J. Barnie Beasley, Jr., PE.
Southern Nuclear Vice President Operating Company, Inc.
Vogtle Project 40 Inverness Center Parkway P0 Box 1295 Birmingham, Alabama '5201 Tel 205.992.7110 Fax 205.992.0403 July 15, 2002 COMPANY Energy to Serve Your World"'
LCV-1593-F Docket Nos. 50-424 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555 Gentlemen:
VOGTLE ELECTRIC GENERATING PLANT MONTHLY OPERATING REPORT - JUNE 2002 Enclosed are the June 2002 monthly operating reports for Vogtle Electric Generating Plant (VEGP) Units 1 and 2. These reports are submitted in accordance with the Technical Specification 5.6.4.
Sincerely, easley, Jr JBB/JLL Enclosures El-VEGP Unit 1 Monthly Operating Report - June 2002 E2-VEGP Unit 2 Monthly Operating Report - June 2002 cc:
Southern Nuclear Operating Company Mr. M. Sheibani SNC Document Management U. S. Nuclear Regulatory Commission Mr. L. A. Reyes, Regional Administrator Mr. F. Rinaldi, Project Manager, NRR Mr. J. Zeiler, Senior Resident Inspector, Vogtle
ENCLOSURE 1 VOGTLE ELECTRIC GENERATING PLANT - UNIT 1 MONTHLY OPERATING REPORT FOR JUNE 2002 TABLE OF CONTENTS OPERATING DATA REPORT and CHALLENGES to PORV and SAFETY VALVES Page El-i UNIT SHUTDOWNS and NARRATIVE REPORT Page E1-2
OPERATING DATA REPORT 50-424 VEGP UNIT 1 July 1, 2002 Andrew R. Cato (706) 826-3823 Operating Status
- 1. Reporting Period:
- 2. Design Electrical Rating (Net MWe):
- 3. Maximum Dependable Capacity (Net MWe):
- 4. Number Of Hours Reactor Was Critical:
- 5. Hours Generator On Line:
- 6. Unit Reserve Shutdown Hours:
- 7. Net Electrical Energy Generated (MWHe):
June - 2002 1169 1148 This Month 720.0 720.0 0.0 842,747 CHALLENGES TO PRESSURIZER PORV AND PRESSURIZER SAFETY VALVES E1-1 Docket No.:
Unit Name:
Date:
Completed By:
Telephone:
Year-To-Date 3295.0 3233.1 0.0 3,744,579 Cumulative 117,904.5 116,385.7 0.0 130,190,645 Date Tag No.
Event Description N/A N/A N/A
UNIT SHUTDOWNS Docket No.:
Unit Name:
Date:
Completed By:
Telephone:
Reporting Period:
50-424 VEGP UNIT 1 July 1, 2002 Andrew R. Cato (706) 826-3823 June - 2002 Type Method of Cause/
F: Forced Duration Shutting Corrective Actions No.
Date S: Scheduled (Hours)
Reason (1)
Down (2)
Comments N/A N/A N/A N/A N/A N/A N/A (1) REASON:
(2) METHOD:
A - Equipment Failure (Explain)
E - Operator Training/License Examination
- 1. Manual
- 4. Continuation B - Maintenance or Test F - Administrative
- 2. Manual Trip/Scram
- 5. Other C - Refueling G - Operational Error (Explain)
- 3. Automatic Trip/Scram D - Regulatory Restriction H - Other (Explain)
CAUSEICORRECTIVE ACTIONICOMMENTS:
EVENT CAUSE:
CORRECTIVE ACTION:
CRITICAL PATH WAS:
NARRATIVE REPORT June 01, 2002 00:00 Unit 1 at 100% power with no significant operating problems.
June 14, 2002 10:38 Unit 1 initated planned derate to 90% power for Heater Drain Pump work.
June 14, 2002 18:00 Unit 1 returned to 100% power following completion of Heater Drain Pump work.
June 30, 2002 23:59 Unit 1 at 100% power with no significant operating problems.
E11-2
ENCLOSURE 2 VOGTLE ELECTRIC GENERATING PLANT - UNIT 2 MONTHLY OPERATING REPORT FOR JUNE 2002 TABLE OF CONTENTS OPERATING DATA REPORT and CHALLENGES to PORV and SAFETY VALVES Page E2-1 UNIT SHUTDOWNS and NARRATIVE REPORT Page E2-2
OPERATING DATA REPORT Docket No.:
Unit Name:
Date:
Completed By:
Telephone:
50-425 VEGP UNIT 2 July 1, 2002 Andrew R. Cato (706) 826-3823 Operating Status
- 1. Reporting Period:
- 2. Design Electrical Rating (Net MWe):
- 3. Maximum Dependable Capacity (Net MWe):
- 4. Number Of Hours Reactor Was Critical:
- 5. Hours Generator On Line:
- 6. Unit Reserve Shutdown Hours:
- 7. Net Electrical Energy Generated (MWHe):
June - 2002 1169 1149 This Month 720.0 720.0 0.0 837,553 Year-To-Date 4343.0 4343.0 0.0 5,113,287 CHALLENGES TO PRESSURIZER PORV AND PRESSURIZER SAFETY VALVES E2-1 Cumulative 105,396.8 104,583.7 0.0 117,905,753 Date Tag No.
Event Description N/A N/A N/A
UNIT SHUTDOWNS Docket No.:
Unit Name:
Date:
Completed By:
Telephone:
Reporting Period:
50-425 VEGP UNIT 2 July 1,2002 Andrew R. Cato (706) 826-3823 June -2002 Type Method of Cause/
F: Forced Duration Shutting Corrective Actions No.
Date S: Scheduled (Hours)
Reason (1)
Down (2)
Comments N/A N/A N/A N/A N/A N/A N/A (1) REASON:
(2) METHOD:
A - Equipment Failure (Explain)
E - Operator Training/License Examination
- 1. Manual
- 4. Continuation B - Maintenance or Test F - Administrative
- 2. Manual Trip/Scram
- 5. Other C - Refueling G - Operational Error (Explain)
- 3. Automatic Trip/Scram D - Regulatory Restriction H - Other (Explain)
CAUSE/CORRECTIVE ACTION/COMMENTS:
EVENT CAUSE:
CORRECTIVE ACTION:
CRITICAL PATH WAS:
NARRATIVE REPORT June 01, 2002 00:00 Unit 2 at 100% power with no significant operating problems.
June 30, 2002 23:59 Unit 2 at 100% power with no significant operating problems.
E2-2