ML013180423

From kanterella
Jump to navigation Jump to search
G20010499 - Ltr. NRC Inspection Plan at Indian Point 2
ML013180423
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 01/04/2002
From: Travers W
NRC/EDO
To: Lochbaum D
Union of Concerned Scientists
Shared Package
ML013180443 List:
References
G20010499
Download: ML013180423 (4)


Text

January 4, 2002 Mr. David A. Lochbaum Nuclear Safety Engineer Union of Concerned Scientists 1707 H Street NW Suite 600 Washington, DC 20006-3919

Dear Mr. Lochbaum:

In your letter of October 23, 2001, you questioned changes to NRC inspections at Indian Point Unit 2 referred to in our October 15th letter to Entergy. Entergys self-assessment efforts were presented to the NRC in a letter dated September 14, 2001, and included plans to perform a comprehensive evaluation by an independent team of 28 people over a three week period.

The results of this assessment, which was subsequently completed in October, are to be used by Entergy to evaluate the effectiveness of corrective actions and to revise the current performance improvement plan.

The NRC considered the changes to our inspection plans, which involved modifying an engineering team inspection and rescheduling a problem identification and resolution (PIR) team inspection, to be prudent in light of the potential benefits to be gained from an extensive self-assessment. The NRC will assess the effectiveness of Entergys self-assessment activities in future inspections by evaluating the extent to which the licensee was able to diagnose problems and develop and implement appropriate corrective actions.

Although the NRC inspection plan was changed, we have continued to implement the baseline inspection program and have provided additional oversight by completing the modified engineering inspection in November 2001. Oversight beyond the baseline program also includes a January 2002 inspection to review the Entergy self-assessment.

We provided our planned inspection schedule through the first half of 2002 to the licensee in a November 16, 2001, letter; a copy of which is enclosed. We consider the NRC inspection program at Indian Point Unit 2 to be appropriate for a plant designated as a multiple degraded cornerstone facility. However, additional inspection changes may result following NRCs oversight process assessments.

Again, thank you for your letter and I trust that the information provided is responsive to your concern.

Sincerely,

/RA/

William D. Travers Executive Director for Operations

Enclosure:

As stated Mr. David A. Lochbaum January 4, 2002 Nuclear Safety Engineer Union of Concerned Scientists 1707 H Street NW Suite 600 Washington, DC 20006-3919

Dear Mr. Lochbaum:

In your letter of October 23, 2001, you questioned changes to NRC inspections at Indian Point Unit 2 referred to in our October 15th letter to Entergy. Entergys self-assessment efforts were presented to the NRC in a letter dated September 14, 2001, and included plans to perform a comprehensive evaluation by an independent team of 28 people over a three week period.

The results of this assessment, which was subsequently completed in October, are to be used by Entergy to evaluate the effectiveness of corrective actions and to revise the current performance improvement plan.

The NRC considered the changes to our inspection plans, which involved modifying an engineering team inspection and rescheduling a problem identification and resolution (PIR) team inspection, to be prudent in light of the potential benefits to be gained from an extensive self-assessment. The NRC will assess the effectiveness of Entergys self-assessment activities in future inspections by evaluating the extent to which the licensee was able to diagnose problems and develop and implement appropriate corrective actions.

Although the NRC inspection plan was changed, we have continued to implement the baseline inspection program and have provided additional oversight by completing the modified engineering inspection in November 2001. Oversight beyond the baseline program also includes a January 2002 inspection to review the Entergy self-assessment.

We provided our planned inspection schedule through the first half of 2002 to the licensee in a November 16, 2001, letter; a copy of which is enclosed. We consider the NRC inspection program at Indian Point Unit 2 to be appropriate for a plant designated as a multiple degraded cornerstone facility. However, additional inspection changes may result following NRCs oversight process assessments.

Again, thank you for your letter and I trust that the information provided is responsive to your concern.

Sincerely,

/RA/

William D. Travers Executive Director for Operations

Enclosure:

As stated Distribution: See next page DOCUMENT NAME: G:\\BRANCH2\\2NDREVL1.WPD Package: ML013180443 After declaring this document An Official Agency Record it will/will not be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP RI/DRP RI/ORA EDO NAME LHarrison/LHarrison PEselgroth/PWE BHolian/BEH HMiller/HJM WTravers DATE 11/5/01 11/5/01 11/7/01 11/14/01 01/04/02 OFFICIAL RECORD COPY

Distribution:

W. Travers, EDO C. Paperiello, DEDMRS W. Kane, DEDR P. Norry, DEDM J. Craig, AO S. Burns, OGC S. Collins, NRR G20010499 LTR-01-0585 H. Miller, RI A. Blough, RI B. Holian, RI P. Eselgroth, RI