January 11, 2002 Mr. Howard Bergendahl Vice President - Nuclear, Davis-Besse FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
REVISION TO THE DAVIS-BESSE NUCLEAR POWER STATION NRC INSPECTION SCHEDULE
Dear Mr. Bergendahl:
This letter is to inform you of a change to the NRC inspection schedule at the Davis-Besse Nuclear Power Station. The NRC has postponed the Problem Identification and Resolution inspection which was originally scheduled to begin February 4, 2002. This inspection will now be conducted in the fall of 2002. The exact dates will be sent to you with our End-of-Cycle Assessment Letter and Inspection Plan in early March 2002. If you have any questions concerning this information, please contact me at 630-829-9619.
Sincerely, Original signed by Christine A. Lipa Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-346 License No. NPF-3 cc:
B. Saunders, President - FENOC Plant Manager Manager - Regulatory Affairs M. OReilly, FirstEnergy Ohio State Liaison Officer R. Owen, Ohio Department of Health Public Utilities Commission of Ohio
DOCUMENT NAME: G:\\DAVI\\davisbessepir.wpd To receive a copy of this document, indicate in the box:"C" = Copy without enclosure "E"= Copy with enclosure"N"= No copy OFFICE RIII RIII NAME LCollins:dtp CLipa DATE 01/11/02 01/11/02 OFFICIAL RECORD COPY
C. Bergendahl ADAMS Distribution: