May 2002 Monthly Operating Report for Calvert Cliffs Units 1 & 2
ML021710439
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 06/13/2002
From: Nietmann K
Constellation Nuclear
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML021710439 (7)


Text

1650 Calvert Cliffs Parkway Lusby, Maryland 20657 Constellation Nuclear Calvert Cliffs Nuclear Power Plant A Member of the Constellation Energy Group June 13, 2002 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:

SUBJECT:

Document Control Desk Calvert Cliffs Nuclear Power Plant Unit Nos. 1 & 2; Docket Nos. 50-317 & 50-318 May 2002 Operating Data Reports The subject reports are being sent to you as required by Technical Specification 5.6.4.

Should you have questions, please contact Mr. Bruce B. Mrowca at (410) 495-3989.

Very truly yours, General Manager KJN/TWG/bjd Attachments cc:

R. S. Fleishman, Esquire J. E. Silberg, Esquire Director, Project Directorate I-1, NRC D. M. Skay, NRC H. J. Miller, NRC Resident Inspector, NRC R. I. McLean, DNR J. Wright, INPO K. N. Larson, ANI

(/'7 V

/

OPERATING DATA REPORT Docket No.

50-317 Calvert Cliffs Unit 1 June 4, 2002 Prepared by Herman 0. Olsen Telephone: (410)495-6734 REPORTING PERIOD DESIGN ELECTRICAL RATING (NET MWe)

MAXIMUM DEPENDABLE CAP'Y (NET MWe)

MAY 2002 845 825 This month NUMBER OF HOURS REACTOR WAS CRITICAL HOURS GENERATOR ON LINE UNIT RESERVE SHUTDOWN HOURS NET ELECTRICAL ENERGY GENERATED(MWH) 0.0 0.0 0.0 0

Year to-Date 1,104.0 1,102.7 0.0 921,814 Cumulative to Date 178,836.1 175,718.4 0.0 143,443,897

1.
2.
3.

4.

UNIT SHUTDOWNS DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE 50-317 Calvert Cliffs - UI June 6, 2002 Herman 0. Olsen (410) 495-6734 REPORTING MONTH May 2002 SReason:

A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error H - Other 2

Method:

I - Manual 2 - Manual Scram.

3 - Automatic Scram.

4 - Continued 5 - Other NO.

DATE TYPE DURATION REASON' METHOD OF CAUSE/CORRECTIVE ACTIONS F:

FORCED (HOURS)

SHUTTING S:

SCHEDULED DOWN 2 COMMENTS02-001 02/02/15 5

744.0 C

I The unit remained shutdown in a planned refueling outage for the entire month.

DOCKET NO. 50-317 CALVERT CLIFFS - UNIT 1 June 6, 2002

SUMMARY

OF OPERATING EXPERIENCE May 2002 The unit began the month defueled in a planned refueling outage.

The following significant work was completed or in progress during the month:

Reactor vessel reassembled.

Steam Generator replacement.

The unit entered mode 6 (refueling) on 05/13/02 at 1106. Refueling was completed and the unit entered mode 5 on 05/23/02 at 1750.

The unit remained in mode 5 for the remainder of the month.

OPERATING DATA REPORT Docket No.

50-318 Calvert Cliffs Unit 2 June 4, 2002 Prepared by Herman 0. Olsen Telephone: (410)495-6734 REPORTING PERIOD DESIGN ELECTRICAL RATING (NET MWe)

MAXIMUM DEPENDABLE CAP'Y (NET MWe)

MAY 2002 845 835 This month

1. NUMBER OF HOURS REACTOR WAS CRITICAL
2.

HOURS GENERATOR ON LINE

3.

UNIT RESERVE SHUTDOWN HOURS

4. NET ELECTRICAL ENERGY GENERATED (MWH) 744.0 744.0 0.0 639,467 Year-Cumulative to-Date to Date 3,623.0 3,623.0 0.0 3,132,430 172,422.8 170,567.7 0.0 140,238,308

DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE 50-318 Calvert Cliffs-U2 June 6, 2002 Herman 0. Olsen (410) 495-6734 REPORT MONTH May 2002 SReason:

A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error H - Other 2 Method:

1 - Manual 2 - Manual Scram.

3 - Automatic Scram.

4 - Continued 5 - Other UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON' METHOD OF CAUSE/CORRECTIVE ACTIONS F:

FORCED (HOURS)

SHUTTING S:

SCHEDULED DOWN 2 COMMENTS There were no shutdowns this month.

DOCKET NO. 50-318 CALVERT CLIFFS - UNIT 2 June 6, 2002

SUMMARY

OF OPERATING EXPERIENCE May 2002 The unit began the month at 100% reactor power.

On 05/10/02 at 2205 power was reduced to 85% for Main Turbine Valve testing. Following the completion of testing, reactor power was returned to 100% on 05/11/02 at 0200.

The unit operated at 100% power for the remainder of the month.