U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF SIGNIFICANT LICENSEE MEETING March 7, 2002 Meeting No.02-009 Licensee:
Dominion Nuclear Connecticut, Inc.
Facilities:
Millstone Units 2 and 3 Docket Nos.:
05000336 and 05000423 Date and Time:
Thursday, March 21, 2002, at 1:30 p.m.
Location:
Millstone Nuclear Power Station L. F. Sillin Jr. Nuclear Training Center Simulator Training Building Rope Ferry Road, Route 156 Waterford, CT 06385
Purpose:
The NRC staff and Dominion management will discuss the results of the NRCs assessment of the safety performance at the Millstone Nuclear Power Station for the period April 1, 2001 to December 31, 2001. This assessment is described in the Annual Assessment Letter, dated March 4, 2002 and can be found at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/mill_2001q4.pdf.
The NRC staff will also provide an overview of the NRCs Reactor Oversight Process. Detailed PI and inspection finding information can be found at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/MILL2/mill2_chart.html and http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/MILL3/mill3_chart.html.
NRC Attendees:
A. Blough, Director, Division of Reactor Projects (DRP), Region I C. Cowgill, Branch Chief, DRP, Region I A. Cerne, Senior Resident Inspector, Millstone Unit 3 B. Sienel, Resident Inspector, Millstone Unit 2 Dominion Attendees: J. Alan Price, Vice-President - Nuclear Technical Services/Millstone C. J. Schwarz, Director, Nuclear Station Operations and Maintenance S. E. Scace, Director, Nuclear Engineering G. D. Hicks, Director, Nuclear Station Safety and Licensing P. J. Parulis, Manager, Nuclear Oversight NOTE: This meeting is open to the public for observation. Members of the public may provide comments or questions in writing in advance of the meeting. They may be sent to USNRC, Attn:
Curtis J. Cowgill, 475 Allendale Road, King of Prussia, PA 19406. Attendance by additional NRC personnel should be made know by March 18, 2002, via telephone call to Curtis J. Cowgill, Chief,
2 Projects Branch 6 at (610) 337-5233. Handicapped persons requiring assistance to attend or participate in the meeting shall make their requests known no later than two business days prior to the meeting.
/RA A. McMurtray for/
Approved by: ____________________________
Curtis J. Cowgill, Chief Projects Branch No. 6 Division of Reactor Projects Distribution:
W. Matthews, Vice President and Senior Nuclear Executive J. A. Price, Vice-President - Nuclear Technical Services/Millstone State of Connecticut Regional Administrator Secretary, RI Deputy Regional Administrator Secretary, RI DRP Division Secretary, RI DRS Division Secretary, RI DNMS Division Secretary, RI DRM Division Secretary, RI Region I Receptionist
3 Distribution (Via E-Mail):
W. Travers, Executive Director for Operations, OEDO W. Kane, Deputy Executive Director for Regulatory Programs, OEDO T. Bergman, Region I Coordinator, OEDO S. Collins, Director, Office of Nuclear Reactor Regulation (NRR)
D. Matthews, Director, Division of Regulatory Improvement Programs, NRR J. Zwolinski, Director, Division of Licensing Project Management, NRR J. Johnson, Deputy Director, Office of Nuclear Regulatory Research E. Adensam, NRR D. Collins, NRR V. Nerses, NRR PMNS NRCWEB D. Screnci, PAO N. Sheehan, PAO G. Matakas, ORA R. Bores, ORA D. White, SAO W. Lanning, DRS R. Crlenjak, DRS S. Schneider, DRP A. Cerne, DRP DOCUMENT NAME: C:\\Program Files\\Adobe\\Acrobat 4.0\\PDF Output\\2002millMN.wpd After declaring this document An Official Agency Record it willbe released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI:DRP RI:DRP NAME Jenison/KMJ Cowgill/ACM f/
DATE 03/07/02 03/07/02 OFFICIAL RECORD COPY