August 2003 Monthly Operating Report for Salem Unit 1
ML032671035
Person / Time
Site: Salem PSEG icon.png
Issue date: 09/15/2003
From: Fricker C
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N03-0393
Download: ML032671035 (3)


Text

I .

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 SEP 1 5 2003 o PSEG NuclearLLC LR-N03-0393 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT I DOCKET NO. 50-272 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 1 Technical Specifications, the operating statistics for August 2003 are being forwarded.

Operations Director Attachments C Distribution 96-2168 REV. 7jgg

DOCKET NO.: 50-272 UNIT: Salem 1 DATE: 919/03 COMPLETED BY: F. Todd TELEPHONE: (856) 339-1316 Reporting Period August 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 1130 Maximum Dependable Capacity (MWe-Net) 1096 A. __.

Month Year-to-aate oumulative No. of hours reactor was critical 732 5761 147949 No. of hours generator was on line (service 686 5714 143265 hours)

Unit reserve shutdown hours 0 0 0 Net Electrical Energy (MWH) 747523 6211583 146115549 UNIT SHUTDOWNS NO. DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION!

F=FORCED (HOURS) (1) SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 1 811103 F 58 hrs. A 4 500kv 1-5 Breaker

. Failure 813103 (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator TraininglLicense Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other

DOCKET NO.: 50-272 UNIT: Salem 1 DATE: 9/9/03 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience

  • Salem I was offline at the beginning of the month.
  • The unit was placed online on August 3, reaching 100% reactor power on August 4.
  • At the end of the month, Salem 1 completed 28 days of continuous on-line operation.