo Road P.O. Box 756 Port Gibson, MS 39150 Tel 601 437 6299 Charles A. Bottemiller Manager Plant Licensing July 17, 2002 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Attention: Document Control Desk
Subject:
Response to NRC Regulatory Issue Summary 2002-09 "Preparation and Scheduling of Operator Licensing Examinations" Grand Gulf Nuclear Station Docket No. 50-416 License No. NPF-29 GNRO-2002/00062 Ladies and Gentlemen:
NRC Regulatory Issue Summary 2002-09 (GNRI-2002/00062), "Preparation and Scheduling of Operator Licensing Examinations", requests licensees to provide the estimate number of candidates to be examined during calendar years 2002 through 2005 and the estimated number of candidates that will participate in the GFE in calendar years 2003 and 2006.
The updated information for Grand Gulf Nuclear Station is provided in the attached NRC Form 536. This information represents the best estimate currently available.
This letter does not contain any commitments.
If you have any questions or require additional information regarding this matter, please contact Michael Rasch at (601) 437-6362 or Jay Miller at (601) 437-7303.
Yours truly, CAB/AMT:amt attachment: NRC Form 536, "Operator Licensing Examination Data" cc: (See Next Page)
G020062
July 17, 2002 GNRO-2002/00062 Page 2 of 2 cc:
Hoeg T. L. GGNS Senior Resident) (w/o)
Levanway D. E. (Wise Carter) (w/o)
Reynolds N. S. (w/o)
Smith L. J. (Wise Carter) (w/o)
Thomas H. L. (w/o)
U.S. Nuclear Regulatory Commission ATTN: Mr. David H. Jaffe NRR/DLPM ATTN: FOR ADDRESSEE ONLY ATTN: U.S. Postal Delivery Address Only Mail Stop OWFN/7D-1 Washington, D.C. 20555-0001 Mr. Robert M. Gallo (w/o)
Chief Operator Licensing Branch U.S. Nuclear Regulatory Commission Mail Stop OWFN 9D-24 Washington, DC 20555 Mr. Ellis W. Merschoff (w/o)
Regional Administrator U.S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011 Mr. Anthony T. Gody (w/a)
Chief Operations Branch U.S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 G020062
NRC FORM 536 U.S NUCLEAR REGULATORY APPROVED BY 0MB NO 3150-0131 EXPIRES 07/31/2002 COMMISSION (8-2000) Estimated request: 1 burden per information response to comply iswith hour. This collection usedthis voluntary to plan information budgets collection and resources for operator examinations. Send comments regarding burden estimate to the Records Management Branch (T-6 E6) U S Nuclear Regulatory Commission, Washington, DC OPERATOR LICENSING 20555-0001 or by internet email to bjsl@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-1 0202, (3150-0131), Office of Management and EXAMINATION DATA Budget Washington, DC 20503. Ifa means used to impose an information collection does not display a currently valid 0MB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
FACILITY NRC REGION GRAND GULF NUCLEAR STATION FACILITY DOCKET NUMBER 50-416 IV ENTERGY, P.O. BOX 756, PORT GIBSON, MS 39150 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY_03 CY 04 CY 05 CY 06 ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS 1 0 1 0 ESTIMATED NUMBER OF NRC-PREPARED EXAMINATIONS 0 0 0 0 B. INITIAL OPERATOR LICENSING EXAMINATIONS PROPOSED NUMBER CY_03 CY 04 CY 05 CY 06 NUMBER OF REACTOR OPERATORS 0 0 5 0 NUMBER OF SENIOR REACTOR OPERATORS-INSTANT 2 0 3 0 NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE 7 0 0 0 NUMBER OF SENIOR REACTOR OPERATORS-LIMITED 0 0 0 0 PROPOSED DATES PRIMARY DATE SEPTEMBER 2003 N/A AUGUST 2005 N/A ALTERNATE DATE OCTOBER 2003 N/A SEPTEMBER 2005 N/A C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE PROPOSED NUMBER CY 03 CY_04 FIRST SECOND THIRD FIRST SECOND THIRD ESTIMATED NUMBER OF CANDIDATES 14 0 0 0 5 0 RlI F-KVIOOR 536 (8-200) PR*INTE- ON R-E-CYCLL-LDPAPER- THIS FORM WAS DESIGNED USING INFORMS