ML020790567
| ML020790567 | |
| Person / Time | |
|---|---|
| Site: | Browns Ferry |
| Issue date: | 03/19/2002 |
| From: | Abney T Tennessee Valley Authority |
| To: | Office of Nuclear Reactor Regulation |
| References | |
| Download: ML020790567 (15) | |
Text
-m-
-m-m
-m-Tennessee Valley Authority Browns Ferry Nuclear Plant Independent Spent Fuel Storage TVAINRC Meeting Region II - Atlanta, GA March 14, 2002
Agenda
- Meeting Objectives
- Background
- Schedule
- Proposed Location
- Security
- Site Specific Issues
- Licensing
- Summary and Closing Remarks Tim Abney Tim Abney Alan Chapman Alan Chapman Alan Chapman Alan Chapman Tim Abney Tim Abney Tim Abney 1
m m
=
=
- =
M
=
M M
M Introduction/Meeting Objectives LLLU Meeting Objectives Provide Status of Browns Ferry Nuclear Plant Spent Fuel Storage Situation Discuss BFN Activities to Date
- Provide a Schedule for Major Project Milestones Discuss Site Specific Issues Obtain Staff Input/Lessons Learned Tim Abney 2
-M-M
-M-M rn
Background
LLWJ
- BFN Spent Fuel Pool Spent Fuel Pools are Currently Licensed for 3471 Fuel Assemblies (FA) Per Unit Full Core Reserve is 764 FAs Unit 1 Spent Fuel Pool Currently Contains 1978 FAs Unit 2 Spent Fuel Pool Currently Contains 2558 FAs Unit 3 Spent Fuel Pool Currently Contains 2160 FAs Including 284 Fresh Assemblies Unit 3 Will Lose Full Core Offload Capacity in November 2005 Tim Abney 3
M-m m
m m
m Background (Cont)
LU Options Considered Rerack Unit 3
> Provide Storage for Unit 3 Until 2012
> Provide Storage for Unit 2 Until 2013 Using the Unit I Pool Dry Storage
> Construct On Site ISFSI and Implement Dry Cask by July 2005 Tim Abney 4
m m
m Background (Cont)
L
- Other Considerations Extended Power Uprate Plant License Renewal
- Decision to Proceed With Dry Storage
- Contract Awarded to Holtec International, November 2001 Tim Abney 5
m M
m m
m m
Schedule 2/2002 5/2002 Negotiate final colt at Assemble Team Detailed schedule development V Identify Dwgs/procedureW Environmental Assessment 3/201 0 03 Hardware Fabrication / Delivery 10/2004
'M MPG's 1W MPC's HI-STORM's HI-TRAC Handling Equipment Ancillary Equipment 5/2003 1/2002 Design 10/2003 Construction 12/2004
- TV RFF and Truck Bay Evaluations Soil Sampling and Analysis Heavy Load Transport Path Design ISFSI Design Security System Design SFP RB Crane Design M
1W Work plan development Construction activities Start-up/Testing/
Closure activities NRC Demonstrations Ops and Maint Procedure Dev.
10/2004 6/2005 Pre-operations Teeing Training Dry Runs On site overpack Fabrication 1/2002 Engineering, Licensing and Other Evaluations 2/2005 Load 3 Casks 7/2005 9/2005 Lo wl oDi opF Analysis Dose rate Assessments 72.212 Report 72.48 Procedure Licensing Submittals Load, weld (close) and transport Alan Chapman 6
m m
m m
m
-M-BFN Proposed Location ULl
- Phase I
- Located Just Outside Current Protected Area Boundary Adjacent to the Switch Yard
- Transport pathway Approximately 1500 ft
- Surrounded By 100 Year Flood Control Ditch (Moat)
Switch Yard Alan Chapman 7
Security
- Extend the Current Protected Area to Encompass Phase I Storage Location Isolation Zone Lighting Camera Locations
- Revise Security Plan
- Eliminate the East Access Point
- Minimal Impact on Current Security Forces Alan Chapman
%.7
Site Specific Issues
- Evaluations and Analyses Heavy Load Handling Path Evaluation
> NUREG-0612, Control Of Heavy Loads 10 CFR 72.212 Evaluations NRC Bulletin 96-04 and ISG-15 Compliance Evaluation Various Off-Normal Condition Analyses and Calculations Radiation Assessment
- Plant Modifications Required to Support Spent Fuel Off-Loading
- Cask Support Stands and Work Platform
- Reactor Building Crane Upgrade NUREG-0554, Single-Failure-Proof Cranes for Nuclear Power Plants
- Truck Bay and Egress Modifications (Potential)
Alan Chapman 9
M--
Site Specific Issues (Cont.)
- Design and Construction of Storage Facility Phase I ISFSI
> 88-Cask Capacity
> Sufficient Storage For Current End-of-License For All 3 Units Through 2016 Phase 11 and Phase Ill Contingency If DOE Does Not Accept Spent Fuel After 2016 Alan Chapman 10
-M-
-M-Site Specific Issues (Cont.)
- Design and Construction of Storage Facility (Cont)
- Transport Roadway and Staging Pad
- Security Boundary Revision (Fence, Cameras, Lighting, E-Field, etc.)
- Facility Startup / Testing
- Procedures Development Training Program Development Personnel Training NRC Demonstrations Startup Testing of Ancillary Equipment Cask Loading and Closure Operations for Initial Campaign Alan Chapman 11
m m
m Site Specific Issues (Cont.)
LLLLl
- Major Procurement Items Multi Purpose Canister Storage Overpack Transfer Cask Handling and Ancillary Equipment Alan Chapman 12
Licensing UXL
- 10 CFR 72.210, General License
- Selection Considerations Flexibility Well Defined Regulatory Precedence Minimize TVA and Staff Resources Efficiency Associated With a Standard Design SQN Site Will Use a General License Lessons Learned
- Potential Submittals Radiological Emergency Plan Security Plan Quality Assurance Plan Tim Abney 13
-M Summary and Closing Remarks Tim Abney 14