J. Barnie Beasley, Jr., P.E.
Vice President Vogtle Project Southern Nuclear Operating Company, Inc.
40 Inverness Center Parkway P0. Box 1295 Birmingham, Alabama 35201 Tel 205.992.7110 Fax 205.992.0403 4ar SOUTHERNA COMPANY Energy to Serve Your World7 LCV-1593-D May 13, 2002 Docket Nos.
50-424 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555 Gentlemen:
VOGTLE ELECTRIC GENERATING PLANT MONTHLY OPERATING REPORT - APRIL 2002 Enclosed are the April 2002 monthly operating reports for Vogtle Electric Generating Plant (VEGP) Units 1 and 2. These reports are submitted in accordance with the Technical Specification 5.6.4.
Sincerely, 1-[
elyJ JBB/JLL Enclosures El-VEGP Unit 1 Monthly Operating Report - April 2002 E2-VEGP Unit 2 Monthly Operating Report - April 2002 cc:
Southern Nuclear Operating Company Mr. M. Sheibani SNC Document Management U. S. Nuclear Regulatory Commission Mr. L. A. Reyes, Regional Administrator Mr. F. Rinaldi, Project Manager, NRR Mr. J. Zeiler, Senior Resident Inspector, Vogtle
ENCLOSURE 1 VOGTLE ELECTRIC GENERATING PLANT - UNIT 1 MONTHLY OPERATING REPORT FOR APRIL 2002 TABLE OF CONTENTS OPERATING DATA REPORT and CHALLENGES to PORV and SAFETY VALVES Page El-i UNIT SHUTDOWNS and NARRATIVE REPORT Page E1-2
OPERATING DATA REPORT Docket No.:
Unit Name:
Date:
Completed By:
Telephone:
- 1. Reporting Period:
- 2. Design Electrical Rating (Net MWe):
- 3. Maximum Dependable Capacity (Net MWe):
- 4. Number Of Hours Reactor Was Critical:
- 5. Hours Generator On Line:
- 6. Unit Reserve Shutdown Hours:
- 7. Net Electrical Energy Generated (MWHe):
50-424 VEGP UNIT 1 May 1, 2002 Andrew R. Cato (706) 826-3823 April - 2002 1169 1148 This Month 293.5 231.5 0.0 220,217 Year To Date 1831.0 1769.1 0.0 2,024,229 CHALLENGES TO PRESSURIZER PORV AND PRESSURIZER SAFETY VALVES EI-1 Operating Status Cumulative 116,440.5 114,921.7 0.0 128,470,295 Date Tag No.
Event Description N/A N/A N/A
UNIT SHUTDOWNS Reporting Period:
Docket No.:
Unit Name:
Date:
Completed By:
Telephone:
April - 2002 50-424 VEGP UNIT 1 May 1, 2002 Andrew R. Cato (706) 826-3823 Type Method of F: Forced Duration Shutting Cause/Corrective Actions No.
Date S: Scheduled (Hours)
Reason (1)
Down (2)
Comments 2002-01 3/6/02 S
452.9 C
4 See Below 2002-02 4/19/02 F
33.32 B
2 See Below 2002-03 4/21/02 S
1.29 B
2 See Below (1) REASON:
(2) METHOD:
A - Equipment Failure (Explain)
E - Operator Training/License Examination
- 1. Manual
- 4. Continuation B - Maintenance or Test F - Administrative
- 2. Manual Trip/Scram
- 5. Other C - Refueling G - Operational Error (Explain)
- 3. Automatic Trip/Scram D - Regulatory Restriction H - Other (Explain)
CAUSE/CORRECTIVE ACTION/COMMENTS:
EVENT 2002-01 CAUSE:
Scheduled Refueling Outage CORRECTIVE ACTION:
Cooldown to 110 Deg. F, vessel disassembly, fuel off load, mid-loop maintenance, re-load core, reassemble vessel, fill and vent reactor vessel, and complete prerequisites for mode changes.
CRITICAL PATH WAS:
Vessel disassembly, fuel off load, mid-loop work, fuel load and vessel reassembly, Turbine Rotor replacement, and Main Generator rewind.
EVENT 2002-02 CAUSE:
Forced Outage due to high vibration on Main Turbine bearing #7. Vibration was induced through the opening of steam dump valve 1-PV -507C. There was a subsequent Reactor trip due to operational problems with Steam Generator Water Level Control.
CORRECTIVE ACTION:
Steam Dump repair, return unit to service. Reference LER 1-2002-03 for actions associated with the reactor trip.
