April 4, 2002 Mr. Robert G. Byram Senior Vice President and Chief Nuclear Officer PPL Susquehanna, LLC Susquehanna Steam Electric Station 2 North Ninth Street Allentown, Pennsylvania 18101
SUBJECT:
SENIOR REACTOR AND REACTOR OPERATOR INITIAL EXAMINATIONS -
SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2
Dear Mr. Byram:
In telephone conversation on April 1, 2002, between Mr. Alan Blamey, Examiner/Inspector, and Mr. Walter Hunt, Manager, Nuclear Training, arrangements were made for the administration of licensing examinations at Susquehanna, during the week of August 11, 2002.
As agreed during the telephone conversation, your staff will prepare the examinations based on the guidelines in Revision 8, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The NRC regional office will discuss with your staff any changes that might be necessary before the examinations are administered.
To meet the above schedule, it will be necessary for your staff to furnish your final examination outlines by Monday, May 27, 2002. We have received your draft examination outlines and provided comments to your staff on March 8, 2002. The written examinations, operating tests, and the supporting reference materials requested by Mr. Blamey will be due by June 25, 2002.
Pursuant to 10 CFR 55.40(b)(3), an authorized representative of the facility licensee shall approve the outlines, examinations, and tests before they are submitted to the NRC for review and approval. All materials should be complete and ready-to-use. Any delay in receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled.
In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final.
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.
Mr. Robert G. Byram To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications (Office of Management and Budget (OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),
and waiver requests (if any) (OMB approval number 3150-0090) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018, which expires on April 30, 2003. The public reporting burden for this collection of information is estimated to average 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, writing the examinations, and completing and reviewing the collection of information.
Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33),
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at SLF@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0101), Office of Management and Budget, Washington, DC 20503.
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.
Thank you for your cooperation in this matter. Mr. Walter Hunt has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRCs examination procedures and guidelines, please contact Mr. Alan Blamey at (610) 337-5366, or me at (610) 337-5183.
Sincerely,
/RA/
Richard J. Conte, Chief Operational Safety Branch Division of Reactor Safety Docket Nos.
50-387, 50-388 License Nos. NPF-14, NPF-22
Mr. Robert G. Byram cc w/encl:
B. L. Shriver, Vice President - Nuclear Site Operations R. Anderson, General Manager - SSES Operations R. L. Ceravolo, General Manager - Plant Support G. A. Williams, General Manager - Nuclear Assurance A. J. Wrape III, General Manager - Nuclear Engineering T. Harpster, Manager - Regulatory Affairs R. R. Sgarro, Supervisor, Nuclear Licensing - SSES C. D. Markley, Supervisor - Nuclear Licensing M. M. Golden, Manager - Nuclear Security P. Nederostek, Nuclear Services Manager, General Electric D. Roth, Manager, Quality Assurance H. D. Woodeshick, Special Assistant to the President G. DallaPalu, PP&L Nuclear Records R. W. Osborne, Vice President, Supply & Engineering Allegheny Electric Cooperative, Inc.
Commonwealth of Pennsylvania R. M. Peal, Manager, Nuclear Training (DRS OL Exam Reports Only)
Mr. Robert G. Byram Distribution:
H. Miller, RA/J. Wiggins, DRA M. Shanbaky, DRP D. Florek, DRP J. Talieri, DRP S. Iyer, DRP R. Junod, DRP S. Hansell, DRP - SRI Susquehanna T. Bergman, RI EDO Coordinator E. Adensam, NRR (RidsNrrDlpmLpdi)
T. Colburn, PM, NRR D. Skay, PM, NRR (Backup)
Region I Docket Room (with concurrences)
W. Lanning, DRS R. Crlenjak, DRS A. Blamey, DRS, Chief Examiner C. Buracker, DRS (OL Facility File)
R. Conte, DRS DOCUMENT NAME: G:\\OSB\\Blamey\\Susquehanna\\2002Exam\\Susq120dayexamltr.wpd ADAMS: ML020590027 After declaring this document An Official Agency Record it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRS RI/DRS RI/DRS NAME CBuracker (RJC for)
ABlamey RConte DATE 04/04/02 04/03/02 04/04/02 04/ /02 04/ /02 OFFICIAL RECORD COPY