ML020940102
ML020940102 | |
Person / Time | |
---|---|
Site: | Ginna |
Issue date: | 03/26/2002 |
From: | Conte R NRC/RGN-I/DRS/OSB |
To: | Maciuska F Rochester Gas & Electric Corp |
References | |
50-244/01301 | |
Download: ML020940102 (2) | |
Similar Documents at Ginna | |
---|---|
Category:License-Operator
MONTHYEARRS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023
[Table view]Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23247A0092022-09-28028 September 2022 Final QA Related Forms RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML20329A4322020-11-17017 November 2020 Final Qa/Related Forms (Folder 1) ML20329A4422020-09-17017 September 2020 Final Qa/Related Form - Form ES-401-6 (Folder 1) ML20329A1812020-09-17017 September 2020 NRC Comments on Draft Licensee-Developed Operating Test Outlines (Folder 2) ML20329A1412020-09-17017 September 2020 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML20322A3502020-09-17017 September 2020 Final Operating Test (Sections a, B, and C) (Folder 3) ML20321A2792020-09-17017 September 2020 Final Written Examination with Answer Key (Form 401-5 Format) (Folder 3) ML20328A1622020-09-17017 September 2020 Final Written Examination and Operating Test Outlines (Folder 3) ML20328A2792020-09-17017 September 2020 Handouts to Applicants (Folder 3) ML20328A2912020-09-17017 September 2020 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML20329A2002020-08-26026 August 2020 Draft Written Examination and Operating Test Outlines (Folder 2) ML22103A2232020-08-26026 August 2020 Revised Draft Written Examination and Operating Test Outlines (2022 Regional Audit Corrective Action) (Folder 2) ML20329A2392020-07-22022 July 2020 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML20329A2232020-07-22022 July 2020 Draft Written Examination (Folder 2) ML20329A3542020-07-22022 July 2020 Licensee 75-Day Letter Transmitting the Draft Written Exam and Operating Test Material (Folder 2) ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML19323D1722019-11-18018 November 2019 R. E. Ginna Nuclear Power Plant - Senior Reactor and Reactor Operator Initial License Examinations ML21041A2942019-10-0303 October 2019 Original Questions for Modified Written Exam Questions RS-19-053, Response to NRC Regulatory Issue Summary 2019-02, Preparation and Scheduling of Operator Licensing Examinations2019-05-16016 May 2019 Response to NRC Regulatory Issue Summary 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML19045A3702019-02-12012 February 2019 March 2019 GFE Cover Letter Ri ML18353A6082018-12-18018 December 2018 Senior Reactor Operator Retake License Examinations ML18344A5852018-12-10010 December 2018 R. E. Ginna - Reactor Operator Retake License Examinations ML19119A1472018-10-30030 October 2018 Final Qa/Related Forms (Folder 1) ML19156A1482018-08-27027 August 2018 Final Qa/Related Form - ES-201-1 (Folder 1) ML18233A5092018-08-21021 August 2018 Operator Licensing Operating Test Approval RS-18-057, Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations2018-04-25025 April 2018 Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17272A3242017-09-28028 September 2017 R. E. Ginna - Senior Reactor and Reactor Operator Initial License Examinations RS-17-070, Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations2017-05-0303 May 2017 Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations ML17114A2862017-04-21021 April 2017 Miscellaneous Exam Material (Folder 1) ML17114A2172017-04-21021 April 2017 Final Qa/Related Forms (Folder 1) ML17114A3172017-04-21021 April 2017 Handouts to Applicants (Folder 3) ML17123A1722017-04-14014 April 2017 Post Exam Comments Resolution References (Folder 1) ML17114A3752017-03-0909 March 2017 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML17114A1562017-03-0909 March 2017 Final Qa/Related Forms - ES-401 (Folder 1) ML17114A3812017-03-0909 March 2017 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML17066A2272017-03-0707 March 2017 Initial Operator Licensing Operating Test Approval: R. E. Ginna Nuclear Power Plant ML17104A2162017-03-0707 March 2017 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML17104A2012017-03-0303 March 2017 Final Operating Test (Sections a, B, and C) (Folder 3) ML17114A4232017-01-19019 January 2017 Draft Written Exam (Folder 2) ML17114A4372017-01-19019 January 2017 Draft Operating Exam (Section a, Section B, Section C) (Folder 2) ML17114A3522017-01-19019 January 2017 Final Outlines (Folder 3) ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 ML17114A4112016-12-0909 December 2016 Draft - Outlines (Folder 2), (Facility Letter. Dtd ML16286A4132016-10-11011 October 2016 Senior Reactor and Reactor Operator Initial License Examinations - )R.E. Ginna Nuclear Power Plant) ML15156A5522015-01-21021 January 2015 Final Qa/Related Forms (Folder 1) ML15043A6812014-12-16016 December 2014 Final Operating Exam (Sections a, B, and C) (Folder 3) 2023-06-16 Category:Part 55 Examination Related Material MONTHYEARRS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023
