End-of-Cycle Public Meeting Invitation Letter to Local Officials of Diablo Canyon (3rd Document Issuance of Same Letter Format)
ML020920245
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 04/01/2002
From: David Proulx
NRC Region 4
To: Richard Anderson
City of Morro Bay, CA
References
Download: ML020920245 (2)


Text

April 1, 2002 Rodger Anderson, Mayor City of Morro Bay 595 Harbor Morro Bay, CA 93442

SUBJECT:

NOTIFICATION OF UPCOMING MEETING

Dear Mayor Anderson:

Each year, NRC conducts an integrated assessment of performance, based upon the risk significance of the inspection findings of the NRCs resident and region-based inspectors and the insights gained from the licensee-provided performance indicators. The results are then communicated with the public through a public meeting held in the vicinity of each reactor power plant. Nationally, plants with significant performance shortcomings are reviewed by NRC senior management and discussed with the Commission in a public meeting in Rockville, Maryland.

We have completed the assessments associated with the inspection findings and performance indicators for the past year for Diablo Canyon. The results can be found at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/DIAB1/diab1_chart.html and http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/DIAB2/diab2_chart.html for Units 1 and 2, respectively. We have also scheduled a public meeting to discuss the results. The meeting for Diablo Canyon is scheduled for 6:30p.m., April 17, 2002, at the Embassy Suites Hotel, 333 Madonna Road, San Louis Obispo, California 93405.

In conjunction with this meeting, we are offering all local decision-makers an opportunity to meet separately with the NRC manager immediately following the public meeting. This opportunity is intended to provide you a forum to ask any questions that you may have and to let you meet personally the NRC personnel with whom you would interface in the event of an emergency at the nuclear power plant.

In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter will be made available electronically for public inspection in the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

I hope you find this opportunity responsive to your needs and I look forward to personally greeting you at the meeting. Should you have any questions concerning this initiative, please contact me at 805/595-2354.

Sincerely,

/RA/

David L. Proulx Senior Resident Inspector Diablo Canyon