February 2002 Monthly Operating Report for Seabrook Station, Unit 1
ML020790298
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 03/08/2002
From: St.Pierre G
North Atlantic Energy Service Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NY-02025
Download: ML020790298 (3)


Text

North Atlantic Energy Service Corporation NorthP.O.

Box 300 North Seabrook, NH 03874 S Atlantic (603) 474-9521 The Northeast Utilities System March 8, 2002 Docket No. 50-443 NYN-02025 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 Seabrook Station February 2002 Monthly Operating Report Enclosed please find Monthly Operating Report 02-02. This report addresses the operating and shutdown experience relating to Seabrook Station Unit 1 for the month of February, 2002 and is submitted in accordance with the requirements of Seabrook Station Technical Specification 6.8.1.5.

Should you require further information regarding this

matter, please contact Mr. James M. Peschel, Manager - Regulatory Programs, at (603) 773-7194.

Very truly yours, NORTH ATLANTIC ENERGY SERVICE CORP.

Gene F. St. Pierre Station Director cc:

H. J. Miller, NRC Region I Administrator G. F. Wunder, NRC Project Manager, Project Directorate 1-2 G.T. Dentel, NRC Senior Resident Inspector

OPERATING DATA REPORT DOCKET NO.

50-443 UNIT Seabrook I DATE March 1,2002 COMPLETED BY J. L. Dalton TELEPHONE (603) 773-7025 OPERATING STATUS

1.

Unit Name:

Seabrook Station Unit 1

2.

Reporting Period:

FEBRUARY 2002

3.

Licensed Thermal Power (MWt):

3411.0

4.

Design Electrical Rating (Net MWe):

1148.0

5.

Maximum Dependable Capacity (Net MWe):

1155.3

6.

If Changes Occur in Capacity Ratings (Items Number 3 through 5)

Not Applicable Since Last Report, Give Reasons:

This Month Yr-to-Date Cumulative

7.

Number of Hours Reactor Was Critical 672.0 1416.0 87919.9

8.

Hours Generator On-Line 672.0 1416.0 85124.7

9.

Unit Reserve Shutdown Hours 0.0 0.0 0.0

10.

Net Electrical Energy Generated (MWH) 778295 1639785 95525317 1 of 2 OPERATING

SUMMARY

The unit operated at 100% Rated Thermal Power (RTP) for the entire month. This yielded an availability factor of 100% and a capacity factor of 100.2% based on the MDC value of 1155.3 Net MWe.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.

50-443 UNIT Seabrook I DATE March 1, 2002 COMPLETED BY J. L. Dalton TELEPHONE (603) 773-7025 MONTH: FEBRUARY 2002 2 of 2 NO.

DATE TYPE' DURATION REASON2 METHOD OF SHUTTING CAUSE / CORRECTIVE ACTIONS (HOURS)

DOWN REACTOR COMMENTS No entries for this month.

2 3

F:

Forced Reason:

Method:

S:

Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip C - Refueling 3 - Automatic Trip D - Regulatory Restriction 4 - Continued from previous month E - Operator Training / License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other (Explain)