ML020500687

From kanterella
Jump to navigation Jump to search

Issuance of Order for Interim Compensatory Security Measures
ML020500687
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 02/25/2002
From: Collins S
Office of Nuclear Reactor Regulation
To: Saunders R
FirstEnergy Corp, FirstEnergy Nuclear Operating Co
Pickett D, NRR/DLPM, 415-1364
References
TAC MB4163
Download: ML020500687 (6)


Text

SAFEGUARDS INFORMATION February 25, 2002 Robert F. Saunders President and Chief Nuclear Officer Perry Nuclear Power Plant, Unit 1 FirstEnergy Nuclear Operating Company FirstEnergy Corporation 76 South Main Street Akron, OH 44308

SUBJECT:

ISSUANCE OF ORDER FOR INTERIM SAFEGUARDS AND SECURITY COMPENSATORY MEASURES FOR - PERRY NUCLEAR POWER PLANT, UNIT 1

Dear Mr. Saunders:

The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Order that modifies the current operating license for your facility to require compliance with the specified interim safeguards and security compensatory measures. The Order applies to all Addressees listed in to the enclosed Order. These interim compensatory measures are listed in (contains Safeguards Information) to the enclosed Order. The Commission recognizes that you have voluntarily and responsibly implemented additional security measures following the events of September 11, 2001, but, in light of the continuing generalized high-level threat environment, the Commission concludes that the security measures should be embodied in an Order, consistent with the established regulatory framework. The Commission has determined that the generalized high-level threat environment requires that the enclosed Order be effective immediately.

These actions are interim and the basis for the Order is the need to take prudent actions to address security requirements in the present generalized high-level threat environment. This Order does not obviate the need for licensees to continue to meet the objectives of Security Level III described in NRC Information Notice 98-35, and maintain the effectiveness of existing security measures taken in response to the events of September 11, 2001. The requirements will remain in effect pending notification from the Commission that a significant change in the threat environment has occurred, or until the Commission determines that other changes are needed following a more comprehensive re-evaluation of current safeguards and security programs.

The enclosed Order calls for responses and actions within specified time frames. Please contact your Licensing Project Manager to facilitate resolution of any issues related to compliance with the requirements in the enclosed Order, or if you have any other questions.

NOTICE: Attachment 2 to the Order (Interim Compensatory Measures) contains "Safeguards Information." Upon separation of Attachment 2 to the Order, this letter, the enclosed Order, and Attachment 1 to the Order (Address List) are "DECONTROLLED."

SAFEGUARDS INFORMATION

R. Saunders The enclosed Order has been forwarded to the Office of the Federal Register for publication.

Sincerely,

/RA/

Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No. 50-440

Enclosures:

1. Order
2. Order Attachment 1 - Address List
3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page

Perry Nuclear Power Plant, Unit 1 cc:

Mary E. O'Reilly FirstEnergy Corporation 76 South Main St.

Akron, OH 44308 Resident Inspector's Office U.S. Nuclear Regulatory Commission P.O. Box 331 Perry, OH 44081-0331 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4531 Sue Hiatt OCRE Interim Representative 8275 Munson Mentor, OH 44060 Gregory A. Dunn Manager - Regulatory Affairs FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P.O. Box 97, A210 Perry, OH 44081 William R. Kanda, Plant Manager FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P.O. Box 97, SB306 Perry, OH 44081 Mayor, Village of North Perry North Perry Village Hall 4778 Lockwood Road North Perry Village, OH 44081 Donna Owens, Director Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P. O. Box 4009 Reynoldsburg, OH 43068-9009 Carol OClaire, Chief, Radiological Branch Ohio Emergency Management Agency 2855 West Dublin Granville Road Columbus, OH 43235-7150 Mayor, Village of Perry P.O. Box 100 Perry, OH 44081-0100 Dennis Clum Radiological Assistance Section Supervisor Bureau of Radiation Protection Ohio Department of Health P.O. Box 118 Columbus, OH 43266-0118 Ohio Environmental Protection Agency DERR--Compliance Unit ATTN: Mr. Zack A. Clayton P.O. Box 1049 Columbus, OH 43266-0149 Chairman Perry Township Board of Trustees 3750 Center Road, Box 65 Perry, OH 44081 State of Ohio Public Utilities Commission East Broad Street Columbus, OH 43266-0573

R. Saunders February 25, 2002 The enclosed Order has been forwarded to the Office of the Federal Register for publication.

Sincerely,

/RA/

Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No. 50-440

Enclosures:

1. Order
2. Order Attachment 1 - Address List
3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):

PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)

PD3-2 DPickett THarris SBajwa AMendiola RidsRgn3MailCenter Accession No. ML020490065 (Package)

Accession No. ML020 (Cover Letter)

Accession No. ML020510635 (Order)

Accession No. ML020520654 (Order Attachment 1 - Address List)

OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY

CNO Heading The enclosed Order has been forwarded to the Office of the Federal Register for publication.

Sincerely,

/RA/

Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No(s).

Enclosures:

1. Order
2. Order Attachment 1 - Address List
3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):

PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)

PD Reading Project Director Section Chief Project Manager Licensing Assistant Region Contact Accession No. ML020520754 (Package)

Accession No. ML020510637 (Cover Letter)

Accession No. ML020510635 (Order)

Accession No. ML020520654 (Order Attachment 1 - Address List)

OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY