April 3, 2000 ORGANIZATION:
Nuclear Energy Institute
SUBJECT:
SUMMARY
OF MEETING WITH THE NUCLEAR ENERGY INSTITUTE (NEI) ON INDUSTRYS COMMENTS ON THE DRAFT GENERIC AGING LESSONS LEARNED (GALL) REPORT - ELECTRICAL EQUIPMENT On March 29, 2000, representative of NEI met with the Nuclear Regulatory Commission (NRC) staff in Rockville, Maryland, regarding the industrys comments on Chapter VI, Electrical Components, of the draft GALL report, dated December 6, 1999. By letter dated March 27, 2000, NEI has provided their written comments for discussion at this meeting. A list of meeting attendees is attached.
Chris Grimes of the staff opened the meeting by discussing his expectations. He indicated that the GALL report should contain as much technical information as practical and should not be affected by process issues. Any controversial areas should be identified and worked separately. NEI asked whether an applicant is required to meet the programs described in the GALL report. The staff responded that the GALL report is a reference for the Standard Review Plan for License Renewal (SRP-LR). The SRP-LR will indicate that the programs in the GALL report are one acceptable way to manage aging for license renewal. An applicant may propose alternatives for staff review. NEI indicated that an applicant would have to address any components that are subject to an aging management review for license renewal for its plant but are not included in the GALL report.
The staff asked the industry to clarify certain of NEIs comments on the draft GALL report.
Based on the discussions, NEI indicated that the industry would consider revising its comments by taking the following actions:
1.
Consider the use of the term electrical cables and connections to be consistent with the 10 CFR 54.21(a)(1)(i) language.
2.
Consider the addition of a boric acid corrosion management program for electrical connectors.
3.
Look into submitting industry-developed reports that are referenced in the GALL report.
4.
Consider and develop the environmental qualification (EQ) program as an aging management program under the 10 CFR 54.21(c)(1)(iii) option, as appropriate.
5.
Clarify that Generic Safety Issue (GSI) 168 is limited to low-voltage instrumentation and control cables.
6.
Clarify that any changes in activation energy values should be justified.
April 3, 2000 7.
Reconsider NEI Comment Number 19 to add the Instrument Calibration Program.
8.
Delete last sentence on Page VI.A-6, that states: Due to the low dielectric... cables.
The staff indicated it would consider NEIs comments on the draft GALL report. NEI discussed that it will be developing an approach for submitting and discussing the industry comments to support the staff schedule for issuing the draft GALL report, SRP-LR, and NEI 95-10, Industry Guideline for Implementing the Requirements of 10 CFR Part 54 - The License Renewal Rule, for public comment in August of 2000. The staff encouraged NEI to continue to provide their comments on an expedited basis to support the aggressive schedule.
/RA/
Samson S. Lee, Sr. Materials Engineer Engineering Section License Renewal and Standardization Branch Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Project No. 690
Enclosure:
As stated cc: See next page April 3, 2000 7.
Reconsider NEI Comment Number 19 to add the Instrument Calibration Program.
8.
Delete last sentence on Page VI.A-6, that states: Due to the low dielectric... cables.
The staff indicated it would consider NEIs comments on the draft GALL report. NEI discussed that it will be developing an approach for submitting and discussing the industry comments to support the staff schedule for issuing the draft GALL report, SRP-LR, and NEI 95-10, Industry Guideline for Implementing the Requirements of 10 CFR Part 54 - The License Renewal Rule, for public comment in August of 2000. The staff encouraged NEI to continue to provide their comments on an expedited basis to support the aggressive schedule.
/RA/
Samson S. Lee, Sr. Materials Engineer Engineering Section License Renewal and Standardization Branch Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Project No. 690
Enclosure:
As stated cc: See next page Distribution:
See next page Document Name: C:\\Sum_329.wpd OFFICE LA RLSB RLSB:SC RLSB:BC NAME EHylton SLee PTKuo CGrimes DATE 04/03/00 04/03/00 04/03/00 04/03/00 OFFICIAL RECORD COPY
NRC MEETING WITH THE NUCLEAR ENERGY INSTITUTE ON LICENSE RENEWAL ATTENDANCE LIST MARCH 29, 2000 NAME ORGANIZATION DON FINDLAY CNS (CEOG)
CHARLES MEYER WOG/WESTINGHOUSE MICHAEL HENIG VIRGINIA POWER STEVE HALE FPL JOHN RYCYNA CNS DAVID LEWIS SHAW PITTMAN E. A. THOMPSON FPL TERRY PICKENS NORTHERN STATES POWER CO.