CRITICAL PATH WAS:
Stabilize plant, isolate steam dump, reactor trip recovery, unit startup.
EVENT 2002-03 CAUSE:
Scheduled Turbine Overspeed Trip Surveillance Test CORRECTIVE ACTION:
Performed Overspeed Trip Test CRITICAL PATH WAS:
Overspeed Trip Test NARRATIVE REPORT E1-2 April 01, 2002 00:00 Unit 1 in Mode 6. Preparing for Reactor Head set.
April 03, 2002 09:40 Unit 1 in Mode 5. First Reactor Stud tensioned.
April 06, 2002 09:04 Unit 1 in Mode 4.
April 07, 2002 15:45 Unit 1 in Mode 3.
April 08, 2002 17:37 Unit 1 in Mode 2. Reactor is critical.
April 08, 2002 23:34 Unit 1 in Mode 3. Low power physics testing complete, awaiting completion of turbine maintenance.
April 18, 2002 09:13 Unit 1 in Mode 2.
April 18, 2002 10:26 Unit 1 Reactor is critical.
April 19, 2002 13:08 Unit 1 in Mode 1.
April 19, 2002 21:52 Unit 1 is tied to the grid.
April 19, 2002 23:09 Unit I Turbine is manually tripped due to high vibration on bearing #7.
April 20, 2002 05:12 Unit 1 Reactor manually tripped due to high Steam Generator Water Level. Unit in Mode 3.
April 20, 2002 18:17 Unit 1 in Mode 2.
April 20, 2002 19:14 Unit 1 Reactor is critical.
April 21, 2002 02:53 Unit 1 in Mode 1.
April 21, 2002 08:28 Unit 1 is tied to the grid.
April 21, 2002 20:42 Unit 1 Turbine is tripped for Overspeed Trip Test Surveillance.
April 21, 2002 21:59 Unit 1 is tied to the grid.
April 24, 2001 18:00 Unit 1 at 100%.
April 30, 2001 23:59 Unit 1 at 100% power with no significant operating problems.
ENCLOSURE 2 VOGTLE ELECTRIC GENERATING PLANT - UNIT 2 MONTHLY OPERATING REPORT FOR APRIL 2002 TABLE OF CONTENTS OPERATING DATA REPORT and CHALLENGES to PORV and SAFETY VALVES Page E2-1 UNIT SHUTDOWNS and NARRATIVE REPORT Page E2-2
OPERATING DATA REPORT Docket No.:
Unit Name:
Date:
Completed By:
Telephone:
50-425 VEGP UNIT 2 May 1, 2002 Andrew R. Cato (706) 826-3823 Operating Status
- 1. Reporting Period:
- 2. Design Electrical Rating (Net MWe):
- 3. Maximum Dependable Capacity (Net MWe):
- 4. Number Of Hours Reactor Was Critical:
- 5. Hours Generator On Line:
- 6. Unit Reserve Shutdown Hours:
- 7. Net Electrical Energy Generated (MWHe):
April - 2002 1169 1149 This Month 719.0 719.0 0.0 842,814 Year To Date 2879.0 2879.0 0.0 3,404,525 CHALLENGES TO PRESSURIZER PORV AND PRESSURIZER SAFETY VALVES E2-1 Cumulative 103,932.8 103,119.7 0.0 116,196,991 Date Tag No.
Event Description N/A N/A N/A
UNIT SHUTDOWNS Reporting Period:
Docket No.:
Unit Name:
Date:
Completed By:
Telephone:
50-425 VEGP UNIT 2 May 1, 2002 Andrew R. Cato (706) 826-3823 April - 2002 Type Method of F: Forced Duration Shutting Cause/Corrective Actions No.
Date S: Scheduled (Hours)
Reason (1)
Down (2)
Comments N/A N/A N/A N/A N/A N/A N/A (1) REASON:
(2) METHOD:
A - Equipment Failure (Explain)
E - Operator Training/License Examination
- 1. Manual
- 4. Continuation B - Maintenance or Test F - Administrative
- 2. Manual Trip/Scram
- 5. Other C - Refueling G - Operational Error (Explain)
- 3. Automatic Trip/Scram D - Regulatory Restriction H - Other (Explain)
CAUSEJCORRECTIVE ACTIONICOMMENTS:
EVENT CAUSE:
CORRECTIVE ACTION:
CRITICAL PATH WAS:
NARRATIVE REPORT April 01, 2002 00:00 Unit 2 at 100% power with no significant operating problems.
April 30, 2002 23:59 Unit 2 at 100% power with no significant operating problems.
E2-2