ML020140063

From kanterella
Jump to navigation Jump to search
Reactor and Senior Reactor Operator Initial Examinations North Anna Power Station - 50-338/2002-301 and 50-339/2002-301
ML020140063
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 01/14/2002
From: Ernstes M
Operator Licensing and Human Performance Branch
To: Christian D
Virginia Electric & Power Co (VEPCO)
References
50-338/2002-301, 50-339/2002-301
Download: ML020140063 (5)


See also: IR 05000338/2002301

Text

January 14, 2002

Virginia Electric and Power Company

ATTN: Mr. David A. Christian

Senior Vice President and

Chief Nuclear Officer

Innsbrook Technical Center

5000 Dominion Boulevard

Glen Allen, VA 23060

SUBJECT: REACTOR AND SENIOR REACTOR OPERATOR INITIAL EXAMINATIONS

NORTH ANNA POWER STATION - 50-338/2002-301 AND 50-339/2002-301

Dear Mr. Christian:

In a telephone conversation on September 5, 2001, between Mr. Joe Scott, Supervisor of

Nuclear Training (Operations) and Mr. Ronald F. Aiello, Senior Operations Engineer,

arrangements were made for the administration of licensing examinations at the North Anna

Power Station, Units 1 and 2 during the week of June 10, 2002.

The NRC will prepare the examinations based on the guidelines in Revision 8, Supplement 1, of

NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." Your staff will

be given the opportunity to review the examinations during the week of May 13, 2002. The

facility has agreed to fill in the scenario details (ES-D-2) and the details of the JPMs. The

facility has also agreed to make all of the copies of the examination prior to administration.

In order to conduct the requested written examinations and operating tests, it will be necessary

for your staff to provide adequate space and accommodations in accordance with ES-402, and

to make the simulation facility available on the dates noted above. In accordance with ES-302,

your staff should retain the original simulator performance data (e.g., system pressures,

temperatures, and levels) generated during the dynamic operating tests until the examination

results are final.

Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in

effect while the written examinations and operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary reactor

operator and senior reactor operator license applications (Office of Management and Budget

(OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),

and waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first

examination date. If the applications are not received at least 30 days before the examination

date, a postponement may be necessary. Signed applications certifying that all training has

been completed should be submitted at least 14 days before the first examination date.

VEPCO 2

This letter contains information collections that are subject to the Paperwork Reduction Act of

1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of

Management and Budget, approval number 3150-0018, which expires on April 30, 2003. The

public reporting burden for this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per

response, including the time for reviewing instructions, gathering and maintaining the data

needed, and completing and reviewing the collection of information. Send comments on any

aspect of this collection of information, including suggestions for reducing the burden, to the

Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission,

Washington, DC 20555-0001, or by Internet electronic mail at BJS1@NRC.GOV; and to the

Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0101), Office of

Management and Budget, Washington, DC 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, a collection

of information unless it displays a currently valid OMB control number.

Thank you for your cooperation in this matter. Mr. Joe Scott has been advised of the policies

and guidelines referenced in this letter. If you have any questions regarding the NRC's

examination procedures and guidelines, please contact Mr. Ronald F. Aiello at (404) 562-4641,

(Internet E-mail: rfa@nrc.gov), or myself at (404) 562-4638, (Internet E-mail: mee@nrc.gov).

Sincerely,

/RA/

Michael E. Ernstes, Chief

Operator Licensing and

Human Performance Branch

Division of Reactor Safety

Docket Nos.: 50-338, 50-339

License Nos.: NPF -4, NPF - 7

cc: (See page 3)

VEPCO 3

cc contd:

Stephen P. Sarver, Director Donald P. Irwin, Esq.

Nuclear Licensing and Hunton and Williams

Operations Support Electronic Mail Distribution

Virginia Electric and Power Company

Electronic Mail Distribution Attorney General

Supreme Court Building

D. A. Heacock 900 East Main Street

Site Vice President Richmond, VA 23219

North Anna Power Station

Electronic Mail Distribution H. Ashley Royal

Manager Nuclear Training

Executive Vice President North Anna Power Station

Old Dominion Electric Cooperative P. O. Box 402

Electronic Mail Distribution Mineral, VA 23117

County Administrator

Louisa County

P. O. Box 160

Louisa, VA 23093

VEPCO 4

Distribution:

S. Mabaque, NRR

A. Boland (Part 72 Only)

RIDSNRRDIPMLIPB

PUBLIC

PUBLIC DOCUMENT (circle one): YES NO

OFFICE RII:DRS RII:DRS RII:DRP

SIGNATURE /RA/ /RA/ /RA By L Garner for/

NAME RAiello:pmd MErnstes KLandis

DATE 9/8/2001 1/10/2002 1/10/2002

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO

OFFICIAL RECORD COPY DOCUMENT NAME: C:\Program Files\Adobe\Acrobat 4.0\PDF Output\Corporate Notification

Lett~.wpd