Exe I m.
Exelon Generation Company, LLC www.exeloncorp.com N uclear Ouad Cities Nuclear Power Station 22710 206" Avenue North Cordova, IL 61242-9740 April 15, 2002 SVP-02-035 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Quad Cities Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265
Subject:
Monthly Operating Report In accordance with Generic Letter 97-02 and Technical Specification 5.6.4, "Monthly Operating Reports," we are submitting the Monthly Operating Report for Quad Cities Nuclear Power Station, Units 1 and 2. This report covers the period of March 1, 2002 to March 31, 2002.
Should you have any questions concerning this letter, please contact Mr. W. J. Beck at (309) 227-2800.
Respectfully, Timot J.Tulon Site Vice President Quad Cities Nuclear Power Station Attachment cc:
Regional Administrator - NRC Region Ill NRC Senior Resident Inspector - Quad Cities Nuclear Power Station
ATTACHMENT QUAD CITIES NUCLEAR POWER STATION UNITS 1 AND 2 MONTHLY OPERATING REPORT EXELON NUCLEAR AND MIDAMERICAN ENERGY COMPANY FACILITY OPERATING LICENSE NOS. DPR-29 AND DPR-30 NRC DOCKET NOS. 50-254 AND 50-265
TABLE OF CONTENTS
- 1.
Introduction II.
Summary of Operating Experience A.
Unit One B.
Unit Two IlI.
Operating Data Statistics A.
Operating Data Report for March - Quad Cities Unit One B.
Operating Data Report for March - Quad Cities Unit Two IV.
Unit Shutdowns A.
Unit One Shutdowns B.
Unit Two Shutdowns V.
Amendments to Facility License or Technical Specifications VI.
Unique Reporting Requirements A.
Main Steam Relief Valve Operations
- i. INTRODUCTION Quad Cities Nuclear Power Station is composed of two Boiling Water Reactors and Steam Turbine/Generators, each with a Maximum Dependable Capacity of 769 MWe Net, located in Cordova, Illinois. The Station is jointly owned by Exelon Nuclear and MidAmerican Energy Company. The Nuclear Steam Supply Systems are General Electric Company Boiling Water Reactors. The Architect! Engineer was Sargent & Lundy, Incorporated, and the primary construction contractor was United Engineers & Constructors. The Mississippi River is the condenser cooling water source. The plant is subject to license numbers DPR-29 and DPR-30, issued October 1, 1971, and March 21, 1972, respectively; pursuant to Docket Numbers 50-254 and 50-265. The date of initial Reactor criticalities for Units One and Two, respectively were October 18,1971, and April 26,1972. Commercial generation of power began on February 18, 1973 for Unit One and March 10, 1973 for Unit Two.
This report was compiled by Ron Baumer and Debbie Cline, telephone numbers 309-227-2811 and 2801, respectively.
II.
SUMMARY
OF OPERATING EXPERIENCE A.
Unit One Unit One operated the month of March at full power with the exception of a downpower on March 15, 2002 to approximately 790 MWe for planned turbine generator testing..
B.
Unit Two Unit Two started the month of March shutdown for refuel outage Q2R16. Unit 2 restarted on March 04, 2002 and achieved full power of 912 MWe on March 14, 2002. The unit operated at full power for the remainder of the month until a planned maintenance outage (Q2M17) shutdown on March 29, 2002. The unit was shutdown for the remainder of the month.
Unit Two restarted with EPU modifications installed. The new Power Level is 2957 (MW th), and Design Electrical Rating of 912 (MWe - Net). The Maximum Dependable Capacity has not been calculated. It will be provided at a later date.
III. OPERATING DATA STATISTICS A. Unit One Operating Data Report for March 2002 DOCKET NO.:
DATE:
COMPLETED BY:
TELEPHONE:
50-254 April 15, 2002 Ron Baumer (309) 227-2811 OPERATING STATUS 0000 030102
- 1. REPORTING PERIOD: 2400 033102 GROSS HOURS IN REPORTING PERIOD: 744
- 2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 2511 MAX. DEPEND. CAPACITY:
769 DESIGN ELECTRICAL RATING (MWe-NET):
789 Quad Cities Unit One Operating Statistics for March 2002 UNIT ONE THIS MONTH YTD CUMULATIVE
- 3.
NUMBER OF HOURS THE REACTOR WAS CRITICAL 744.00 1556.10 203588.90
- 4.
REACTOR RESERVE SHUTDOWN HOURS 0.00 603.90 4082.50
- 5.
HOURS GENERATOR ON-LINE 744.00 1523.00 198261.60
- 6.
UNIT RESERVE SHUTDOWN HOURS 0.00 637.00 1615.20
- 7.
GROSS THERMAL ENERGY GENERATED (MWH) 1866889.68 3698514.24 441550195.32
- 8.
GROSS ELECTRICAL ENERGY GENERATED (MWH) 608090.00 1200499.00 142890024.00
- 9.
NET ELECTRICAL ENERGY GENERATED (MWH) 581382.00 1145098.00 129659487.00
- 10.
REACTOR SERVICE FACTOR 100.00 72.04 77.50
- 11.
REACTOR AVAILABILITY FACTOR 100.00 72.04 79.05
- 12.