[Table view]Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23247A0092022-09-28028 September 2022 Final QA Related Forms RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML20329A4322020-11-17017 November 2020 Final Qa/Related Forms (Folder 1) ML20329A4422020-09-17017 September 2020 Final Qa/Related Form - Form ES-401-6 (Folder 1) ML20329A1812020-09-17017 September 2020 NRC Comments on Draft Licensee-Developed Operating Test Outlines (Folder 2) ML20329A1412020-09-17017 September 2020 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML20328A2792020-09-17017 September 2020 Handouts to Applicants (Folder 3) ML20321A2792020-09-17017 September 2020 Final Written Examination with Answer Key (Form 401-5 Format) (Folder 3) ML20322A3502020-09-17017 September 2020 Final Operating Test (Sections a, B, and C) (Folder 3) ML20328A1622020-09-17017 September 2020 Final Written Examination and Operating Test Outlines (Folder 3) ML20328A2912020-09-17017 September 2020 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML22103A2232020-08-26026 August 2020 Revised Draft Written Examination and Operating Test Outlines (2022 Regional Audit Corrective Action) (Folder 2) ML20329A2002020-08-26026 August 2020 Draft Written Examination and Operating Test Outlines (Folder 2) ML20329A2392020-07-22022 July 2020 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML20329A2232020-07-22022 July 2020 Draft Written Examination (Folder 2) ML20329A3542020-07-22022 July 2020 Licensee 75-Day Letter Transmitting the Draft Written Exam and Operating Test Material (Folder 2) ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML19323D1722019-11-18018 November 2019 R. E. Ginna Nuclear Power Plant - Senior Reactor and Reactor Operator Initial License Examinations ML21041A2942019-10-0303 October 2019 Original Questions for Modified Written Exam Questions RS-19-053, Response to NRC Regulatory Issue Summary 2019-02, Preparation and Scheduling of Operator Licensing Examinations2019-05-16016 May 2019 Response to NRC Regulatory Issue Summary 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML18353A6082018-12-18018 December 2018 Senior Reactor Operator Retake License Examinations ML18344A5852018-12-10010 December 2018 R. E. Ginna - Reactor Operator Retake License Examinations ML19119A1472018-10-30030 October 2018 Final Qa/Related Forms (Folder 1) ML19156A1482018-08-27027 August 2018 Final Qa/Related Form - ES-201-1 (Folder 1) ML18233A5092018-08-21021 August 2018 Operator Licensing Operating Test Approval RS-18-057, Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations2018-04-25025 April 2018 Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17272A3242017-09-28028 September 2017 R. E. Ginna - Senior Reactor and Reactor Operator Initial License Examinations RS-17-070, Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations2017-05-0303 May 2017 Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations ML17114A2862017-04-21021 April 2017 Miscellaneous Exam Material (Folder 1) ML17114A2172017-04-21021 April 2017 Final Qa/Related Forms (Folder 1) ML17114A3172017-04-21021 April 2017 Handouts to Applicants (Folder 3) ML17123A1722017-04-14014 April 2017 Post Exam Comments Resolution References (Folder 1) ML17114A3752017-03-0909 March 2017 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML17114A1562017-03-0909 March 2017 Final Qa/Related Forms - ES-401 (Folder 1) ML17114A3812017-03-0909 March 2017 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML17104A2162017-03-0707 March 2017 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML17066A2272017-03-0707 March 2017 Initial Operator Licensing Operating Test Approval: R. E. Ginna Nuclear Power Plant ML17104A2012017-03-0303 March 2017 Final Operating Test (Sections a, B, and C) (Folder 3) ML17114A4232017-01-19019 January 2017 Draft Written Exam (Folder 2) ML17114A4372017-01-19019 January 2017 Draft Operating Exam (Section a, Section B, Section C) (Folder 2) ML17114A3522017-01-19019 January 2017 Final Outlines (Folder 3) ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 ML17114A4112016-12-0909 December 2016 Draft - Outlines (Folder 2), (Facility Letter. Dtd ML16286A4132016-10-11011 October 2016 Senior Reactor and Reactor Operator Initial License Examinations - )R.E. Ginna Nuclear Power Plant) ML15156A5522015-01-21021 January 2015 Final Qa/Related Forms (Folder 1) ML15043A6792014-12-16016 December 2014 Final Written Examination with Answer Key (401-5 Format) (Folder 2) ML15043A6802014-12-16016 December 2014 Handouts to Applicants (Folder 3) 2023-06-16 |
Text
March 26, 2002 Mr. Frank Maciuska Manager - Operations Training Rochester Gas & Electric Co.
R.E. Ginna Nuclear Power Plant 89 East Avenue Rochester, NY14649
Dear Mr. Maciuska:
Enclosed find five certificates for the following operators:
Reactor Operator Senior Reactor Operator Dale S. Bisaillon Thomas A. Fouts Donald W. Dean Rex T. Reissner Robert C. Schnall No response to this letter is required.
Sincerely,
/RA/
Richard J. Conte, Chief Operational Safety Branch Division of Reactor Safety Docket No.: 050-0244
Enclosure:
As stated cc w/o enclosure:
R. C. Mecredy, Vice President - Nuclear Operations CERTIFIED MAIL -
RETURN RECEIPT REQUESTED
Mr. Frank Maciuska Distribution:
Facility File DOCUMENT NAME: G:OSB/Bissett/Ginna Exam Feb2002/GNExamCertsLtr.wpd ADAMS PKG: ML0124000143 After declaring this document An Official Agency Record it will/will not be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRS/ R1/DRS/ /
NAME CBuracker /RA/ RJConte /RA/
DATE 03/25/02 03/26/02 04/ /02 04/ /02 04/ /02 OFFICIAL RECORD COPY