January 2002 Monthly Operating Report for Monticello Nuclear Generating Plant
ML020590360
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 02/13/2002
From: Forbes J
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML020590360 (4)


Text

NMcl Committed to Nuclear Eclec f Monticello Nuclear Generating Plant Operated by Nuclear Management Company, LLC February 13, 2002 US Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 MONTICELLO NUCLEAR GENERATING PLANT Docket No. 50-263 License No. DPR-22 Submittal of Monticello Monthly Operatina Report for January 2002 In accordance with Monticello Technical Specification 6.7.A.3, the report of operating statistics for the Monticello Nuclear Generating Plant for the month of January is provided.

Please contact Paul Hartmann, Senior Licensing Analyst, at (763) 271-5172 if you require further information.

Jeffrey S. Forbes Site Vice President Monticello Nuclear Generating Plant c: Regional Administrator- III, NRC NRR Project Manager, NRC Sr. Resident Inspector, NRC Minnesota Dept. of Commerce J:\LICENSE\NRC Misc Correspondence\Monthly Operating Report.doc 2807 West County Road 75

  • Monticello, Minnesota 55362-9637 Telephone: 763.295.5151
  • Fax: 763.295.1454

OPERATING DATA REPORT DOCKET NO. 50-263 DATE 2 2 COMPLETED BY E. H. Limbeck TELEPHONE 763/295-1006 OPERATING STATUS

]Notes

1. Unit Name :_Monticello ]] ]]
2. Reporting period: January
3. Licensed Thermal Power (MWt) : 1775 ] I
4. Nameplate Rating (Gross MWe): 613 ] ]
5. Design Electrical Rating (Net MWe) : 600 ] ]
6. Maximum Dependable Capacity (Gross MW~eYT605.1 ] ]
7. Maximum Dependable Capacity (Net MWe): 578.1 ] ]
8. If Changes Occur in Capacity Ratings (Ite-ms Nun] ber 3 Through 7) Since Last Report, Give Reasons: N/A
9. Power Level To Which Restricted, If Any (Net MW( e): N/A
10. Reasons For Restrictions, If Any: __N/A THIS MONTH YR. -TO-DATE CUMULATIVE
11. Hours In Reporting Period 744 744 268153
12. Number Of Hours Reactor. Was Critical 656.0 656.0 220825.6
13. Reactor Reserve Shutdown Hours 0.0 0.0 940.7
14. Hours Generator On-Line 604.1 604.1 217402.8
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1049743 1049743 343172095
17. Gross Electrical Energy Generated (MWH) 362736 362736 116429220
18. Net Electrical Energy Generated (MWH) 349057 349057 111499042
19. Unit Service Factor 81.2% 81.2% 81.1%
20. Unit Availability Factor 81.2% 81.2% 81.1%
21. Unit Capacity Factor (Using MDC Net) 81.2% 81.2% 76.8%
22. Unit Capacity Factor (Using DER Net) 78.2% 78.2% 75.4%
23. Unit Forced Outage Rate 18.8% 18.8% 4.7%
24. Shutdowns Scheduled Over Next 12 Months (Type, I)ate, and Duration of Each)

_Not Reported

25. If Shut Down At End Of Report Period, Estimated Date Of Startup:
26. Units In Test Status(Prior to Commercial Operati on): N/A Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

NARRATIVE

SUMMARY

OF OPERATING EXPERIENCE DATE 2 2 TELEPHONE 763/295-1006 MONTH JAN 01-01-02 Power operation.

to 01-11-02 01-11-02 Power reduction to 65% to perform Maximum Core Flow/Prompt to Flow Control Line Determination test, investigate Main 01-12-02 Condenser air in-leakage and to adjust control rods and precondition fuel.

01-12-02 Power operation.

to 01-21-02 01-21-02 Reactor shutdown following scram. Failure of the Pressure to Control System caused a load reject signal. The return to 01-27-02 power was delayed by the failure of MO-2076, RCIC Steam Line Isolation Outboard, during startup, and subsequent repair.

01-27-02 Reduced power operations during startup for scram recovery.

to 01-29-02 01-29-02 Power operation.

to 01-31-02 Note: Power operation defined as essentially 100% of rated power except for weekend load drops for specified surveillance testing.

UNIT SHUTDOWNS DOCKET NO. 50-263 UNIT NAME Monticello DATE 02-01-02 COMPLETED BY E. H. Limbeck REPORT MONTH January TELEPHONE 763-295-1006 Method of Cause & Corrective Type Duration Reason Shutdown Action to No. Date (1) (hours) (2) (3) Prevent Recurrence 1/21/02 F 139.9 A 3 Load reject signal. The Mechanical Pressure Regulator (MPR) began competing with the Electrical Pressure Regulator to control system pressure. The rate feedback bellows on the MPR was found to have cracks and was repaired.

1 2 3 4 F Forced Reason: Method: Draft IEEE Standard S Scheduled A Equipment Failure (Explain) 1 Manual 805-1984 (P805-D5)

B Maintenance or Test 2 Manual Scram C Refueling 3 Automatic Scram 5 D Regulator Restriction 4 Other (Explain) IEEE Standard 803A-1983 E Operator Training & Licensing Examination F Administrative G Operational Error (Explain)

H Other (Explain)