December 2002 Monthly Operating Report for Salem Unit 2
ML030230367
Person / Time
Site: Salem PSEG icon.png
Issue date: 01/14/2003
From: Waldinger L
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N02-0008
Download: ML030230367 (3)


Text

-- S Director - Operations RAR Attachments C Distribution 95-2168 REV 7199 PSEG Nuclear LLC P 0. Box 236, Hancocks Bndge, New Jersey 08038-0236 0 PSEG Nuclear LLC JAN 1 4 2003 LR-N02-0008 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555.

Gentlemen:

MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT 2 DOCKET NO. 50-311 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 2 Technical Specifications, the operating statistics for December 2002 are being forwarded.

Sincerely,

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-311 Salem 2 1/8/03 F. Todd (856) 339-1316 Reporting Period December 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1131 1092 Month Year-to-date Cumulative 744 7703 120416 744 7620 116958 0

0 0

834071 8367434 119188975 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS)

(1)

SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)

(1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 1/8/03 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience

"* Salem 2 began the month at 100% reactor power.

On December 15, power was reduced to approximately 46% for control valve testing and was returned to 100% later that day. Power remained at approximately 100% power for the rest of the month.

" At the end of the month, Salem 2 completed 228 days of continuous on line operation.