RAY BAKER SOUTHERN COMPANY BILL CORBIN VIRGINIA POWER HARRY BLAKE VIRGINIA POWER AL PAGLIA SCE&G ROBERT WHORTON SCE&G ERACH PATEL PECO ENERGY FRED POLASKI PECO ENERGY ROBIN DYLE INSERVICE ENGINEERING WINSTON LIU NRR/DRIP/RLSB KENNETH R. HENRY OMAHA PUBLIC POWER DISTRICT PHILIP A. DIBENEDETTO CNS PAUL SHEMANSKI NRC/NRR/DE/EEIB DOUG WALTERS NEI PETER J. KANG NRC/NRR/DRIP/RLSB ROBERT LOFARO BROOKHAVEN NATIONAL LABORATORY C. I. GRIMES NRC/RLSB JIT VORA NRC/RES/DET P. T. KUO NRC/RLSB JIM STRNISHA NRC/RLSB SAM LEE NRC/NRR/DRIP/RLSB PAUL COLAIANNI DUKE POWER ROSEMARY REEVES NUS-IS BILL HORIN WINSTON & STRAWN GARRY G. YOUNG ENTERGY OPERATIONS Enclosure
DISTRIBUTION:
Hard copy File Center PUBLIC RLSB RF N. Dudley, ACRS - T2E26 E. Hylton E-mail:
R. Zimmerman J. Johnson D. Matthews S. Newberry C. Grimes C. Carpenter B. Zalcman J. Strosnider R. Wessman G. Bagchi E. Imbro W. Bateman J. Calvo S. Peterson G. Holahan T. Collins C. Gratton B. Boger J. Peralta J. Moore J. Rutberg R. Weisman B. Poole M. Mayfield S. Bahadur A. Murphy D. Martin W. McDowell S. Droggitis RLSB Staff A. Thadani M. Federline C. Julian R. Gardner D. Chyu M. Modes J. Vora
NUCLEAR ENERGY INSTITUTE (License Renewal Steering Committee)
Project No. 690 cc:
Mr. Dennis Harrison U.S. Department of Energy NE-42 Washington, D.C. 20585 Mr. Ricard P. Sedano, Commissioner State Liaison Officer Department of Public Service 112 State Street Drawer 20 Montipelier, Vermont 05620-2601 Mr. Douglas J. Walters Nuclear Energy Institute 1776 I Street, N.W.
Washington, DC 20006-3708 DJW@NEI.ORG National Whistleblower Center 3238 P Street, N.W.
Washington, DC 20007-2756 Mr. Garry Young Entergy Operations, Inc.
Arkansas Nuclear One 1448 SR 333 GSB-2E Russellville, Arkansas 72802 Mr. James P. Riccio Public Citizens Critical Mass Energy Project 211 Pennsylvania Avenue, SE Washington, DC 20003 Mr. Robert Gill Duke Energy Corporation Mail Stop EC-12R P.O. Box 1006 Charlotte, NC 28201-1006 Mr. Charles R. Pierce Southern Nuclear Operating Co.
40 Inverness Center Parkway BIN B064 Birmingham, AL 35242 Carl J. Yoder Baltimore Gas and Electric Company Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway NEF 1st Floor Lusby, Maryland 20657 Chattooga River Watershed Coalition P. O. Box 2006 Clayton, GA 30525 Mr. David Lochbaum Union of Concerned Scientists 1616 P. St., NW Suite 310 Washington, DC 20036-1495 Mr. Paul Gunter Director of the Reactor Watchdog Project Nuclear Information & Resource Service 1424 16th Street, NW, Suite 404 Washington, DC 20036