ML020350453

From kanterella
Jump to navigation Jump to search
December 2001 Monthly Operating Report for R.E. Ginna Nuclear Power Plant
ML020350453
Person / Time
Site: Ginna Constellation icon.png
Issue date: 01/10/2002
From: Widay J
Rochester Gas & Electric Corp
To:
Document Control Desk, NRC/NRR/DLPM/LPD1
References
Download: ML020350453 (3)


Text

ROCHESTER GAS AND ELECTRIC CORPORATION & 89 EAST AVENUE, ROCHESTER, N. Y 74649-0001 AREA CODE 716 546-2700 January 10, 2002 US Nuclear Regulatory Commission Document Control Desk Attn: Robert Clark Project Directorate I-1 Washington, DC 20555

Subject:

Monthly Report for December, 2001 Operating Status Information R.E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Mr. Clark:

Pursuant to Ginna Improved Technical Specifications Section 5.6.4, attached is the monthly operating status report for Ginna Station for the month of December, 2001.

Very truly yours, se A. Widay Plant Manager xc: U.S. Nuclear Regulatory Commission Mr. Robert Clark (Mail Stop O-8E9)

Project Directorate I-1 Washington, D.C. 20555 U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 U.S. NRC Ginna Senior Resident Inspector Attachments

OPERATING DATA REPORT 50-244 January 10, 2002 COMPLETED BY:

/John V. Walden TELEPHONE (585) 771-3588 OPERATING STATUS

1. Unit Name: R.E. GINNA NUCLEAR POWER PLANT Notes:
2. Reporting Period: December, 2001
3. Design Electric Rating (Net MWe): 470
4. Maximum Dependable Capacity (Net MWe): 480 This Month Yr.-to-Date Cumulative**
5. Number of hours Reactor Was Critical 744.0 8760.0 231022.2
6. Hours Generator On-line 744.0 8760.0 227906.1
7. Unit Reserve Shutdown Hours 0.0 0.0 8.5
8. Net Electrical Energy Generated (MWH) 369246.0 4286279.0 103485560.8
    • CUMULATIVE TOTAL COMMENCING NOVEMBER 8,1969

DOCKET NO: 50-244 UNIT NAME: R.E. GINNA NUCLEAR POWER PLANT DATE: January 10, 2002 COMPLETED BY: John V. Walden TELEPHONE: (585) 771-3588 UNIT SHUTDOWN REPORTING PERIOD: December, 2001 (Month/Year)

NO. DATE TYPE DURATION REASON(1 ) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUTTING 5: SCHEDULED DOWN(2) COMMENTS

SUMMARY

The unit operated at full power for the entire month of December. Average power for the month of December was 99.8%.

(1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other (Explain)