ML020580451
| ML020580451 | |
| Person / Time | |
|---|---|
| Site: | Perry |
| Issue date: | 02/11/2002 |
| From: | Dunn G FirstEnergy Nuclear Operating Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| GL-97-002, PY-CEI/NRR-2615L | |
| Download: ML020580451 (3) | |
Text
Perry Nuclear Power Plant 10 Center Road FE OCP.O.
Box 97 FirstEnergy N-clear Operting C pany Perry, Ohio 44081 Feburary 11, 2002 PY-CEI/NRR-2615L United States Nuclear Regulatory Commission Document Control Desk Washington, D.C.
20555 Perry Nuclear Power Plant Docket No. 50-440 License No. NPF-58 Monthly Operating Report Ladies and Gentlemen:
Attached is a re-issue of November 2001 Monthly Operating Report for Perry Unit 1. Page 1 contains the Operating Data Report and page 2 contains the Unit Shutdowns Report. This report was submitted in accordance with Technical Specification 5.6.4 and Generic Letter 97-02, "Revised Contents of the Monthly Operating Report" on December 12, 2001. This report is being resubmitted as the previous letter had the incorrect month's data attached.
I apologize for any inconvenience this may have caused. If you have questions or require additional information, please contact Ms. Toni Phelps at (440) 280-7660.
Very truly yours, Gregory A. Dunn Manager - Regulatory Affairs Attachment cc: NRC Region III Administrator NRC Project Manager NRC Resident Inspector
OPERATING DATA REPORT UNIT:
Perry_
DATE:
12/10/01 Docket: 50-440 Unit Name:
Perry Nuclear Power Plant Reporting Period: November 2001 Utility
Contact:
T. Phelps Telephone: 440-280-7660 Design Electrical Rating (Net MWe):
Maximum Dependable Capacity (Net MWe):
- 1.
- 2.
- 3.
- 4.
- 5.
- 6.
7-Hours Reactor was Critical Hours Generator On-Line Unit Reserve Shutdown Hours Net Electrical Energy (MWeH)
This Month 720.0 720.0 0.0 907_234.0 Yr-to-Date 6,285.4
- r. nwt sz 0.0 7066.780.0 Cumulative 95,894.0 93,446.0 0.0 105.887.737.0
- The New Design Electrical Rating is based on the 105% uprate which was completed April of 2001.
- The new MDC was effective April 1,2001.
Page 1 1266*
1241 **
- 8.
- 9.
- 10.
11.
UNIT SHUTDOWNS REPORT MONTH - NOVEMBER 2001 DOCKET NO: 50-440 NAME: Perry Nuclear Power Plant DATE: 12/10/01 CONTACT: T. Phelps TELEPHONE: (440) 280-7660 No.
Date Type Duration Reason Method Cause and Corrective Action to Prevent Recurrence 1
Hours 2
3
SUMMARY
- The Perry plant began the month on line. The unit remained on line the entire month of November, 2001
- 1. TYPE:
F: Forced S: Scheduled
- 2. REASON:
A - Equipment Failure (explain)
B - Maintenance or Test C - Refueling D - Regulatory E - Operating Training &
License Examination F - Administrative G - Operational Error (explain)
H - Other (explain)
- 3. METHOD:
1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continuation 5 - Other Page 2