ML020790567

From kanterella
Jump to navigation Jump to search
Summary Meeting - Tennessee Valley Authority Brown Ferry Nuclear Plant Independent Spent Fuel Storage
ML020790567
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 03/19/2002
From: Abney T
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation
References
Download: ML020790567 (15)


Text

-m-

-m-m

-m-Tennessee Valley Authority Browns Ferry Nuclear Plant Independent Spent Fuel Storage TVAINRC Meeting Region II - Atlanta, GA March 14, 2002

Agenda

  • Meeting Objectives
  • Background
  • Schedule
  • Proposed Location
  • Security
  • Site Specific Issues
  • Licensing
  • Summary and Closing Remarks Tim Abney Tim Abney Alan Chapman Alan Chapman Alan Chapman Alan Chapman Tim Abney Tim Abney Tim Abney 1

m m

=

=

- =

M

=

M M

M Introduction/Meeting Objectives LLLU Meeting Objectives Provide Status of Browns Ferry Nuclear Plant Spent Fuel Storage Situation Discuss BFN Activities to Date

- Provide a Schedule for Major Project Milestones Discuss Site Specific Issues Obtain Staff Input/Lessons Learned Tim Abney 2

-M-M

-M-M rn

Background

LLWJ

  • BFN Spent Fuel Pool Spent Fuel Pools are Currently Licensed for 3471 Fuel Assemblies (FA) Per Unit Full Core Reserve is 764 FAs Unit 1 Spent Fuel Pool Currently Contains 1978 FAs Unit 2 Spent Fuel Pool Currently Contains 2558 FAs Unit 3 Spent Fuel Pool Currently Contains 2160 FAs Including 284 Fresh Assemblies Unit 3 Will Lose Full Core Offload Capacity in November 2005 Tim Abney 3

M-m m

m m

m Background (Cont)

LU Options Considered Rerack Unit 3

> Provide Storage for Unit 3 Until 2012

> Provide Storage for Unit 2 Until 2013 Using the Unit I Pool Dry Storage

> Construct On Site ISFSI and Implement Dry Cask by July 2005 Tim Abney 4

m m

m Background (Cont)

L

  • Decision to Proceed With Dry Storage
  • Contract Awarded to Holtec International, November 2001 Tim Abney 5

m M

m m

m m

Schedule 2/2002 5/2002 Negotiate final colt at Assemble Team Detailed schedule development V Identify Dwgs/procedureW Environmental Assessment 3/201 0 03 Hardware Fabrication / Delivery 10/2004

'M MPG's 1W MPC's HI-STORM's HI-TRAC Handling Equipment Ancillary Equipment 5/2003 1/2002 Design 10/2003 Construction 12/2004

  • TV RFF and Truck Bay Evaluations Soil Sampling and Analysis Heavy Load Transport Path Design ISFSI Design Security System Design SFP RB Crane Design M

1W Work plan development Construction activities Start-up/Testing/

Closure activities NRC Demonstrations Ops and Maint Procedure Dev.

10/2004 6/2005 Pre-operations Teeing Training Dry Runs On site overpack Fabrication 1/2002 Engineering, Licensing and Other Evaluations 2/2005 Load 3 Casks 7/2005 9/2005 Lo wl oDi opF Analysis Dose rate Assessments 72.212 Report 72.48 Procedure Licensing Submittals Load, weld (close) and transport Alan Chapman 6

m m

m m

m

-M-BFN Proposed Location ULl

  • Phase I

- Located Just Outside Current Protected Area Boundary Adjacent to the Switch Yard

  • Transport pathway Approximately 1500 ft
  • Surrounded By 100 Year Flood Control Ditch (Moat)

Switch Yard Alan Chapman 7

Security

  • Extend the Current Protected Area to Encompass Phase I Storage Location Isolation Zone Lighting Camera Locations
  • Revise Security Plan
  • Eliminate the East Access Point
  • Minimal Impact on Current Security Forces Alan Chapman

%.7

Site Specific Issues

  • Evaluations and Analyses Heavy Load Handling Path Evaluation

> NUREG-0612, Control Of Heavy Loads 10 CFR 72.212 Evaluations NRC Bulletin 96-04 and ISG-15 Compliance Evaluation Various Off-Normal Condition Analyses and Calculations Radiation Assessment

  • Plant Modifications Required to Support Spent Fuel Off-Loading

- Cask Support Stands and Work Platform

- Reactor Building Crane Upgrade NUREG-0554, Single-Failure-Proof Cranes for Nuclear Power Plants

- Truck Bay and Egress Modifications (Potential)

Alan Chapman 9

M--

Site Specific Issues (Cont.)

  • Design and Construction of Storage Facility Phase I ISFSI

> 88-Cask Capacity

> Sufficient Storage For Current End-of-License For All 3 Units Through 2016 Phase 11 and Phase Ill Contingency If DOE Does Not Accept Spent Fuel After 2016 Alan Chapman 10

-M-

-M-Site Specific Issues (Cont.)

  • Design and Construction of Storage Facility (Cont)

- Transport Roadway and Staging Pad

- Security Boundary Revision (Fence, Cameras, Lighting, E-Field, etc.)

  • Facility Startup / Testing

- Procedures Development Training Program Development Personnel Training NRC Demonstrations Startup Testing of Ancillary Equipment Cask Loading and Closure Operations for Initial Campaign Alan Chapman 11

m m

m Site Specific Issues (Cont.)

LLLLl

  • Major Procurement Items Multi Purpose Canister Storage Overpack Transfer Cask Handling and Ancillary Equipment Alan Chapman 12

Licensing UXL

  • Selection Considerations Flexibility Well Defined Regulatory Precedence Minimize TVA and Staff Resources Efficiency Associated With a Standard Design SQN Site Will Use a General License Lessons Learned
  • Potential Submittals Radiological Emergency Plan Security Plan Quality Assurance Plan Tim Abney 13

-M Summary and Closing Remarks Tim Abney 14