April 2002 Monthly Operating Report for Browns Ferry Nuclear Plant
ML022040670
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 05/14/2002
From: Abney T
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML022040670 (8)


Text

Tennessee Valley Authority, Post Office Box 2000, Decatur, Alabama 35609-2000 MIvy 14, 2002 U.S.

Nuclear Regulatory Commission ATTN:

Document Control Desk Mail Stop OWFN, P1-35 Washington, D.C. 20555-0001 Gentlemen:

In the Matter of Tennessee Valley Authority BROWNS FERRY NUCLEAR PLANT (BFN)

APRIL OPERATING REPORT Docket Nos.

50-259 50-260 50-296 2002 MONTHLY The enclosure provides the April 2002 Monthly Operating Report (MOR) as required by BFN Technical Specifications Section 5.6.4.

Only one paper copy of this document is being sent to the NRC Document Control Desk.

If you have any questions concerning this report, please call me at (256) 729-2636.

Sincerel T.

E.

Abney Manager ofJLicen ing

,aTrIndustry A fairs nclosure d:..

See page 2 I

Printed on recycled paper

) )

U.S. Nuclear Regulatory Commission Page 2 May 14, 2002 Enclosure cc (Enclosure):

(Via NRC Electronic Distribution)

Mr.

Kahtan N.

Jabbour, Senior Project Manager U.S. Nuclear Regulatory Commission One White Flint, North (MS 08G9)

Office of Nuclear Reactor Regulation 11555 Rockville Pike Rockville, Maryland 20852-2738 NRC Resident Inspector Browns Ferry Nuclear Plant P.O. Box 149 Athens, Alabama 35611 Regional Administrator U.S.

Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, S.W.,

Suite 23T85 Atlanta, Georgia 30303-8931

ENCLOSURE 1 TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)

MONTHLY OPERATING REPORT APRIL 2002 UNIT 1 DOCKET NUMBER 50-259 LICENSE NUMBER DPR-33 UNIT 2 DOCKET NUMBER 50-260 LICENSE NUMBER DPR-52 UNIT 3 DOCKET NUMBER 50-296 LICENSE NUMBER DPR-68

Docket No.

50-259 Unit Name BFN Unit 1 Date May 9, 2002 Completed By J. E. Wallace Telephone (256) 729-7874 Reporting Period April 2002

1.

Design Electrical Rating (Net MWe):

2.

Maximum Dependable Capacity (MWe-Net)

3.

Number of Hours Reactor was Critical

4.

Hours Generator On-Line

5.

Unit Reserve Shutdown Hours

6.

Net Electrical Energy Generated (MWh)

Month Yr-to-Date Cumulative*

0 0

59521 0

0 58267 0

0 0

0 0

53,796,427

  • Excludes hours under Administration Hold (June 1, 1985 to Present)

OPERATING DATA REPORT Docket No.

50-260 Unit Name BFN Unit 2 Date May 9, 2002 Completed By J. E. Wallace Telephone (256) 729-7874 Reporting Period April 2002

1. Design Electrical Rating (Net MWe):
2.

Maximum Dependable Capacity (MWe-Net) 1120 1118

3.

Number of Hours Reactor was Critical

4.

Hours Generator On-Line

5.

Unit Reserve Shutdown Hours

6.

Net Electrical Energy Generated (MWh)

Month Yr-to-Date Cumulative 530 2690 142,799 523 2683 140,175 0

0 0

598,321 3,025,409 139,266,874 E-2 OPERATING DATA REPORT 1065 0

OPERATING DATA REPORT Docket No.

50-296 Unit Name BFN Unit 3 Date May 9, 2002 Completed By J. E. Wallace Telephone (256) 729-7874 Reporting Period April 2002

1.

Design Electrical Rating (Net MWe):

2.

Maximum Dependable Capacity (MWe-Net)

3.

Number of Hours Reactor was Critical

4.

Hours Generator On-Line

5.

Unit Reserve Shutdown Hours

6.

Net Electrical Energy Generated (MWh)

Month Yr-to-Date Cumulative 512 2,537 99,367 501 2,526 97,943 0

0 0

497,858 2,689,797 99,412,589 E-3 1120 1118

UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH: APRIL 2002 DOCKET NO:

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

50-259 BFN-1 May 9, 2002 J. E. Wallace

(?';ý 779Q-7R74 1

06/01/85 S

719 F

4

_ _I

_ I

~

I I_

I

'F: Forced S: Scheduled Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training and License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain)

N/A N/A N/A Administrative hold to resolve various TVA and NRC concerns.

I I

-

.1 _____________

1 ________________________________________

3Method 1-Manual 2-Manual Scram 3-Automatic Scram 4-Continuation of Existing Outage 5-Reduction 9-Other

SUMMARY

Unit 1 has been on administrative hold since June 1, 1985.

E-4 4 Instructions for Preparation of Data Entry sheets for Licensee Event Report (LER)

(NUREG - 1022)

UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH: APRIL 2002 DOCKET NO:

50-260 UNIT NAME:

BFN-2 DATE:

May 9, 2002 COMPLETED BY:

J. E Wallace TELEPHONE:

(256) 729-7874 2

N/A N/A N/A At 0300 hours0.00347 days <br />0.0833 hours <br />4.960317e-4 weeks <br />1.1415e-4 months <br />, Unit 2 initiated a reactor shutdown for a mid-cycle outage to replace leaking fuel bundles. The Unit was tied to the grid on May 1, 2002, at 0005 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.

I I

I I__

I I

I__

_J_

'Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training and License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain) 3Method 1-Manual 2-Manual Scram 3-Automatic Scram 4-Continuation of Existing SInstructions for Preparation of Data Entry sheets for Licensee Event Report (LER)

(NUREG - 1022)

Outage 5-Reduction 9-Other Unit 2 has operated near 100 percent power without any significant events with the exception noted above.

E-5 2

04/23/02 S

189 B

1F: Forced S: Scheduled

SUMMARY

UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH: APRIL 2002 DOCKET NO:

UNIT NAME:

DATE:

COMPLETED BY:

TII*I.V.Pl:gnV-*N 50-296 BFN-3 May 9, 2002 J. E. Wallace (9 f*

'790Q_7R7A The Unit continued in the Cycle 10 refueling outage which began on March 26, 2002, at 0859 hours0.00994 days <br />0.239 hours <br />0.00142 weeks <br />3.268495e-4 months <br />. The Unit was tied to the grid on April 10, 2002, at 0254 hours0.00294 days <br />0.0706 hours <br />4.199735e-4 weeks <br />9.6647e-5 months <br />.

2 Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training and License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain) 3 Method 1-Manual 2-Manual Scram 3-Automatic Scram 4-Continuation of Existing Outage 5-Reduction 9-Other 4 Instructions for Preparation of Data Entry sheets for Licensee Event Report (LER)

(NUREG - 1022)

SUMMARY

Unit 3 has operated at or near 100 percent available power after power ascension to 100 percent on 4/14/02.

E-6 1

04/01/02 S

218 C

2 N/A N/A N/A 1F: Forced S: Scheduled