LR-N03-0258, May 2003 Monthly Operating Report for Salem Unit 1
| ML031690373 | |
| Person / Time | |
|---|---|
| Site: | Salem |
| Issue date: | 06/11/2003 |
| From: | Waldinger L Public Service Enterprise Group |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| LR-N03-0258 | |
| Download: ML031690373 (3) | |
Text
-'
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 JUN 1-1 2003 LR-N03-0258 O PSEG Nuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT I DOCKET NO. 50-272 In compliance with Section 6.9, ReporUng Requirements for the Salem Unit I Technical Specifications, the operating statistics for May 2003 are being forwarded.
Sincerely, Operations Director Attachments C Distribution 95-2168 REV. 7/99
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-272 Salem 1 6/6/03 F. Todd (856) 339-1316 Reporting Perod May 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)
Maximum Dependable Capacity (MWe-Net)
No. of hours reactor was critical No. of hours generator was on line (service hours)
Unit reserve shutdown hours Net Electrical Energy (MWH) 1130 1096 Month Year-to-date Cumulative 744 3623 145811 744 3623 141174 0
0 0
8269221 39033741 143807340 UNIT SHUTDOWNS NO.
DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTIONl F=FORCED (HOURS)
(1)
SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)
(1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other I - Manual 2 - Manual Trip/Scram 3 - Automatic TrplScram 4-Confinuaffon 5 - Other (Explain)
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-272 Salem 1 616/03 R. Ritzman (856) 339-1445 Summary Of Monthly Operatinn Experience
- Salem 1 started the month at approximately 79% power due to a 500kv line outage. Power was restored to approximately 100% on May 1.
- On May 3, power was reduced to approximately 68% due to another 500kv line outage (grass fire). Powerwas restored to approximately 100% laterthat day.
At the end of the month, Salem I completed 199 days of continuous on-line operation.