MONTHYEARIR 05000336/20240032024-11-0707 November 2024 Integrated Inspection Report 05000336/2024003 and 05000423/2024003 and Apparent Violation and Independent Spent Fuel Storage Installation Inspection Report 07200008/2024001 IR 05000318/20240072024-11-0606 November 2024 Assessment Follow-Up Letter for Calvert Cliffs Nuclear Power Plant, Unit 2 (Report 05000318/2024007) IR 05000317/20240032024-10-22022 October 2024 Integrated Inspection Report 05000317/2024003, 05000318/2024003, and Independent Spent Fuel Storage Installation Report 07200008/2024001 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24283A0012024-10-0909 October 2024 Senior Reactor and Reactor Operator Initial License Examinations IR 05000317/20245012024-10-0707 October 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000317/2024501 and 05000318/2024501 ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000317/20240052024-08-29029 August 2024 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2024005 and 05000318/2024005) ML24240A2462024-08-27027 August 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report ML24240A1112024-08-27027 August 2024 Registration of Use of Casks to Store Spent Fuel ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000317/20240022024-08-0606 August 2024 Integrated Inspection Report 05000317/2024002 and 05000318/2024002 IR 05000317/20240102024-07-31031 July 2024 Age-Related Degradation Inspection Report 05000317/2024010 and 05000318/2024010 ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24198A0442024-07-16016 July 2024 Inservice Inspection Report IR 05000317/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000317/2024401 and 05000318/2024401 ML24177A1832024-06-25025 June 2024 Inservice Inspection Report RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24161A0012024-06-0909 June 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report ML24150A0522024-05-29029 May 2024 Operator Licensing Examination Approval ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24136A1962024-05-15015 May 2024 Independent Spent Fuel Storage Installation - Annual Radiological Environmental Operating Report IR 05000317/20240012024-05-0707 May 2024 Integrated Inspection Report 05000317/2024001 and 05000318/2024001 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000317/LER-2024-002, Emergency Diesel Generators Automatic Start Due to Loss of a 13kV Bus2024-04-29029 April 2024 Emergency Diesel Generators Automatic Start Due to Loss of a 13kV Bus 05000318/LER-2024-001, Manual Reactor Trip Due to 22 Steam Generator Feed Pump Trip2024-04-24024 April 2024 Manual Reactor Trip Due to 22 Steam Generator Feed Pump Trip ML24101A1942024-04-22022 April 2024 Closeout Letter for GL 2004-02 ML24114A0182024-04-18018 April 2024 Electronic Reporting of Occupational Exposure Reporting 05000318/LER-2023-004-01, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-04-12012 April 2024 Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000317/20240402024-04-11011 April 2024 95001 Supplemental Inspection Report 05000317/2024040 and Follow-Up Assessment Letter RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24082A0082024-03-22022 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 ML24078A1152024-03-18018 March 2024 10 CFR 50.46 Annual Report ML24059A0632024-03-15015 March 2024 Authorization and Safety Evaluation for Alternative Request ISI-05-021 (EPID L-2023-LLR-0006) - Non-Proprietary IR 05000317/20230062024-02-28028 February 2024 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2, (Reports 05000317/2023006 and 05000318/2023006 ML24052A0072024-02-14014 February 2024 Core Operating Limits Report for Unit 1, Cycle 27, Revision 0 ML24040A0962024-02-0909 February 2024 Notification of Readiness for NRC 95001 Inspection ML24040A1492024-02-0909 February 2024 Response to NRC Request for Additional Information Regarding Final Response to Generic Letter 2004-02 IR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank IR 05000317/20230102023-11-20020 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000317/2023010 and 05000318/2023010 2024-09-06
[Table view] Category:Congressional Correspondence
