Peter E. Katz Plant General Manager 1650 Calvert Cliffs Parkway Lusby, Maryland 20657 410 495-4101 Constellation Nuclear Calvert Cliffs Nuclear Power Plant A Member of the Constellation Energy Group January 14, 2002 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:
SUBJECT:
Document Control Desk Calvert Cliffs Nuclear Power Plant Unit Nos. 1 & 2; Docket Nos. 50-317 & 50-318 December 2001 Operating Data Reports The subject reports are being sent to you as required by Technical Specification 5.6.4.
Should you have questions, please contact Mr. Bruce B. Mrowca at (410) 495-3989.
Very truly yours, PEKITWG/bjd Attachments cc:
R. S. Fleishman, Esquire J. E. Silberg, Esquire Director, Project Directorate I-1, NRC D. M. Skay, NRC H. J. Miller, NRC Resident Inspector, NRC R. I. McLean, DNR J. Wright, INPO K. N. Larson, ANI
OPERATING DATA REPORT Docket No.
50-317 Calvert Cliffs Unit 1 January 3, 2002 Prepared by Herman 0. Olsen Telephone: (410)495-6734 REPORTING PERIOD DESIGN ELECTRICAL RATING (NET MWe)
MAXIMUM DEPENDABLE CAP'Y (NET MWe)
DECEMBER 2001 845 825 This month NUMBER OF HOURS REACTOR WAS CRITICAL HOURS GENERATOR ON LINE UNIT RESERVE SHUTDOWN HOURS NET ELECTRICAL ENERGY GENERATED(MWH) 744.0 744.0 0.0 641,102 Year to-Date 8,734.2 8,727.8 0.0 7,454,775 Cumulative to Date 177,732.1 174,615.7 0.0 142,522,083
- 1.
- 2.
- 3.
4.
UNIT SHUTDOWNS DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE 50-317 Calvert Cliffs - U 1 January 3, 2002 Herman 0. Olsen (410) 495-6734 REPORTING MONTH December 2001
' Reason:
A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error H - Other 2
Method:
I - Manual 2 - Manual Scram.
3 - Automatic Scram.
4 - Continued 5 - Other NO.
DATE TYPE DURATION REASON' METHOD OF CAUSE/CORRECTIVE ACTIONS F:
FORCED (HOURS)
SHUTTING S:
SCHEDULED DOWN' COMMENTS There were no shutdowns this month.
DOCKET NO. 50-317 CALVERT CLIFFS - UNIT 1 January 3, 2002
SUMMARY
OF OPERATING EXPERIENCE December 2001 The unit began the month at 100%.
Power was reduced to 85% on 12/14/01 to perform Main Turbine Valve Testing. After the completion of testing, power was returned to 100% on 12/15/01 at 0405.
The unit operated at 100% power for the remainder of the month.
OPERATING DATA REPORT Docket No.
50-318 Calvert Cliffs Unit 2 January 3, 2002 Prepared by Herman 0. Olsen Telephone: (410) 495-6734 REPORTING PERIOD DESIGN ELECTRICAL RATING (NET MWe)
MAXIMUM DEPENDABLE CAP'Y (NET MWe)
DECEMBER 2001 845 835 This month Year-Cumulative to-Date to Date
- 1. NUMBER OF HOURS REACTOR WAS CRITICAL
- 2.
HOURS GENERATOR ON LINE
- 3.
UNIT RESERVE SHUTDOWN HOURS
- 4.
NET ELECTRICAL ENERGY GENERATED(MWH) 744.0 744.0 0.0 7,334.3 7,298.6 0.0 168,799.8 166,944.7 0.0 646,233 6,201,519 137,105,878
UNIT SHUTDOWNS DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE 50-318 Calvert Cliffs-U2 January 3, 2002 Herman 0. Olsen (410) 495-6734 REPORT MONTH December 2001
' Reason:
A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error H - Other 2
Method:
1 - Manual 2 - Manual Scram.
3 - Automatic Scram.
4 - Continued 5 - Other NO.
DATE TYPE DURATION REASON 1 METHOD OF CAUSE/CORRECTIVE ACTIONS F:
FORCED (HOURS)
SHUTTING S:
SCHEDULED DOWN 2 COMMENTS There were no shutdowns this month.
DOCKET NO. 50-318 CALVERT CLIFFS - UNIT 2 January 3, 2002
SUMMARY
OF OPERATING EXPERIENCE December 2001 The unit operated at 100% power for the entire month.