Minutes of Internal Meeting of Davis-Besse Nuclear Power Station IMC 0350 Panel Regarding Implementation of IMC 0350 Process for Davis-Besse
ML021490262
Person / Time
Site: Davis Besse 
Issue date: 05/28/2002
From: Grobe J
NRC/RGN-III
To:
References
FOIA/PA-2005-0261
Download: ML021490262 (4)


Text

May 28, 2002 MEMORANDUM TO:

Davis-Besse Nuclear Power Station IMC 0350 Panel FROM:

John A. Grobe, Director, DRS /RA/

SUBJECT:

MINUTES OF INTERNAL MEETING OF THE DAVIS-BESSE NUCLEAR POWER STATION IMC 0350 PANEL The implementation of the IMC 0350 process for the Davis-Besse Nuclear Power Station was announced on April 29, 2002. An internal panel meeting was held May 9. Attached for your information are the minutes from the internal meeting of the IMC 0350 panel.

Attachment:

As stated cc w/att:

H. Nieh, OEDO W. Dean, NRR A. Mendiola, NRR D. Pickett, NRR S. Bloom, NRR G. Grant, RIII S. Reynolds, RIII C. Lipa, RIII L. Collins, RIII D. Simpkins, RIII J. Jacobson, RIII S. Burgess, RIII S. Thomas, RIII

MEMORANDUM TO:

Davis-Besse Nuclear Power Station IMC 0350 Panel FROM:

John A. Grobe, Director, DRS

SUBJECT:

MINUTES OF INTERNAL MEETING OF THE DAVIS-BESSE NUCLEAR POWER STATION IMC 0350 PANEL The implementation of the IMC 0350 process for the Davis-Besse Nuclear Power Station was announced on April 29, 2002. An internal panel meeting was held May 9. Attached for your information are the minutes from the internal meeting of the IMC 0350 panel.

Attachment:

As stated cc w/att:

H. Nieh, OEDO W. Dean, NRR A. Mendiola, NRR D. Pickett, NRR S. Bloom, NRR G. Grant, RIII S. Reynolds, RIII C. Lipa, RIII L. Collins, RIII D. Simpkins, RIII J. Jacobson, RIII S. Burgess, RIII S. Thomas, RIII DOCUMENT NAME: G:\\Davis-Besse 0350\\internalmtgminutes0509.wpd To receive a copy of this document, indicate in the box:"C" = Copy without enclosure "E"= Copy with enclosure"N"= No copy OFFICE RIII RIII RIII NAME LCollins:dtp Clipa JGrobe DATE 05/28/02 05/28/02 05/28/02 OFFICIAL RECORD COPY

MEETING MINUTES:

Internal IMC 0350 Restart Panel Meeting Davis-Besse Nuclear Power Station DATE:

May 9, 2002 TIME:

3:00 pm (Central)

ATTENDEES:

S. Bloom S. Burgess T. Chan D. Coe S. Coffin L. Collins W. Dean J. Grobe J. Jacobson M. Johnson C. Lipa A. Mendiola D. Pickett D. Simpkins Agenda Items:

At the beginning of the meeting Jim Dyer addressed the panel members to lay out expectations and to discuss the challenges facing the panel during the IMC 0350 process.

1.

Reports from Staff Repair/Replacement Plans (DE)

DE staff and the panel discussed the panels role in the technical review of any repair or replacement submitted to the NRC. The panel will have no technical involvement in the review but needs to maintain awareness of the process and in particular, any dissenting views regarding the processing of the licensing decision. The panel needs to be briefed prior to issuing any licensing action.

Risk Analysis (DSSA/SRA)

S. Long and S. Burgess discussed the SDP phase 3 evaluation that is currently underway. The TIA sent in from Region III was accepted. RES is performing technical evaluations to determine the pressure at which the as found cavity would fail and also how large the cavity would need to be to fail at normal operating pressure. RES is also looking at how fast the cavity might have been expanding with time. The results of these evaluations will be used in the SDP phase 3 assessment.

The licensees response to the RAI was extended to June 7. This was communicated to the NRC on the weekly calls between the licensee and NRR.

Allegations/Investigations (EICS, OI)

This item was not discussed.

Licensing Issues/Actions (DLPM)

The petition review board met today to discuss a 2.206 petition that was received.

Two green ticket items were discussed.

A revision to the Confirmatory Action Letter was discussed.

2.

IMC 0350 Panel Business Inspection Schedule This item was not discussed.

Process Plan/Restart Checklist Updates This item was not discussed. The panel agreed to review the process plan line by line at the next panel meeting.

3.

Utilization of the Web Page This item was not discussed.

4.

Future Activities/Plans/Meetings This item was not discussed.

5.

Discuss how to handle public or staff comments, questions, allegations, and concerns received by phone, fax, letter, email, or at public meetings.