MONTHYEARML12279A3642012-10-0404 October 2012 EDATS: Region I-2012-0309 - Response Letter to Maryland Senator Reilly Regarding Calvert Cliffs Dropped Control Rod ML11213A0292011-07-22022 July 2011 G20110566/LTR-11-0440/EDATS: SECY-2011-0433 - Email & Ltr. Benjamin Cook (Rep. Chris Van Hollen'S Office) Calvert Cliffs CY-92-223, G20110523/LTR-11-0411/EDATS: SECY-2011-0411 - Ltr. from Rep. E.J. Markey to Chairman Jaczko NRC Safety Requirements for Reactors Granted Construction Permits Prior to 19712011-07-14014 July 2011 G20110523/LTR-11-0411/EDATS: SECY-2011-0411 - Ltr. from Rep. E.J. Markey to Chairman Jaczko NRC Safety Requirements for Reactors Granted Construction Permits Prior to 1971 ML0715809252007-06-0808 June 2007 Ltr to Congressman Peter J. Visclosky Providing an Invitation to the Subcommittee on Energy and Water Development to a Tour of Calvert Cliffs Nuclear Plant on Friday, July 27, 2007 ML0133002042002-01-29029 January 2002 G20010507/LTR-01-0595 & G20010534/LTR-01-0621- Sen. Barbara A. Mikulski Ltr, Proposed Reopened of Cove Point & Request for Nrc;S Active Participation in the Ferc'S Reconsideration of Cove Point Liquefied Natural Gas 2012-10-04
[Table view] |
Text
January 29, 2002 The Honorable Barbara A. Mikulski United States Senate Washington, D.C. 20610-2003
Dear Senator Mikulski:
I am responding on behalf of the Nuclear Regulatory Commission (NRC) to your letters of November 7 and November 14, 2001, concerning the proposed reactivation of the Cove Point liquified natural gas (LNG) terminal and its proximity to the Calvert Cliffs Nuclear Power Plant.
As part of its licensing basis and as specified in the Final Safety Analysis Report for the Calvert Cliffs plant, the licensee must demonstrate site suitability, in part, by evaluating the effects of accidents that could result from the operation of the Cove Point facility. The licensee is also required to submit a revised analysis when modifications are made to the LNG facility that could impact the safety of the Calvert Cliffs plant.
In 2001, the licensee informed the NRC that the owner of Cove Point intended to reactivate the terminal for importing LNG by ship in 2002 and to build an additional storage tank on site. The licensee has since assessed the effects of the proposed changes to Cove Point, and the conclusions of this assessment will be provided to the NRC for review when the licensees actions are complete.
In a safety evaluation issued August 31, 1995, the staff assessed the risks corresponding to the most credible accidents that might impact the safety of the nuclear plant and the independent spent fuel storage installation. Although the owners of Cove Point did not plan to import LNG by ship at the time of this evaluation, the NRC examined the potential hazards associated with shipping to ensure that shipping would not invalidate its conclusions.
These scenarios included release of LNG from a cargo tank on board a tanker caused by collision with another vessel, an explosion aboard a tanker, and an accident while unloading. In evaluating the consequences of the spilled LNG, the NRC staff considered the properties of LNG and its ability to vaporize, move toward Calvert Cliffs, ignite, and create an area of overpressure. The NRC staff concluded that, for the types of accidents that were considered to be most credible, the resulting ignition and overpressure would occur at sufficient distance from Calvert Cliffs as not to cause damage impacting the safety of the units.
In response to the recently proposed reactivation of the shipping terminal at Cove Point, the NRC has briefly reviewed the environmental assessment which was prepared by the Federal Energy Regulatory Commission (FERC). The environmental assessment indicates that the proposed frequency of ships arriving at the facility is less than that evaluated in 1995.
However, no study to date has considered the potential impact of terrorism. The NRC will review the licensees analysis in the context of its earlier evaluation, and considering the current
security concerns, will take actions as appropriate consistent with the agencys approach to handling potential terrorist activities.
I assure you that the NRC was an active participant in FERCs reconsideration of the Cove Point facility. The NRC staff maintained communication with FERC regarding this facility and participated in the November 16, 2001, technical conference with FERC and other stakeholders, including the Coast Guard, the Department of Transportation, the Department of Energy, and the owners of Cove Point. The NRC staff will also continue to maintain communication with FERC and other appropriate Federal agencies regarding this facility to ensure the protection of the health and safety of the public in the vicinity of the Calvert Cliffs Nuclear Power Plant.
If you have any further questions, please feel free to contact me.
Sincerely,
/RA/
Richard A. Meserve