LR-N02-0189, April 2002 Monthly Operating Report for Salem Unit 2

From kanterella
Jump to navigation Jump to search
April 2002 Monthly Operating Report for Salem Unit 2
ML021650310
Person / Time
Site: Salem PSEG icon.png
Issue date: 05/15/2002
From: Garchow D, Todd F
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N02-0189
Download: ML021650310 (3)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 MAY 1 5 2002 LR-N02-0189 o PSEG Nuclear LILC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT 2 DOCKET NO. 50-311 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 2 Technical Specifications, the operating statistics for April 2002 are being forwarded.

Sincerely, D. F. Ghrchow Vice President - Operations RAR Attachments C Distribution 9

95-2168 REV. 7/99

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 05/10/02 COMPLETED BY: F. Todd TELEPHONE: (856) 339-1316 Reporting Period April 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 1131 Maximum Dependable Capacity (MWe-Net) 1092 Month Year-to-date Cumulative No. of hours reactor was critical 96 2150 114863 No. of hours generator was on line (service 96 2128 111466 hours)

Unit reserve shutdown hours 0 0 0 Net Electrical Energy (MWH) 100047 2336017 113157558 UNIT SHUTDOWNS NO. DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS) (1) SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 3 4/5/02 S 623 hrs. C 2 Refuel Outage 4/30/02 (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 05/10/02 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience

  • Salem 2 began the month at 100% power.
  • On April 4, during power reduction to begin the refueling outage, power was reduced from 92% to approximately 61% due to a 21 Steam Generator Feed Pump trip. The plant was shutdown later that day to begin the refueling outage.
  • At the end of the month, Salem 2 was in the refueling outage.