Technical Specification Pages Amendment 144, Changes TS Surveillance Requirements for Manual Actuation of Certain Main Steamline Safety/Relief Valves, Including Those Valves That Provide the Automatic Depressurization
ML020850381
Person / Time
Site: Clinton Constellation icon.png
Issue date: 03/19/2002
From:
NRC/NRR/DLPM
To:
Hopkins J
References
TAC MB2256
Download: ML020850381 (3)


Text

S/RVs 3.4.4 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.4.4.1 Verify the safety function lift setpoints of the required S/RVs are as follows:

Setpoint (psig) 1165 +/- 34.9 1180 +/- 35.4 1190 +/- 35.7 Following testing, lift settings shall be within +/- 1%.

SR 3.4.4.2


-NOTE N

Valve actuation may be excluded.

Verify each required relief function S/RV actuates on an actual or simulated automatic initiation signal.

SR 3.4.4.3 -- -----

NOTE N

Not required to be performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after reactor steam pressure and flow are adequate to perform the test.

Verify each required S/RV actuator strokes when manually actuated.

In accordance with the Inservice Testing Program 18 months 18 months I-_____________________

CLINTON Amendment No.144 Number of S/RVs 7

5 4

3.4-11

ECCS-Operating 3.5.1 SURVEILLANCE REQUIREMENTS (continued)

SURVEILLANCE FREQUENCY SR 3.5.1.5 NOTE-------------------N Vessel injection/spray may be excluded.

Verify each ECCS injection/spray subsystem 18 months actuates on an actual or simulated automatic initiation signal.

SR 3.5.1.6


NOTE -------------------

Valve actuation may be excluded.

Verify the ADS actuates on an actual or 18 months simulated automatic initiation signal.

SR 3.5.1.7


NOTE -------------------

Not required to be performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after reactor steam pressure and flow are adequate to perform the test.

Verify each ADS valve actuator strokes when 18 months manually actuated.

SR 3.5.1.8


NOTE -------------------

ECCS actuation instrumentation is excluded.

Verify the ECCS RESPONSE TIME for each ECCS injection/spray subsystem is within limits.

18 months CLINTON Amendment No.144 3.5-5

LLS Valves SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.1.6.1 NOTE-------------------

Not required to be performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after reactor steam pressure and flow are adequate to perform the test.

Verify each LLS valve actuator strokes 18 months when manually actuated.

SR 3.6.1.6.2


NOTE-------------------

Valve actuation may be excluded.

Verify the LLS System actuates on an 18 months actual or simulated automatic initiation signal.

Amendment No. 144 CLINTON 3.6-23