VERMONT YANKEE
-NUCLEAR POWER CORPORATION 185 OLD FERRY ROAD, PO BOX 7002, BRATTLEBORO, VT 05302-7002 (802) 257-5271 January 14, 2002 BVY 02-04 SAFEGUARDS INFORMATION U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
Reference:
Letter, USNRC to VYNPC, "Vermont Yankee Generating Station - NRC Inspection Report 50-271/01-010," NVY 01-114, dated November 28, 2001
Subject:
Vermont Yankee Nuclear Power Station License No. DPR-28 (Docket No. 50-271)
NRC Inspection Report 50-271/01-010 Operational Safeguards Response Evaluation The referenced letter provided NRC's Inspection Report and preliminary results from an Operational Safeguards Response Evaluation (OSRE) conducted at the Vermont Yankee Nuclear Power Station (VYNPS) during the week of August 20, 2001.
In this matter, Vermont Yankee (VY) requested a Regulatory Conference (to be held on January 18, 2002), during which VY will provide its perspective on the OSRE.
The attached (Safeguards Information) represents VY's evaluation of the OSRE and includes aspects that differ from the findings and conclusions contained in the referenced inspection report. Foremost, VY's evaluation of the first two force-on-force drills, which were conducted on the evening of August 21, determined that those drills were entirely inconclusive because of significant artificialities in the exercises and controller errors.
VY acknowledges that there were some valuable lessons learned from the OSRE. In this regard, VY immediately established compensatory measures which NRC inspectors confirmed were adequate.
In addition, VY has initiated substantial efforts to upgrade and strengthen overall physical security capability at VYNPS.
We look forward to discussing this matter with you during the Regulatory Conference.
Sincerely, VERMONT YANKEE NUCLEAR POWER CORPORATION Michael A. Balduzzi Senior Vice President and Chief Nuclear Officer ENCLOSURE CONTAINS SAFEGUARDS INFORMATION UPON SEPARATION THIS PAGE IS DECONTROLLED
SAFEGUARDS INFORMATION cc:
(with attachment, via Federal Express only)
Mr. John R. White, Chief, Radiation Safety and Safeguards Branch, Region I Mr. Glenn M. Tracy, Chief, Operator Licensing, Human Performance and Plant Support Branch, NRR (mailstop 06 H16)
(without attachment)
USNRC Region I Administrator USNRC Resident Inspector - VYNPS USNRC Project Manager - VYNPS Vermont Department of Public Service SAFEGUARDS INFORMATION ENCLOSURE CONTAINS SAFEGUARDS INFORMATION UPON SEPARATION THIS PAGE IS DECONTROLLED