05000348/LER-2024-002-01, Manual Reactor Trip Due to Loss of Power to the 2A 125 Volt DC Distribution Panel
NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in
NL-24-0234, Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown
NL-24-0230, License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-500, Revision 2, DC Electrical Rewrite – Update to TSTF-360
ML24178A376
ML24184A045
NL-24-0227, Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)
NL-24-0281, License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions
NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023
ML24199A207
ML24200A139
ML24201A203
ML24215A377
NL-24-0315, – ISFSI, Registration of Spent Fuel Cask Use
IR 05000348/2024002
NL-24-0321, License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions - Supplemental Information
ML24226B211
IR 05000348/2024005
ML24233A137
ML24240A081
ML24233A002
ML24242A133
NL-24-0259, License Amendment Request to Revise Technical Specification 3.4.14, Reactor Coolant System Pressure Isolation Valve Leakage, Surveillance Requirement 3.4.14.3 Acceptance Criteria and Miscellaneous Obsolete Changes
NL-24-0340, Unit 1 - Inservice Inspection Program Owners Activity Report (OAR-1) for Outage 1 R32
ML24247A110
NL-24-0341, Response to Request for Additional Information Related to the Application to Revise Technical Specifications Regarding Change to Containment Spray Nozzle Test Frequency
IR 05000348/2024401
NL-24-0349, Units 1 and 2 - 10 CFR 26.719(c)(1) 30-Day Report Blind Performance Test Results Inconsistent with Sample Provided
NL-24-0320, License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3,.
NL-24-0384, Request for Alternative RR-PR-04 for Inservice Testing of the 2A, 2B, and 2C Charging Pumps and Mini-Flow Isolation Valves
NL-24-0396, Response to Request for Additional Information Related to Relief Request to Defer Charging Pump and Mini-Flow Isolation Valve Inservice Testing
NL-24-0392, Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-002
NL-24-0364, Notification of Deferral of Baffle Former Bolt Inspections from Farley 1R33 to 1R34
IR 05000348/2024403
IR 05000348/2024003
ML24320A134
NL-24-0397, Response to Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement
NL-24-0406, Response to Request for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-003
ML24302A297
IR 05000348/2024012
IR 05000348/2024402
ML24351A040
ML24330A123
ML25008A037
ML25008A248
NL-25-0014, Withdrawal of Request for Exemption from Physical Barrier Requirements
NL-25-0433, License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-500, Revision 2 - DC Electrical Rewrite - Update to TSTF-360 - Response to Request for Additional Information
ML25021A104
NL-24-0117, Change to Quality Assurance Program to Adopt Regulatory Guide 1.8 Revision 4 and License Amendment Request to Relocate Control of the Unit/Facility/Plant Staff Qualification Requirements from Technical Specifications to the Quality Assura
Post Office Box 1295 Birmingham, Alabama 35201 Tel 205.992.5131 SOUTHERNA COMPANY Energy to Serve Your World April 25, 2002 Docket Nos.:
NEL-02-0098 50-348 50-364 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 - 0001 Joseph M. Farley Nuclear Plant 2001 Annual Environmental Operating Report (Nonradiological)
Ladies and Gentlemen:
In accordance with subsection 5.4.1 of the Joseph M. Farley Nuclear Plant Environmental Protection Plan (Units 1 & 2), Appendix B to Facility Operating License Nos. NPF-2 and NPF-8, please find enclosed the Annual Environmental Operating Report for 2001.
If you have any questions, please advise.
Respectfully submitted, Dave Morey ABG/sl: 2001 Annual Environmental Operation Report.doc
Attachment:
1. Annual Environmental Operating Report for 2001 (Nonradiological) 0_'
Dave Morey Vice President Farley Project
Page 2 U. S. Nuclear Regulatory Commission cc:
Southern Nuclear Operating Company Mr. D. E. Grissette, General Manager - Farley U. S. Nuclear Regulatory Commission, Washington, D. C.
Mr. F. Rinaldi, Licensing Project Manager - Farley U. S. Nuclear Regulatory Commission, Region II Mr. L. A. Reyes, Regional Administrator Mr. T. P. Johnson, Senior Resident Inspector - Farley
ATTACHMENT 1 SOUTHERN NUCLEAR OPERATING COMPANY JOSEPH M. FARLEY NUCLEAR PLANT - UNITS 1 AND 2 NRC DOCKET NOS. 50-348 AND 50-364 FACILITY OPERATING LICENSE NOS. NPF-2 AND NPF-8 ANNUAL ENVIRONMENTAL OPERATING REPORT FOR 2001 (NONRADIOLOGICAL)
JOSEPH M. FARLEY NUCLEAR PLANT - UNITS 1 AND 2 ANNUAL ENVIRONMENTAL OPERATING REPORT FOR 2001 (NONRADIOLOGICAL)
INTRODUCTION In accordance with Subsection 5.4.1 of the Joseph M. Farley Nuclear Plant Environmental Protection Plan, Appendix B to Facility Operating License Nos. NPF-2 and NPF-8, this report is submitted summarizing implementation of the Environmental Protection Plan for calendar year 2001.
REPORTING REQUIREMENTS A.
Summaries and Analyses of Results of Environmental Protection Activities Required by Subsection 4.2 of the Environmental Protection Plan (EPP) for the Reporting Period
1. Aerial Remote Sensing - Aerial Remote Sensing is no longer required.
2. Herbicide Application - There is no reporting requirement associated with this condition.
3. Land Management - There is no reporting requirement associated with this condition.
B.
Comparison of the 2001 Monitoring Activities with Preoperational Studies, Operational Controls, and Previous Non-Radiological Monitoring Reports These comparisons were not required because no nonradiological environmental monitoring programs were conducted during the reporting period beyond those performed in accordance with NPDES Permit No. AL0024619.
C.
Assessment of the Observed Impacts of Plant Operation on the Environment There were no significant adverse environmental impacts associated with plant operation during 2001.
D.
EPP Noncompliance and Corrective Actions There were no EPP noncompliances during 2001.
E.
Changes in Station Design or Operation, Tests, or Experiments Made in Accordance with EPP Section 3.1 Which Involved a Potentially Significant Unreviewed Environmental Question There were no changes in station design or operation, tests, or experiments in 2001 which involved a potentially significant unreviewed environmental question.
F.
Nonroutine Reports Submitted in Accordance with EPP Section 5.4.2 There were no nonroutine reports submitted in 2001.