UNIT SERVICE FACTOR 100.00 70.51 75.47
- 13.
UNIT AVAILABILITY FACTOR 100.00 70.51 76.08
- 14.
UNIT CAPACITY FACTOR (Using MDC) 101.62 68.94 64.18
- 15.
UNIT CAPACITY FACTOR (Using Design MWe) 99.04 67.191 62.56
III. OPERATING DATA STATISTICS B. Unit Two Operating Data Report for March 2002 DOCKET NO.:
50-265 DATE:
April 15, 2002 COMPLETED BY:
Ron Baumer TELEPHONE:
(309) 227-2811 OPERATING STATUS 0000 030102
- 1. REPORTING PERIOD: 2400 033102 GROSS HOURS IN REPORTING PERIOD: 744
- 2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 2957 MAX. DEPEND. CAPACITY: 769 DESIGN ELECTRICAL RATING (MWe-NET):
912 Quad Cities Unit Two Operating Statistics for March 2002 UNIT TWO THIS MONTH YTD CUMULATIVE
- 3.
NUMBER OF HOURS THE REACTOR WAS CRITICAL 615.20 1624.50 197563.30
- 4.
REACTOR RESERVE SHUTDOWN HOURS 128.80 535.50 4175.60
- 5.
HOURS GENERATOR ON-LINE 585.00 1593.00 191412.15
- 6.
UNIT RESERVE SHUTDOWN HOURS 159.00 567.00 1971.90
- 7.
GROSS THERMAL ENERGY GENERATED (MWH) 1419073.20 3890604.96 425984522.46
- 8.
GROSS ELECTRICAL ENERGY GENERATED (MWH) 445270.00 1251410.00 136867341.00
- 9.
NET ELECTRICAL ENERGY GENERATED (MWH) 426135.00 1197576.00 130055746.00
- 10.
REACTOR SERVICE FACTOR 82.69 75.21 72.04
- 11.
REACTOR AVAILABILITY FACTOR 82.69 74.06 79.83
- 12.
UNIT SERVICE FACTOR 78.63 73.75 70.51
- 13.
UNIT AVAILABILITY FACTOR 78.63 72.64 77.00
- 14.
UNIT CAPACITY FACTOR (Using MDC) 74.48 72.10 68.94
- 15.
UNIT CAPACITY FACTOR (Using Design MWe) 62.80 60.79 58.13
IV. UNIT SHUTDOWNS A. Unit One Shutdowns for March 2002 DOCKET NO.:
DATE:
COMPLETED BY:
TELEPHONE:
50-254 April 15, 2002 Ron Baumer (309) 227-2811 No.
DATE TYPE DURATION REASON METHOD CORRECTIVE F OR S (HOURS)
OF ACTIONSICOMMENTS SHUTTING R EA C TO R I _________
L _________
+/- ____________
+/-
a ____________
L Legend:
(1) Reason A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other (Explain)
(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
IV. UNIT SHUTDOWNS B. Unit Two Shutdowns for March 2002 DOCKET NO.:
DATE:
COMPLETED BY:
TELEPHONE:
50-265 April 15, 2002 Ron Baumer (309) 227-2811 No.
DATE TYPE DURATION REASON METHOD CORRECTIVE F OR S (HOURS)
OF ACTIONS/COMMENTS SHUTTING DOWN REACTOR 2002-01 02/11/02 S
104 C
4 Reactor shutdown to perform Refuel Outage Q2R16 2002-02 03/29/02 S
55 B
1 Reactor shutdown to perform II Maintenance outage Q2M17 Legend:
(1) Reason A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other (Explain)
(2) Method 1 -Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
IV. UNIT SHUTDOWNS A. Unit One Shutdowns for March 2002 DOCKET NO.:
DATE:
COMPLETED BY:
TELEPHONE:
50-254 April 15, 2002 Ron Baumer (309) 227-2811 No.
DATE TYPE DURATION REASON METHOD CORRECTIVE FOR S (HOURS)
OF ACTIONS/COMMENTS SHUTTING DOWN REACTOR Legend:
(1) Reason A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other (Explain)
(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
IV. UNIT SHUTDOWNS B. Unit Two Shutdowns for March 2002 DOCKET NO.:
DATE:
COMPLETED BY:
TELEPHONE:
50-265 April 15, 2002 Ron Baumer (309) 227-2811 No.
DATE TYPE DURATION REASON METHOD CORRECTIVE F OR S (HOURS)
OF ACTIONS/COMMENTS SHUTTING DOWN REACTOR 2002-01 02/11/02 S
104 C
4 Reactor shutdown to perform Refuel Outage Q2R16 2002-02 03/29/02 S
55 B
1 Reactor shutdown to perform Maintenance outage Q2M17 Legend:
(1) Reason A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other (Explain)
(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
V. AMENDMENTS TO FACILITY LICENSE OR TECHNICAL SPECIFICATIONS There were no Technical Specification changes in March.
VI. UNIQUE REPORTING REQUIREMENTS There were no relief valve actuations in the month of March for Unit 1. For Unit 2, there were five relief valve actuations for the month of March. Valve 3A was actuated for 5 seconds, and valves 3B, C, D and E were actuated for 10 seconds for Technical Specification operability testing.