LR-N03-0519
Download: ML033570218 (3)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 DEC 1 5 2003 o Nuclear PSEG LLC LR-N03-051 9 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT 2 DOCKET NO. 50-311 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 2 Technical Specifications, the operating statistics for November 2003 are being forwarded.

Sincerely, Salem Plant Manager Attachments C Distribution 95-2168 REV. 7/99

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 12/11/03 COMPLETED BY: F. Todd TELEPHONE: (856) 339-1316 Reporting Period November 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 1131 Maximum Dependable Capacity (MWe-Net) 1092 Month Year-to-date Cumulative No. of hours reactor was critical 121 6674 127090 No. of hours generator was on line (service 90 6611 123569 hours)

Unit reserve shutdown hours O o 0 Net Electrical Energy (MWH) 39190 7244369 126433344 UNIT SHUTDOWNS NO. DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS) (1) SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 3 11/01/03 S 630 Hrs. C 4 Refuel Outage 11/27/03 (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic TriplScram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other

DOCKET NO.: 50-311

'UNIT: Salem 2 DATE: 12/11/03 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summarv Of Monthly Operatinq Experience

  • Salem 2 entered the month in a refueling outage and was placed back on-line on November 27.
  • At the end of the month, Salem 2 completed 3 days of continuous on-line operation.