SAFEGUARDS INFORMATION February 25, 2002 David Christian Senior Vice President - Nuclear Operations and Chief Nuclear Officer Millstone Nuclear Power Station, Unit Nos. 2 & 3 Innsbrook Technical Center - 2SW 5000 Dominion Boulevard Glenn Allen, VA 23060

SUBJECT:

ISSUANCE OF ORDER FOR INTERIM SAFEGUARDS AND SECURITY COMPENSATORY MEASURES FOR - MILLSTONE NUCLEAR POWER STATION, UNIT NOS. 2 & 3

Dear Mr. Christian:

The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Order that modifies the current operating license for your facility to require compliance with the specified interim safeguards and security compensatory measures. The Order applies to all Addressees listed in to the enclosed Order. These interim compensatory measures are listed in (contains Safeguards Information) to the enclosed Order. The Commission recognizes that you have voluntarily and responsibly implemented additional security measures following the events of September 11, 2001, but, in light of the continuing generalized high-level threat environment, the Commission concludes that the security measures should be embodied in an Order, consistent with the established regulatory framework. The Commission has determined that the generalized high-level threat environment requires that the enclosed Order be effective immediately.

These actions are interim and the basis for the Order is the need to take prudent actions to address security requirements in the present generalized high-level threat environment. This Order does not obviate the need for licensees to continue to meet the objectives of Security Level III described in NRC Information Notice 98-35, and maintain the effectiveness of existing security measures taken in response to the events of September 11, 2001. The requirements will remain in effect pending notification from the Commission that a significant change in the threat environment has occurred, or until the Commission determines that other changes are needed following a more comprehensive re-evaluation of current safeguards and security programs.

The enclosed Order calls for responses and actions within specified time frames. Please contact your Licensing Project Manager to facilitate resolution of any issues related to compliance with the requirements in the enclosed Order, or if you have any other questions.

NOTICE: Attachment 2 to the Order (Interim Compensatory Measures) contains "Safeguards Information." Upon separation of Attachment 2 to the Order, this letter, the enclosed Order, and Attachment 1 to the Order (Address List) are "DECONTROLLED."

SAFEGUARDS INFORMATION

D. Christian The enclosed Order has been forwarded to the Office of the Federal Register for publication.

Sincerely,

/RA/

Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket Nos. 50-336 and 50-423

Enclosures:

1. Order
2. Order Attachment 1 - Address List
3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page

Millstone Nuclear Power Station Units 2 and 3 cc:

Ms. L. M. Cuoco Senior Nuclear Counsel Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Hartford, CT 06141-0270 Edward L. Wilds, Jr., Ph.D.

Director, Division of Radiation Department of Environmental Protection 79 Elm Street Hartford, CT 06106-5127 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 First Selectmen Town of Waterford 15 Rope Ferry Road Waterford, CT 06385 Mr. W. R. Matthews Vice President and Senior Nuclear Executive - Millstone Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. Charles Brinkman, Manager Washington Nuclear Operations ABB Combustion Engineering 12300 Twinbrook Pkwy, Suite 330 Rockville, MD 20852 Senior Resident Inspector Millstone Nuclear Power Station c/o U.S. Nuclear Regulatory Commission P. O. Box 513 Niantic, CT 06357 Mr. P. J. Parulis Manager - Nuclear Oversight Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Ernest C. Hadley, Esq.

P. O. Box 1104 West Falmouth, MA 02574-1104 Mr. John Markowicz Co-Chair Nuclear Energy Advisory Council 9 Susan Terrace Waterford, CT 06385 Mr. C. J. Schwarz Director - Nuclear Operations and Chemistry Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. D. A. Smith Manager - Regulatory Affairs Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Ms. Nancy Burton 147 Cross Highway Redding Ridge, CT 00870 Mr. G. D. Hicks Director - Nuclear Training Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. Evan W. Woollacott Co-Chair Nuclear Energy Advisory Council 128 Terrys Plain Road Simsbury, CT 06070

Millstone Nuclear Power Station Units 2 and 3 cc:

Mr. William D. Meinert Nuclear Engineer Massachusetts Municipal Wholesale Electric Company P.O. Box 426 Ludlow, MA 01056 Mr. J. Alan Price Vice President - Nuclear Operations - Millstone c/o Mr. David A. Smith Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385

D. Christian February 25, 2002 The enclosed Order has been forwarded to the Office of the Federal Register for publication.

Sincerely,

/RA/

Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket Nos. 50-336 and 50-423

Enclosures:

1. Order
2. Order Attachment 1 - Address List
3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):

PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)

PD1-2 VNerses TClark EAdensam JClifford RidsRgn1MailCenter Accession No. ML020490017 (Package)

Accession No. ML020 (Cover Letter)

Accession No. ML020510635 (Order)

Accession No. ML020520654 (Order Attachment 1 - Address List)

OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY

CNO Heading The enclosed Order has been forwarded to the Office of the Federal Register for publication.

Sincerely,

/RA/

Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No(s).

Enclosures:

1. Order
2. Order Attachment 1 - Address List
3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):

PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)

PD Reading Project Director Section Chief Project Manager Licensing Assistant Region Contact Accession No. ML020520754 (Package)

Accession No. ML020510637 (Cover Letter)

Accession No. ML020510635 (Order)

Accession No. ML020520654 (Order Attachment 1 - Address List)

OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY