LR-N02-0188, April 2002 Monthly Operating Report for Salem Unit 1
| ML021650316 | |
| Person / Time | |
|---|---|
| Site: | Salem |
| Issue date: | 05/15/2002 |
| From: | Garchow D, Todd F Public Service Enterprise Group |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| LR-N02-0188 | |
| Download: ML021650316 (3) | |
Text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 MAY 1 5 200Z LR-N02-0188 o PSEG Nuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT I DOCKET NO. 50-272 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 1 Technical Specifications, the operating statistics for April 2002 are being forwarded.
Sincerely, D. F. Gt chow Vice President - Operations RAR Attachments C Distribution 95-2168 REV. 7/99
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-272 Salem 1 05/10/02 F. Todd (856) 339-1316 Reporting Period April 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)
Maximum Dependable Capacity (MWe-Net)
No. of hours reactor was critical No. of hours generator was on line (service hours)
Unit reserve shutdown hours Net Electrical Energy (MWH) 1130 1096 Month Year-to-date Cumulative 719 2721 136948 719 2641 132336 0
0 0
794998 2893127 134176525 UNIT SHUTDOWNS (1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
NO.
DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/
F=FORCED (HOURS)
(1)
SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)
- i. ______
.1 ____________
.I. _______
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-272 Salem 1 05/10/02 R. Ritzman (856) 339-1445 Summary Of Monthly Operatinq Experience Salem 1 began the month at 100% power.
On April 17, power was reduced to approximately 74% due to the 13A and 13B circulators being out of service. 13A circulator was out of service for planned maintenance. The 13B circulator waterbox became bio-fouled and was taken out of service for cleaning. Power was restored to approximately 100% on April 19.
"* On April 22, power was reduced to approximately 60% due to 12 Steam Generator Feed Pump being removed from service. Power was returned to 100% later that day.
"* At the end of the month, Salem 1 completed 48 days of continuous operation.