February 2002 Monthly Operating Report for St. Lucie, Units 1 & 2
ML020770084
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 03/13/2002
From: Jernigan D
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, L-2002-050
Download: ML020770084 (7)


Text

0 I PL Florida Power & Light Company, 6501 South Ocean Drive, Jensen Beach, FL 34957 March 13, 2002 L-2002-050 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Re:

St. Lucie Units 1 and 2 Docket Nos. 50-335 and 50-389 Monthly Operating Report Pursuant to Technical Specification 6.9.1.6, and the guidance of Generic Letter 97-02, attached are the February 2002 Operating Data Report, Summary of Operating Experience Report, and Unit Shutdowns and Power Reductions for St. Lucie Units 1 and 2.

Please contact us should there be any questions regarding this information.

Donald E. Jernigan Vice President St. Lucie Plant DEJ/spt Attachments an FPL Group company

" -, -, e,--- 9 -4

ýIk

DOCKET NO.:

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

50-335 St. Lucie Unit 1 Mar. 5, 2002 J. A. Rogers (772) 467-7296 REPORTING PERIOD: February 2002

1. Design Electrical Rating (Mwe-Net)
2. Maximum Dependable Capacity (Mwe-Net).
3. Number of Hours Reactor Critical
4. Number of Hours Generator On Line
5. Unit Reserve Shutdown Hours
6. Net Electrical Energy (MWH) 830 839 MONTH 672 672 0.0 577652

-YTD 1416 1416 0.0 1216730 CUMULATIVE 178016.5 176203 0.0 143893469

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-335 St. Lucie #1 Mar. 5, 2002 J.A. Rogers (772) 467-7296 REPORT MONTH February 2002 Unit 1 operated at essentially full power through the entire month of February.

In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-335 St. Lucie #1 Mar. 5, 2002 J.A. Rogers (772) 467-7296 REPORT MONTH February 2002 Reason A - Equipment Failure (Explain)

B Maintenance or Test C

Refueling D - Regulatory Restriction E

Operator Training & License Examination F - Administrative G - Operational Error (Explain)

H - Other (Explain)

Method 1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continued 5 - Load Reduction 9 - Other (Explain)

Number Date Type I Duration Reason2 Method of Cause & Corrective (Hours)

Shutting Down Action to Reactor3 Prevent Recurrence Unit 1 operated at essentially full power for the entire month I

Iof February.

F Forced S

Scheduled 2

091S87 FPL

DOCKET NO.:

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

50-389 St. Lucie Unit 2 Mar. 5, 2002 J. A. Rogers (772) 467-7296 REPORTING PERIOD: February 2002

1. Design Electrical Rating (Mwe-Net)
2. Maximum Dependable Capacity (Mwe-Net).
3. Number of Hours Reactor Critical
4. Number of Hours Generator On Line
5. Unit Reserve Shutdown Hours
6. Net Electrical Energy (MWH) 830 839 MONTH 657.4 654.6 0.0 555263

-YTD 1401.4 1398.6 0.0 1193326 CUMULATIVE 141414.6 139656.3 0.0 114923972

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-389 St. Lucie #2 Mar. 5, 2002 J.A. Rogers (772) 467-7296 REPORT MONTH February 2002 Unit 2 downpowered on February 4 and was removed from service on February 5 for repair of switchyard equipment.

In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-389 St. Lucie #2 Mar.5, 2002 J.A. Rogers (772) 467-7296 REPORT MONTH February 2002 Reason A - Equipment Failure (Explain)

B - Maintenance or Test C

Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error (Explain)

H - Other (Explain)

Method 1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continued 5 -

Load Reduction 9 - Other (Explain) 091587 FPL Number Date Typel Duration Reason2 Method of Cause & Corrective (Hours)

Shutting Down Action to Reactor3 Prevent Recurrence 1

2/4/02 S

0.0 A

5 Unit 2 downpowered for repair of switchyard equipment.

2 2/5/02 S

17.4 A

I Unit 2 offline for repair of switchyard equipment F

Forced S

Scheduled