PSEG Nuclear LLC P 0 Box 236, Hancocks Bndge, New Jersey 08038-0236 0 PSEG Nuclear LLC JAN 1 4 2003 LR-N02-0007 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT I DOCKET NO. 50-272 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 1 Technical Specifications, the operating statistics for December 2002 are being forwarded.
Sincerely, Lon H. Waldinger Director - Operations RAR Attachments C Distribution
/j,4-95-2168 REV 7/99
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-272 Salem 1 1/8/03 F. Todd (856) 339-1316 Reporting Period December 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)
Maximum Dependable Capacity (MWe-Net)
No. of hours reactor was critical No. of hours generator was on line (service hours)
Unit reserve shutdown hours Net Electrical Energy (MWH) 1130 1096 Monmt YTear-to-uate i.umulalive 744 7960 142188 744 7855 137551 0
0 0
833318 8620568 139903966 UNIT SHUTDOWNS j ______
1 ___________
1 ________
.1 1 _________
1 __________________
(1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2 - Manual Trip/Scram 3 -Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
NO.
DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/
F=FORCED (HOURS)
(1)
SHUTTING COMMENT S=SCHLE(
SHD DOWN THE REACTOR (2) 4 4
I
-t t
I
DOCKET NO.: 50-272 UNIT: Salem 1 DATE: 1/8/03 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience
", Salem 1 entered the month at 100% reactor power.
" On December 21, power was reduced to approximately 62% due to a 500KV Line outage. Power was restored to 100% on December 22 and remained there for the rest of the month.
", At the end of the month, Salem 1 completed 48 days of continuous on-line operation.