May 3, 2002 Mr. Mark Reddemann Site Vice President Kewaunee and Point Beach Nuclear Plants Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241
SUBJECT:
ELECTRIC POWER RESEARCH INSTITUTE (EPRI) REPORT TR-113594, RESOLUTION OF GENERIC LETTER 96-06 WATERHAMMER ISSUES, VOLUMES 1 AND 2 (TAC NOS. M96852 AND M95853)
Dear Mr. Reddemann:
The Nuclear Regulatory Commissions (NRCs) Generic Letter (GL) 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions, dated September 30, 1996, requested that licensees evaluate, among other things, waterhammer and two-phase flow concerns associated with containment air cooler cooling water systems. Your remaining actions to fully address these concerns were deferred pending NRC review and approval of EPRI Report TR-113594, Resolution of Generic Letter 96-06 Waterhammer Issues, Volumes 1 and 2. The purpose of this letter is to inform you that we have completed our review and determined that use of EPRI Report TR-113594 for evaluating the GL 96-06 waterhammer issues is acceptable to the extent specified and within the limitations delineated in the EPRI report and the associated NRC safety evaluation. A copy of our April 3, 2002, acceptance letter to EPRI, which includes the NRC safety evaluation, is enclosed for your information. We request that you complete your actions to address GL 96-06 and submit the information referred to in Section 3.3 of the NRC safety evaluation by July 30, 2002.
Please contact me at (301) 415-2928 to make alternate arrangements if you are unable to meet this schedule.
Sincerely,
/RA/
Deirdre W. Spaulding, Acting Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Enclosure:
NRC letter to EPRI, dated April 3, 2002 cc w/encl: See next page
May 3, 2002 Mr. Mark Reddemann Site Vice President Kewaunee and Point Beach Nuclear Plants Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241
SUBJECT:
ELECTRIC POWER RESEARCH INSTITUTE (EPRI) REPORT TR-113594, RESOLUTION OF GENERIC LETTER 96-06 WATERHAMMER ISSUES, VOLUMES 1 AND 2 (TAC NOS. M96852 AND M95853)
Dear Mr. Reddemann:
The Nuclear Regulatory Commissions (NRCs) Generic Letter (GL) 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions, dated September 30, 1996, requested that licensees evaluate, among other things, waterhammer and two-phase flow concerns associated with containment air cooler cooling water systems. Your remaining actions to fully address these concerns were deferred pending NRC review and approval of EPRI Report TR-113594, Resolution of Generic Letter 96-06 Waterhammer Issues, Volumes 1 and 2. The purpose of this letter is to inform you that we have completed our review and determined that use of EPRI Report TR-113594 for evaluating the GL 96-06 waterhammer issues is acceptable to the extent specified and within the limitations delineated in the EPRI report and the associated NRC safety evaluation. A copy of our April 3, 2002, acceptance letter to EPRI, which includes the NRC safety evaluation, is enclosed for your information. We request that you complete your actions to address GL 96-06 and submit the information referred to in Section 3.3 of the NRC safety evaluation by July 30, 2002.
Please contact me at (301) 415-2928 to make alternate arrangements if you are unable to meet this schedule.
Sincerely,
/RA/
Deirdre W. Spaulding, Acting Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Enclosure:
NRC letter to EPRI, dated April 3, 2002 cc w/encl: See next page DISTRIBUTION:
PUBLIC PDIII-1 Reading DSpaulding RBouling OGC ACRS JTatum RLanksbury, RIII ADAMS Accession No.: ML021220036 OFFICE PDIII-1/PM(A)
PDIII-1/LA PDIII-1/SC NAME DSpaulding RBouling LRaghavan DATE 05/03/02 05/03/02 05/03/02 OFFICIAL AGENCY RECORD
Point Beach Nuclear Plant, Units 1 and 2 cc:
Mr. John H. ONeill, Jr.
Shaw, Pittman, Potts & Trowbridge 2300 N Street, NW Washington, DC 20037-1128 Mr. Richard R. Grigg President and Chief Operating Officer Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 Site Licensing Manager Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Ken Duveneck Town Chairman Town of Two Creeks 13017 State Highway 42 Mishicot, WI 54228 Chairman Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 Ms. Sarah Jenkins Electric Division Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Mr. Roy A. Anderson Executive Vice President and Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Nuclear Asset Manager Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 March 2002