January 2002 Monthly Operating Report for Perry Nuclear Power Plant, Unit 1
ML020580448
Person / Time
Site: Perry 
Issue date: 02/11/2002
From: Dunn G
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, PY-CEI/NRR-2616L
Download: ML020580448 (3)


Text

Perry Nuclear Power Plant FENOC10 Center Road PrO. Box 97 FirstEnergy NuclearOperating 70p0ny Perry, Ohio 44081 February 11, 2002 PY-CEI/NRR-2616L United States Nuclear Regulatory Commission Document Control Desk Washington, D.C.

20555 Perry Nuclear Power Plant Docket No. 50-440 License No. NPF-58 Monthly Operating Report Ladies and Gentlemen:

Attached is the January 2002 Monthly Operating Report for Perry Unit 1. Page 1 is the Operating Data Report and page 2 is the Unit Shutdowns Report. This report is submitted in accordance with Technical Specification 5.6.4 and Generic Letter 97-02, "Revised Contents of the Monthly Operating Report."

If you have questions or require additional information, please contact Ms. Toni Phelps at (440) 280-7660.

Very truly yours, Gregory A.D nn Manager - Regulatory Affairs Attachment cc: NRC Region III Administrator NRC Project Manager NRC Resident Inspector

OPERATING DATA REPORT UNIT:

Perry_

DATE:

02/07/02

1.

Docket: 50-440

2.

Unit Name:

Perry Nuclear Power Plant

3.

Reporting Period: January 2002

4.

Utility

Contact:

T. Phelps

5.

Telephone: 440-280-7660

6.

Design Electrical Rating (Net MWe):

1260*

7.

Maximum Dependable Capacity (Net MWe):

1235**

This Month Yr-to-Date Cumulative

8.

Hours Reactor was Critical 744.0 744.0 97,329.2 a

Hou.rs Gnerato',r On-I ine 7440 744.0 94.817.0

10.

Unit Reserve Shutdown Hours

11.

Net Electrical Energy (MWeH)

The New Design Electrical Rating' The new MDC was effective April 1

"* *A new Design Electrical Rating is

    • The new MDC is 1235 MWe 0.0 0.0 0.0 918,229.0 918,229.0 107,518,631.0 is based on the 105% uprate which was completed April of 2001.

1,2001.

based on new net generation definitions Page 1 r

)

UNIT SHUTDOWNS REPORT MONTH - JANUARY 2002 DOCKET NO: 50-440 NAME: Perry Nuclear Power Plant DATE: 02/07/02 CONTACT: T. Phelps TELEPHONE: (440) 280-7660 No.

Date Type Duration Reason Method Cause and Corrective Action to Prevent Recurrence 1

Hours 2

3

SUMMARY

The Perry Plant remained on line the entire month.
1. TYPE:

F: Forced S: Scheduled

2.

REASON:

A - Equipment Failure (explain)

B - Maintenance or Test C - Refueling D - Regulatory E - Operating Training &

License Examination F - Administrative G - Operational Error (explain)

H - Other (explain)

3.

METHOD:

1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continuation 5 - Other Page 2