LR-N03-0118, February 2003 Monthly Operating Report for Salem, Unit 1
| ML030770767 | |
| Person / Time | |
|---|---|
| Site: | Salem |
| Issue date: | 03/11/2003 |
| From: | Waldinger L Public Service Enterprise Group |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| LR-N03-0118 | |
| Download: ML030770767 (3) | |
Text
PSEG Nuclear LLC P.O Box 236, Hancocks Bndge, New Jersey 08038-0236 MAR 1 1 2003 LR-N03-0118 O PSEG Nuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
'MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT I DOCKET NO. 50-272 In compliance with Section 6.9, Reporting Requirements for the Salem Unit I Technical Specifications, the operating statistics for February 2003 are being forwarded.
Sincerely, RAR Attachments C Distribution 95-2168 REV 7199
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-272 Salem 1 3/10/03 F. Todd (856) 339-1316 Reporting Period February 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)
Maximum Dependable Capacity (MWe-Net)
No. of hours reactor was critical No. of hours generator was on line (service hours)
Unit reserve shutdown hours Net Electrical Energy (MWH) 1130 1096 uuI *
-L nvonin T ear-1o-aale j
umuiative 672 1416 143604 672 1416 138967 0
0 0
736485 1575171
.141479137 UNIT SHUTDOWNS L.
L J
I J
(1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
NO.
DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/
F=FORCED (HOURS)
(1)
SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)
I t
I
DOCKET NO.: 50-272 UNIT: Salem 1 DATE: 3/10/03 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience
- Salem 1 entered the month at 100% reactor power.
- On February 22, a planned power reduction was taken for Turbine Control Valve Testing and a 500KV Line Outage. Power was restored to 100% on February 25.
- At the end of the month, Salem 1 completed 107 days of continuous on-line operation.